Kilburn Engineering Ltd Guidance Report - SOIC x StockScans Report
as of Nov 2026
- FY27 order book - closing at ₹500 cr+ (1st April FY27)
Missed - At the Q3 FY26 call, management expected to open the order book on 1st April FY27 at 500 cr plus. The closing order book as on 31st March 2026 was ₹467 cr, below the ₹500 cr target.
- Kilburn standalone FY26 revenue - ₹450-500 cr
Delivered - At the Q3 FY26 call, management guided standalone FY26 revenue of 450-500 cr for Kilburn. FY26 standalone revenue came in at ₹448 cr, marginally below the guided range.
- M.E. Energy FY26 revenue - ₹100-105 cr guidance
Pending - On the Q3 FY26 call, management said it expects ₹100-105 cr revenue from M.E. Energy for FY26, within the ₹625-650 cr consolidated guidance "as we see on 31st March". FY26 has since closed, but no separate M.E. Energy FY26 revenue was disclosed; management declined subsidiary breakups on the Q4 FY26 call.
- FY25 standalone Kilburn revenue - ₹380 cr (later ₹300-350 cr)
Delivered - At the Q3 FY24 call, management confirmed confidence in clocking \~₹400 cr for Kilburn standalone in FY25; at Q3 FY25 this was revised to ₹300-350 cr. FY25 standalone revenue was ₹335 cr, within the revised range.
- FY24 order book - closing at ₹200 cr+ (later ₹260-280 cr)
Delivered - At the Q2 FY24 call, management expected a closing FY24 order book of ₹200 plus crores; at Q3 FY24 this became ₹260-280 cr for Kilburn plus ₹70-80 cr for M.E. Energy as on 31st March 2024. Consolidated order book as on 31st March 2024 was ₹284.7 cr.
- M.E. Energy and Monga Strayfield combined - ₹500 cr revenue in FY28
On track - At the Q2 FY27 call, the Chairman stated the two subsidiaries together can comfortably deliver over ₹500 cr of revenue in FY28, subject to getting orders. H1 FY27 subsidiary revenue roughly doubled from ₹73.4 cr to around ₹141.7 cr; no FY28 outcome yet.
- Monga Strayfield enclosure business - ₹50-60 cr in FY27, \~₹100 cr in FY27-28
On track - At the Q2 FY27 call, management expected the enclosure/data-center business to generate ₹50-60 cr in FY27 on current capacity, and roughly ₹100 cr in annual revenue in FY27-28 with Vertiv, which indicated a ₹90 cr requirement for the year. Q2 FY27 brought AI data centre orders of ₹147.9 mn, 10.8% of Q2 orders; no full-year FY27 revenue disclosed yet.
- Warrants conversion - ₹120-140 cr cash by FY26
Delivered - At the Q3 FY25 call, management stated warrant conversion in FY26 would bring ₹120-140 cr of cash; later revisions pointed to \~₹200 cr by June-July FY26 and remaining \~₹138 cr by May 2026. Q1 FY27 saw \~₹98 cr received via warrants converted at ₹425, fully subscribed, completing a \~₹300 cr fund raise in May 2026.
- FY26 CapEx - ₹25 cr (later ₹40-45 cr over 12 months)
Missed - At the Q4 FY25 call, FY26 CapEx was targeted "somewhere around ₹25 crores", described as "very fluid"; revisions raised this to ₹40-45 cr over 12 months and \~₹40 cr. CapEx for the first nine months of FY26 was around ₹5-6 cr, with CWIP of ₹4.63 cr at FY26-end and no full-year figure disclosed.
- Monga Strayfield FY26 revenue - ₹90-95 cr revised
Partial - At the Q4 FY25 call, management guided Monga Strayfield top line to ₹90-110 cr for FY26, revised to ₹90-95 cr by end-March at Q3 FY26. The FY26 outcome was never disclosed; at Q4 FY26 management cited Monga Strayfield execution delays expected to even out by H1 FY27.
- M.E. Energy revenue - ₹100 cr+ in FY25 (later ₹120 cr, then ₹100-110 cr)
Partial - At the Q4 FY24 call, management guided M.E. Energy FY25 revenue at "definitely would be more than ₹100 crores", raised to ₹120 cr at Q1 FY25, then ₹100-110 cr at Q3 FY25. Reported FY25 revenue was ₹77 cr, with actual execution close to ₹95 cr, netted off against intercompany work for Kilburn.
- Nuclear orders - significant orders in 2-3 years from FY25
Delivered - At the Q1 FY25 call, management expected "significant orders to come through in the next two, three years from the nuclear space". Nuclear order book reached ₹50 cr by Q4 FY25, with NPCIL and Heavy Water Board orders won by Q3 FY26 and ₹60.3 cr by Q4 FY26.
- Cement sector entry - first order by FY25, large WHR orders by FY27
Partial - At the Q4 FY24 call, management said they were entering the cement industry "this year" and hoped to "open our account", later hoping for one or two large cement WHR orders of ₹70-80 cr each by FY27. The first order came in Q1 FY25 from Shree Cements, a repeat ₹17.7 cr order followed in Q2 FY26, and by Q2 FY27 M.E. Energy had only qualified to quote for a cement WHR system.
- Granules India order - commercial execution after pilot completion
Missed - At the Q4 FY25 call, management expected the ₹70-odd-crore Granules India order, on hold pending pilot completion, to move to commercial execution, with the pilot "hopefully in the next three, four months should get completed". By Q4 FY26 the order was "still at the same level, status quo", with no further update in Q1 or Q2 FY27.
- Exports - 30-40% of revenue (medium/long-term)
On track - At the Q2 FY26 call, Director Khaitan said Kilburn's export share should rise from \~15% of revenue historically to 30-40%, reiterated at Q4 FY26 as 30-40% of revenue from exports. At the Q3 FY26 webinar (Dec 2025), management expected \~30% export turnover for FY26, with \~₹70 cr of the \~₹300 cr standalone closing order book export-related.
- NSE listing - timeline 6-8 months from Q1 FY26
Partial - At the Q1 FY26 call, management said NSE listing paperwork was underway, expected to take "maybe 6 to 8 months". By Q2 FY26 the Board had approved applying, with no timeline given, and no listing was completed as of Q2 FY27.
- Net debt-free by end of FY25
Missed - At the Q1 FY25 call, management stated "we should be in a comfortable position net debt free by end of the year, unless any other acquisition opportunity comes up". FY25 ended with consolidated cash flow from operations negative ₹10 cr, short-term borrowing rose from ₹27 cr to ₹40 cr in Q2 FY26, and net debt-free status came only after the \~₹300 cr fund raise in May 2026.
- Kilburn East End JV - ₹50 cr order in first year (FY27)
Pending - At the Q3 FY26 call, management expected the new JV Kilburn East End Private Limited to get an order in the range of ₹50 cr in its first year, FY27, and execute it. The JV was incorporated on 28th January 2026; as of Q2 FY27 it would be placing the Middle East high-margin order, with no disclosed order value yet.
- Monga Strayfield enclosure expansion - ₹25 cr CapEx, ₹120-150 cr revenue potential
On track - At the Q2 FY27 call, management announced Board approval for a ₹25 cr investment at Monga Strayfield's Pune facility over 6-9 months, expanding capacity for enclosures, cabinets and engineered assemblies, supporting annual revenue potential of ₹120-150 cr. The expansion was under planning at Q1 FY27 and Board-approved at Q2 FY27; no completion yet.
- FY28 revenue - ₹1,000 cr (20-25% CAGR)
On track - At the Q1 FY26 call, management set a vision to be a "1000-crore company by 2028", reiterated at Q3 FY26 and Q4 FY26. At Q1 FY27 the Chairman said no FY28 guidance had been given, then at Q2 FY27 reaffirmed 20-25% CAGR on the \~₹620 cr FY26 base by FY28, with FY27 tracking at ₹600-650 cr.
- FY27 EBITDA margin - 20%+ (later 22-23%)
On track - At the Q4 FY26 call, management guided FY27 EBITDA margins of 20% plus, "looking at maintaining margins of 22%, 23%", reiterated at 20% at Q1 FY27; at Q2 FY27 guidance was reset to around 20% blended, declining quarterly specifics. H1 FY27 consolidated EBITDA margin was 18.9%, below the 20% floor.
- FY27 order intake - ₹800 cr+
On track - At the Q4 FY26 call, management targeted group order intake of \~₹800-1,000 cr for FY27, reiterated at Q1 FY27 and Q2 FY27. FY27 inflows were \~₹190 cr till Q1 FY27 plus ₹136 cr of Q2 orders - about ₹326 cr in H1 FY27 against the ₹800 cr target.
- FY27 consolidated revenue - ₹800 cr (later ₹700 cr, then ₹600-650 cr)
On track - At the Q2 FY26 call, management expected \~₹650 cr for FY26 and 25% growth on that for FY27, restated as ₹800 cr at Q3 FY26; this was revised to around ₹700 cr at Q1 FY27 and around ₹600-650 cr at Q2 FY27. H1 FY27 consolidated revenue was ₹270.1 cr, down 4.5% YoY, with Q2 revenue of ₹153.1 cr.
- Saravali brownfield expansion - CapEx ₹25-30 cr, completion by March 2026
Partial - At the Q1 FY26 call, management announced Board in-principle approval for the Saravali unit brownfield expansion with CapEx \~₹30 cr and a timeline of "March 2026 approximately"; revisions moved completion to end Q2 FY27, six-to-eight months out, end October 2026, and Q3-early Q4 FY27. Work commenced in Q3 FY26, and as of Q2 FY27 the \~₹25 cr standalone CapEx was "well on track" for commissioning by December 2026.
- FY26 order intake - ₹600-700 cr (later ₹500-600 cr)
Delivered - At the Q4 FY25 call, management expected FY26 order intake of ₹600-700 cr, based on 20-25% conversion of the ₹3,000 cr+ pipeline; at Q1 FY26 Khaitan reiterated 500-600 cr. FY26 order inflows were \~₹600 cr.
- FY26 EBITDA margin - 22-23% (later 26%, then 22-23%)
Delivered - At the Q4 FY25 call, management guided consolidated EBITDA margins of 20-22%, raised to \~23% at Q1 FY26; Q2 FY26 saw a 26% close expectation before reverting to 22-23% at Q3 FY26. FY26 consolidated EBITDA margin was 25.13%, above the 22-23% range.
- FY26 consolidated revenue - 50% growth (\~₹650 cr)
Delivered - At the Q4 FY25 call, management guided \~50% consolidated top line growth for FY26, roughly ₹675-700 cr, reiterated through the year until Q3 FY26 narrowed it to ₹625-650 cr. FY26 consolidated revenue was ₹629 cr, within the revised range.
- M.E. Energy Phase 2 expansion - completion by March 2025
Partial - At the Q2 FY25 call, management stated M.E. Energy phase two CapEx would be completed by March 25; revisions pushed this to the middle of H2 FY26, with commencement only in Q3 FY26 after delays. As of Q2 FY27 the Pune expansion was under process/getting commissioned, with completion expected by March 2027.
- Monga Strayfield acquisition - completion by December 2024
Partial - At the Q2 FY25 call, management stated the Monga Strayfield acquisition was in due diligence and expected to be completed by December end. The acquisition completed on 27th January 2025.
- Ambernath factory - ₹100 cr revenue capacity, operational by FY25
Delivered - At the Q1 FY25 call, management stated the new Ambernath facility had CapEx of \~₹22 cr with expected revenue of ₹100 cr, and would be "up and running in two to three months' time"; revisions set handover by end November 2024 and 100% capacity by June 2025. The factory was fully operational at 100% capacity by Q4 FY25, with ₹100 cr expected to be added to FY26 turnover.
- FY25 EBITDA margin - 20%+ (consolidated)
Delivered - At the Q4 FY24 call, management targeted consolidated EBITDA of 20% for FY25, reiterated as "over 20% to 21%" at Q1 FY25 and at Q2 FY25. FY25 consolidated EBITDA margin was 23.79%, above the guided floor.
- FY25 group order intake - ₹500 cr+
Delivered - At the Q4 FY24 call, management targeted group order intake of ₹500 cr plus for FY25, reiterated at Q1 FY25 and Q3 FY25. At the Q4 FY25 call, Kilburn's highest-ever intake was ₹493 cr with M.E. Energy adding ₹83 cr and Monga Strayfield also contributing, taking group intake past the target.
- FY25 consolidated revenue - ₹500 cr+
Missed - At the Q4 FY24 call, management targeted consolidated revenue of ₹500 cr plus for FY25 with EBITDA of 20%, reiterated at Q1 FY25 and Q2 FY25; at Q3 FY25 the expectation was revised to ₹450-500 cr at group level on cleared hold orders and revenue spillover. FY25 consolidated revenue was ₹424.46 cr, below even the revised range.
- FY24 EBITDA margin - 18-20% (later 20%+)
Delivered - At the Q2 FY24 call, management expected to maintain EBITDA of 20% plus for FY24, resetting an earlier 17-18% target upward; at Q3 FY24 guidance was 18%-20% for KEL and 15%-20% for M.E. Energy. FY24 standalone EBITDA margin was 22.1% and consolidated 23.19%.
- M.E. Energy acquisition - completion by December 2023
Partial - At the Q2 FY24 call, management expected the acquisition of 100% of M. E. Energy Private Limited to be completed by December 2023, in the current quarter. The acquisition completed on 20th February 2024.
- FY24 revenue - ₹300 cr+ (later ₹290-300 cr standalone)
Delivered - At the Q1 FY24 call, management expected revenue "in the range of around ₹300 crores plus" for FY24, based on an open order book of \~₹220 cr on 1st April plus four to five months of orders, reiterated as "₹300 plus crores" at Q2 FY24; at Q3 FY24 standalone Kilburn was guided to ₹290-300 cr with M.E. Energy adding \~₹30 cr post-acquisition. FY24 standalone revenue was ₹293.2 cr, with consolidated revenue of ₹329.48 cr including M.E. Energy's \~₹36 cr.