Key Takeaways
- Pig iron margin collapse is the central pain point: Contribution margins have shrunk from INR 10,000 to INR 3,000 per ton over 2-3 years, and management admits "we don't cover our costs" at current realizations.
- Casting and tubes are carrying the portfolio: Casting EBITDA margins sit above 15% on a favorable product mix, while tube volumes grew 24% YoY with margins largely retained despite a 7% realization drop from Chinese dumping.
- Consolidated profitability still grew: EBITDA rose from INR 195 crores to INR 214 crores and PBT grew 9.4%, driven by volume growth and cost management across the stronger segments.
- A capex cycle is underway across renewables, steel and foundry: Close to INR 200 crores on wind, another 25-30 MW of solar next year, a steelmaking project, and Oliver foundry expansion to 48,000 tons all signal a multi-year investment phase.
- What to watch next quarter: Whether pig iron realizations actually bottom as management hopes, the pace of casting volume ramp toward 16,000 tons per month, and any relief on the INR 45 crore sequential power cost step-up.
Pig Iron: The Margin Problem
- Demand-supply imbalance: Oversupply of pig iron in the market, no shortage of steel scrap creating more competition, and iron ore prices that have not dropped much while pig iron prices have come down very substantially.
- Margin trajectory: Contribution per ton collapsed from INR 10,000 to INR 3,000 over 2-3 years, a level management says does not cover costs. Efficiency projects like PCI and oxygen enrichment have not been enough to offset the pressure.
- Competitor behavior: Most players starting steel plants sell pig iron until they scale up to steel, so they keep selling even at negative margins rather than closing capacity. Management sees the solution as moving to high value-added products, not waiting for competitors to exit.
- Recovery expectation: Management expects to recover to 10%+ EBITDA on pig iron through integration work (coke oven, power generation, efficiency improvements), but the timeline is tied to market conditions shifting.
- Strategic pivot: The plan is to make steel from at least one blast furnace, reducing dependency on pig iron sales, though this "takes a couple of years." Separately, the Hiriyur steel project upgrade (INR 125+ crores) will not be executed in the current low-realization environment.
Gumaste: "I can tell you that - we don't cover our costs."
Casting: The Margin Anchor
- Product mix shift: Casting sales realization held up despite the commodity downturn because of a deliberate shift toward high-value castings for auto and tractor segments, plus new product development. EBITDA margins are above 15%.
- Volume trajectory: Q1 saw some industry drag; tractor segment picked up from May/June, but extended monsoon affected moving equipment (minus 6%). Some volume was routed to Oliver (5,000 tons). As of October/November, all lines are loaded and volumes are increasing.
- Targets: Expect to reach 16,000 metric tons per month very shortly; targeting 160,000-170,000 tons this year and close to 2 lakh tons next year.
- Oliver foundry: Started production and sale of close to 5,000 tons; expected to do 15,000-16,000 tons going forward. In process of merging Oliver with KFIL. Board approved INR 100 crores investment over the next year to take capacity to 48,000 metric tons per annum, subject to environmental clearance.
Gumaste: "We are definitely above the 15% EBITDA margins in casting business and quite healthy, and we are catching up with the volume sales in castings."
Tubes: Volume Growth, Price Pressure
- Volume up, realization down: Tube volumes grew 24% YoY but realization dropped 7% due to commodity pressure and Chinese dumping. Despite this, margins have been retained to a great extent.
- Capacity expansion: Seamless tube operations already ramped to a 2 lakh ton operating level; debottlenecking measures should deliver another 10-12% next year. Management is looking to produce bigger seamless tubes and ramp to 3 lakh metric tons "in the coming year."
- Tender wins: Won some tenders in tube which will help load mills fully.
- Volume outlook: Look forward to seeing 200,000 tons very close to this year; another 10% attempt to go up next year before adding a bigger-size seamless tube manufacturing facility.
Power Costs & Renewable Energy
- Sequential cost step-up: Power cost rose by INR 45 crores sequentially due to seasonal effects (more rains, less solar generation), government tariff changes, and higher production volumes (tube production up 33%).
- Wind investment: Commissioning close to 20 MW of wind by end of this year; investing close to INR 200 crores.
- Solar investment: Will continue to invest another 25-30 MW for solar, realized next year.
- Policy-driven shift: Government of Maharashtra changed time slots; only 52% of power consumption can be from solar, forcing a shift in renewable strategy from solar to wind.
- Renewable target: Will keep adding more renewable capacity for at least 2-3 years to reach 65% of power from renewable energy.
Gumaste: "We cannot ask the rain god to stop. He will play his role."
Steel & Other Projects
- Steel project: Will start the steel project; down the line after 2 years, expect 3.5 lakh tons of pig iron going into steel making. Plan to upgrade the Hiriyur steel project so that in spite of one furnace going for steel, the company will continue to have 5 lakh tons of pig iron production.
- Steel segment performance: Sales realization down, sales value dropped close to 3% for the quarter.
- Copper and mines: Look forward to cutting costs and operationalizing mines; continue to pursue copper projects.
- NSE listing: Update on NSE listing progress was deferred to later in the call.
Segment Profitability & Analyst Pushback
- Current operating levels: Casting and tubes at 15-16% EBITDA; pig iron at 6-7% EBITDA currently. When asked if 6-7% is steady-state for pig iron, management pushed back, saying they expect recovery to 10%+, not steady state at 4-7%.
- Tube margin levers unquantified: An analyst asked for quantification of margin contribution from operating leverage, product mix (OCTG high-value tubes), backward integration, and resolution of Chinese dumping to achieve 14-16% EBITDA margins. Management gave a general answer about doing well and pursuing value addition but did not quantify or address the specific levers.
- Pig iron spread question deflected: Asked whether the spread on pig iron is negative or positive, management said "the effort to keep them positive is always there" but then stated "we don't cover our costs," avoiding a direct yes/no.
- Bottom not called: Asked whether this quarter would be the last for low realizations, management did not give a timeline or confirm a bottom, only described the price decline from INR 68,000 to half.
Gumaste: "Typically, you have seen unless the whole market changes hands forth. But otherwise, I think we should expect to get about 10% back into pig iron."
Guidance & Commitments
| Commitment | Specifics | Timeline |
|---|---|---|
| Casting volumes | Reach 16,000 metric tons per month; 160,000-170,000 tons this year; close to 2 lakh tons next year | "Very shortly" / FY26 / FY27 |
| Tube volumes | 200,000 tons this year; another 10% next year; seamless ramp to 3 lakh metric tons | FY26 / FY27 / "coming year" |
| Pig iron EBITDA recovery | Recover to 10%+ EBITDA from current 6-7% | No date; conditional on market |
| Oliver foundry capacity | Expand from 28,000-30,000 to 48,000 metric tons per annum (INR 100 crores investment) | Over next 1 year, subject to environmental clearance |
| Wind power commissioning | Close to 20 MW of wind (INR 200 crores investment) | By end of this year |
| Solar power addition | Another 25-30 MW of solar | Next year |
| Renewable energy share | Reach 65% of power from renewable energy | Over at least 2-3 years |
| Steel project | Start steelmaking; 3.5 lakh tons of pig iron into steel | After 2 years |
| Hiriyur steel upgrade | INR 125+ crores upgrade | Deferred; will not execute in current low pig iron realization scenario |
Key Metrics
| Metric | Q2 FY26 |
|---|---|
| Total sales | ₹1,736 cr, vs ₹1,683 cr last year |
| EBITDA | ₹214 cr, vs ₹195 cr last year |
| H1 EBITDA | ₹427 cr, vs ₹383 cr last year |
| PBT | ₹126 cr, vs ₹115 cr last year, growth of 9.4% |
| H1 PBT | ₹256 cr, vs ₹219 cr last year, 16.8% higher |
| Pig iron external sales volume | 131,508 metric tons |
| Casting sales volume | 36,673 metric tons, slightly less than last year Q2 |
| Casting sales value | ₹456 cr, vs ₹458 cr last year, drop of 0.3% |
| Casting sales realization | ₹124.466 per kg, vs ₹123.653 per kg last year |
| Tube sales volume | 49,588 tons, vs 39,866 tons last year, 24% growth |
| Tube sales value | ₹565 cr, vs ₹478 cr last year, 18% growth |
| Tube sales realization | ₹104,690 per ton, vs ₹112,440 last year, drop of 7% |
| Steel sales value | ₹139 cr, vs ₹144 cr last year, drop of close to 3% |
| Steel sales realization | ₹71,055 per ton, vs ₹76,362 last year |
| Power cost as a percentage of sales | 8.5% |
| Hot metal production | 165,179 metric tons, of which 131,508 external sales, balance internal transfer |
| Casting segment EBITDA margin | above 15% |
| Pig iron segment EBITDA margin | 6% to 7%, under pressure |
| Pig iron contribution margin (gross level) | ~₹3,000 per ton, down from ~₹10,000 over last 2-3 years |
| PCI usage rate | up to 125 kg per ton of hot metal in MBF 1 and 2 |
| Oliver foundry production and sales (since start) | close to 5,000 tons, expected 15,000 to 16,000 tons going forward |
| Casting volume target FY26 | 160,000 to 170,000 tons, vs 132,000 last year |
| Tube volume target FY26 | very close to 200,000 tons, H1 volume 98,000 metric tons |
| Renewable power cost benefit FY26 | ₹70 cr to ₹80 cr total benefit expected |
| Wind mill capacity addition FY26 | ~16.8 MW (8 wind mills of 2.1 MW each), investing close to ₹200 cr |
| Hiriyur maintenance shutdown production loss | ~21,000 to 22,000 tons, ~40 days stoppage |