Key Takeaways
- A quarter of headwinds, but volumes held: Pig iron EBITDA collapsed to 5–7% from a 29% peak, yet overall volumes did not fall much and demand is already improving into Q4.
- Oliver is the near-term volume catalyst: Trial production has started, sample supplies are out, and the ramp begins in February–March, adding 1,000–1,500 tons per month quickly, independent of the tractor cycle.
- Casting is operationally delevered, not broken: Solapur is running two foundries but selling the output of one, a cost drag that resolves when volumes reach 5,000 tons per month in 2–3 quarters.
- Cost relief is arriving with a lag: Blended coal cost is falling from $205 to $195 to $177 over the next two quarters, and own iron ore consumption from Bharat Mines has begun.
- What to watch next quarter: The pace of the Oliver ramp, whether Solapur volumes cross 5,000 tons per month, and any stabilization in pig iron prices as the coal-cost benefit flows through.
Pig Iron & Steel: The Margin Reset
- Pig iron EBITDA has collapsed to trough levels: Margins fell from 29% during the Ukraine-war price spike to 5–7% now, driven by an oversupply of pig iron from new producers who are not yet converting to steel.
- The problem is supply, not demand: Management argues that as the iron and steel cycle improves, producers will make steel rather than dump pig iron, tightening the market.
- Cost relief is coming from two directions: Blended coal cost is declining sequentially ($205 in Q3, $195 in Q4, $177 next quarter), and own iron ore from Bharat Mines has started flowing into consumption. A stronger dollar partially offsets the coal benefit.
- No immediate price recovery expected: Management sees no major increase in pig iron prices soon, so margin recovery depends on the cost side.
- Steel and tube volumes are normalizing: Q1 and Q2 were disrupted by sluggish markets and the ERP implementation during the ISMT merger. Q3 improved, and Q4 is expected in line or slightly better.
R. V. Gumaste: "It is oversupply problem, not demand problem. Iron and steel improves, they will make steel rather than dumping pig iron. All newcomers, substantial pig iron and they are not going fully into steel. So supply should -- situation should improve rather than the consumption side."
Casting: Volume-Led Recovery in Motion
- The Solapur cost drag is temporary: Running two foundries while selling the output of one is the primary reason casting profitability is lower. The fix is volume: once Solapur reaches 5,000 tons per month, both foundries begin generating profit. That is expected in 2–3 quarters.
- Tractor slowdown cost 15,000–20,000 tons: The subdued tractor industry was the main reason casting volumes disappointed. The company is developing alternative components to reduce this dependency.
- Oliver adds volume independent of tractors: Trial production has begun, sample supplies are out, and the ramp starts in February–March. Management expects 1,000–1,500 tons per month to load quickly, and this volume is not linked to a tractor market recovery.
- Commercial vehicles are a bright spot: Volumes are increasing, with at least 20% growth expected over the next couple of months. Earthmoving equipment demand remains steady and supportive.
- FY26 casting target: 1,75,000–1,80,000 tons: This builds from Solapur reaching 50,000–55,000 tons, Hospet adding another 5,000, and Oliver contributing. Order booking and components under development support the ramp.
- Market share is growing in critical items: The company is gaining share in block and head castings across auto, tractors, and earthmoving. It may be slightly losing share in housings, but Oliver (30,000 tons, mainly housings) is expected to reverse that.
- SG iron opens new end-markets: Work has begun on SG iron castings in addition to gray iron, which will unlock railways and defense sectors. The facility should be available within six months at Oliver and Solapur.
R.V. Gumaste: "One of the main reason is we are running 2 foundries in Solapur, whereas selling 1 foundry quantity. And that increases the cost substantially."
Oliver: The Next Leg of Volume Growth
- Trial production has started: Sample supplies from the Oliver plant have begun, and the ramp-up in production and sales is expected from February and March. Oliver should start contributing volumes from Q1 of next financial year.
- Quick-loading volume of 1,000–1,500 tons per month: Management expects this initial volume to load quickly, and it is not dependent on an improvement in the tractor market.
- Merger into KFIL planned: The company intends to merge Oliver into KFIL in the next financial year.
- Oliver is central to the casting doubling plan: The company aims to go from 1,35,000 tons of realized casting capacity to 2,70,000 metric tons per annum over the next three years. Oliver, with its 30,000 tons of mainly housing capacity, is a key piece of that ambition.
Renewables & Cost Structure
- Solar power is now at scale: Phase I and Phase II are commissioned, operating close to 69 megawatts out of 70-megawatt capacity.
- Wind power has been ordered: 12.6 megawatts of wind power is in the pipeline.
- Another 70–80 MW equivalent is planned within a year: This includes roughly 25 MW of wind (equivalent to 50 MW solar) plus 30 MW of solar, with a capex of about INR200 crores.
- Solar expansion beyond this is on hold: Management wants to expand to 200 MW DC but is closely watching government policies on power banking. Without at least one-day banking, further expansion is difficult, and battery storage is not yet viable.
- Oxygen enrichment is improving coal efficiency: The target is to improve to 135–140 kg, capturing another 10 kg of co-consumption benefit.
- Own iron ore consumption is ramping: Bharat Mines operations have started and iron ore is being consumed. Next year, the company expects to mine and utilize 2.0–2.5 lakh tons, up from 1.2 lakh tons, reaching 25–30% of total iron ore requirement.
R.V. Gumaste: "The solar expansion requires at least the bare minimum 1-day banking. Without that -- the monthly banking is the ideal, but without that, it is very difficult."
Iron Ore Mines: One Working, One Stalled
- Bharat Mines is operational: Iron ore is being moved and consumed, with utilization expected to reach 2.0–2.5 lakh tons next year.
- The second mine (Chitradurga) is effectively blocked: The mine is in a reserve forest or wildlife reserve forest and is not going to become operational soon. Management expects it will take a couple of years, and they are awaiting official communication from the government.
- The industry is exploring a workaround: There are discussions about whether the government might permit operating mines within a larger integrated block, but there is no clarity yet.
- The company will cautiously bid for more mines: Additional mine auctions are on the radar, but participation will be cautious.
R.V. Gumaste: "That mine has gone into the reserve forest or wildlife reserve forest, and it's not going to become operational."
Guidance & Commitments
| Commitment | Specifics | Timeline |
|---|---|---|
| Hot metal production | 7 lakh tons hot metal; saleable pig iron ~5.7–6.0 lakh tons | Next 12 months |
| Casting volumes | 1,75,000–1,80,000 tons (from ~1,26,000–1,28,000 last year) | FY26 |
| Tube volumes | Close to 2,00,000 tons (Baramati ~1,50,000 + Ahmednagar 40,000–45,000) | Next year |
| Solapur foundry breakeven volume | 5,000 tons per month, at which point both foundries generate profit | 2–3 quarters |
| Oliver volume ramp | 1,000–1,500 tons per month to load quickly; volumes from Q1 | February–March ramp; Q1 FY26 |
| Renewable capacity addition | ~70–80 MW equivalent (wind + solar), INR200 crores capex | Within 1 year |
| Own iron ore consumption | 2.0–2.5 lakh tons, reaching 25–30% of total requirement | Next year |
| Blended coal cost trajectory | $195 in Q4, then $177 | Q4 and next quarter |
| SG iron casting facility | Available at Oliver and Solapur, opening railways and defense | Within 6 months |
| Oliver merger into KFIL | Merger executed | Next financial year |
| Casting capacity doubling | From 1,35,000 to 2,70,000 metric tons per annum | Next 3 years |
| NSE listing | Work in progress | As early as possible |
Key Metrics
| Metric | Q3 FY25 |
|---|---|
| Revenue | Improved by 4% YoY, marginally better than Q3 last year |
| Pig iron EBITDA margin | ~5%–7%, down from 15%–16% in prior periods and 29% peak |
| Pig iron production | ~1,50,000 tons liquid pig iron, 3% less than Q3 last year |
| Casting production | 35,000 tons between 2 units, 19% higher than Q3 last year |
| Tube production | 52,465 tons, 23% higher than Q3 last year |
| Steel production | 48,800 tons, down 12% QoQ from 55,000 tons last year |
| Casting volumetric growth (9M FY25) | 9% YoY, with sales of ~1 lakh metric ton vs 91,000 last year |
| Pig iron cumulative sales growth (9M FY25) | ~26% higher YoY |
| Capacity utilization (pig iron) | 93% at Hiriyur plant due to maintenance; other 2 furnaces above 100% |
| Solar power capacity operational | 69 MW out of 70 MW commissioned; capex of ₹370 cr at ~₹3.8 cr per MW |
| Blended coking coal cost | $205 per ton in Q3; expected $195 in Q4 and $177 in the following quarter |
| Pig iron ex-works average price | ₹37,000–₹38,000 per ton, range of ₹32,000–₹45,000 across grades |
| Casting volume target (FY26) | ~1,70,000–1,75,000 tons, including ~15,000 tons from Oliver |
| Tube volume target (FY26) | ~2,00,000 tons, with Baramati at 1,50,000 and Ahmednagar at 40,000–45,000 |
| Renewable energy capex (next 12 months) | ~₹200 cr for additional ~70–80 MW equivalent (solar + wind) |
| Total capex guidance (FY26) | ₹500–600 cr, including ₹200 cr for renewable energy |