Key Takeaways
- Execution hit by extended rains, not demand: Kerala HAM projects (₹4,000 cr order book) lost most of April–December to heavy rainfall, dragging Q3 revenue and tempering the Q4 outlook.
- Order inflow deliberately muted: 9M inflows were weak because EPC tenders are clocking 30–35% below normal levels; management refuses to bid at prices that risk future project viability.
- Margin compression from input costs, not competition: EBITDA slipped to 18–19% from ~20% as steel prices surged from ₹56,000 to ₹72,000 per tonne with no pass-through, and high-margin irrigation contribution fell from 35% to 23% YoY.
- Receivables improvement underway: Telangana irrigation receivables reduced from ₹900 cr to ₹650 cr after ₹450 cr in collections, though further work added to the balance.
- What to watch next quarter: Whether the ₹2,000 cr March order inflow target materializes, the pace of irrigation receivable resolution, and any margin recovery if input prices stabilize.
Execution & Revenue
- Rain disruption concentrated in Kerala: Kerala HAM projects saw rains from April through December, including 10 days in December; only 1–1.5 months of progress occurred post-December. Additional constraints: restrictions on working at 2 levels and night work stoppage.
- Mangalore project also affected: The ₹1,100 cr Bangalore-Mangalore project suffered from high rainfall and quarry permission delays because the environment clearance committee was not in place; permission now received and execution running at ~₹70 cr/month, but may need 5–6 months additional time.
- Q4 outlook tempered: Management will try to achieve last year's Q4 figures but "little bit bullishness is not there in this top line numbers."
- FY23 revenue guided to ₹3,500 cr: Expected to close between ₹3,000 cr and ₹3,500 cr, with FY24 target around ₹4,000 cr.
- Project milestones progressing: Magadi-Somwarpeth (Karnataka) 115 km of 164 km completed, targeting provisional completion (PCOD) by March end; Palani project PCOD submitted in September with 32 days bonus, NHAI yet to grant it.
- Irrigation completion target: All irrigation projects targeted for completion before elections (end of calendar 2023), because post-election policy direction is uncertain; completion is subject to receiving payments on time.
Jalandhar Reddy: "So little bit bullishness is not there in this top line numbers. But however, the next year is concerned, I think may not be so much rainy, definitely we'll do our best."
Order Inflow & Bidding Discipline
- Aggressive bidding environment: EPC tenders clocking below 30–35% levels; newcomers quoting lower and some have already failed on projects. Prominent players have come down to normal bidding levels.
- Price discipline is non-negotiable: Management unwilling to bid at levels that could cause future problems; "compromise on margin is not at all in our top of things because by compromising a margin is fairly the project will end up in NPA."
- March target: ₹2,000 cr would be "very happy": 22 tenders expected to bid in March, 10–12 bids to submit in February, ticket sizes ₹500 cr to ₹1,100 cr. Doubtful all 22 will actually bid due to repeated postponements.
- FY23 order inflow target at risk: The ₹4,000–5,000 cr target is "a little bit challenging" as of now; management ready to scale down rather than take orders at extra-low margins.
- Market normalization expected in 3–4 months: Management expects volatility to persist for another couple of 3–4 months before normalization.
- NHAI ordering catalyst: NHAI has only 5–6 months left to complete their order book position; large ordering activity expected before March 2023, similar to pre-election 2018. NHAI planning to award 14,000 km, though timeline uncertain due to land availability.
Jalandhar Reddy: "Sir, actually, this year -- I mean, March, if I'm happily getting around INR 2,000 crores, so I'm very happy. Even if I don't get also -- if I don't get a bad price, that is good. That is a major thing."
Margins
- Input cost pressure the primary drag: Steel prices rose steeply from ₹56,000–₹57,000 to ₹70,000–₹72,000 per tonne; cement costs also up. These could not be passed on.
- Irrigation mix shift structural, not temporary: Irrigation contribution to turnover fell from 35% in Q3 last year to 23% this Q3; Kerala project is ~65% steel and cement work (flyovers, viaducts, retaining structures, ₹600 cr of drain), amplifying input cost sensitivity.
- Sustainable EBITDA guided at 18–18.5%: 9-month EBITDA of 19.85% includes a ₹7 cr bonus and JV assignment deed in Q2; excluding those, it is ~18.5%. Management says current EBITDA is sustainable because irrigation will contribute only 20–25% max going forward.
- Highway margins reasonable at 15–16%: Management sees 15–16% EBITDA as reasonable for highway projects, maybe 1–2% less for fine-tuning on availability.
- Margin recovery conditional on input prices: If inflation is controlled and input prices stabilize, margins could match previous levels from Q4 onwards.
K. Venkatram Rao: "So that's why that our EBITDA, what we are giving today is that is sustainable EBITDA because the contribution of the irrigation will be to the extent of between 20% to 25% max only."
Irrigation & Receivables
- Telangana receivables improving: Combined debtors and unbilled reduced from ~₹900 cr in September to ~₹650 cr by December after ~₹450 cr in collections last quarter, though further work done increased the balance again.
- Payment streams differentiated: Package 4 is bank-funded, received ₹350 cr last quarter, no payment issues. Vattem and Package 3 are on budgetary support; government promised ₹50 cr/month, only last month missed.
- Old receivables expected closed by March: Based on government promise to release quantum every month.
- Vattem project resumed: Clearance has come and work has started after an earlier issue.
- Irrigation pipeline limited: Management will continue to focus but bidding scope is very limited; looking for HAM projects ₹700 cr and above, some at ₹1,500–₹2,000 cr slated before March.
Balance Sheet, Tax & Corporate
- Income tax provision of ₹34.2 cr: Reassessment proceedings initiated for FY2016-17 to 2021-22 following a March 2022 search operation under Section 132. Provision includes ₹24.75 cr tax + ₹9.45 cr interest, booked as a prudent measure; no demand raised as on date. Assessment expected to take 6 months to 1 year.
- No GST input credit issue: KNR getting almost 99% of input credit; sector has issues with subcontractor GST input but KNR does not face any such issue.
- HAM monetization under evaluation: Policy is not to accumulate HAM projects; inquiries are coming and being assessed; decision will be taken at the right time.
- Capex: ~₹110 cr done till date; FY23 expected to close at ₹140–₹150 cr. Existing capex will take care of all existing projects; next year's requirement not yet quantified.
- Subsidiary transfer completed: Equity shares in 3 subsidiaries (KNR Tirumala Infra, KNR Shankarampet Projects, KNR Srirangam Infra) transferred to CUBE Highways and Infrastructure.
- Chittoor-Thatchur HAM: Received appointed date on 25th January 2023.
K. Venkatram Rao: "But to be as a prudent policy, it's better to provide both income tax and the interest for the past year. That's what has happened."
Strategic Direction
- Railways entry in early stages: Discussions with 3 JV partners for composite qualification covering bridges, station building, and track construction; things not yet materialized.
- Metro projects under consideration: Looking at metro/elevated work independently if payments are not a problem.
- BOT/Toll projects a last resort: Considered only if unable to get orders from other areas; concession agreement not viewed as favorable.
- NHAI HAM contribution reduction still undecided: Proposal to reduce NHAI contribution from 40% to 20% is at a decisional stage, facing pressure not to reduce; draft concession agreements not modified as of now.
- Sector runway intact: Bharatmala expected to take another 4–5 years; highway sector work available for next 5–6 years. River linking program "has to come one day."
S. Vaikuntanathan: "Now the percentage, it is about allowing so many new entrants who can compete at a very lesser price than even the cost of the work project. That is creating problem. It's not that the work is not there."
Guidance & Commitments
| Commitment | Specifics | Timeline |
|---|---|---|
| FY23 revenue | Close between ₹3,000 cr and ₹3,500 cr | FY23 end |
| FY24 revenue target | Around ₹4,000 cr | FY24 |
| March order inflow | ~₹2,000 cr would be "very happy" | March 2023 |
| Irrigation project completion | All irrigation projects completed | Before elections (end of CY2023), subject to payments |
| Telangana old receivables | Closed based on government monthly releases | March 2023 |
| Magadi-Somwarpeth PCOD | Provisional completion | March end 2023 |
| Sustainable EBITDA | 18–18.5% range | Going forward |
| Margin recovery | Match previous levels if input prices stabilize | Q4 FY23 onwards |
| Market normalization | Volatility to subside | 3–4 months |
| Income tax assessment completion | Proceedings to conclude | 6 months to 1 year |
Key Metrics
| Metric | Q3 FY23 |
|---|---|
| Consolidated revenue | ₹874.9 cr, +2% YoY |
| Standalone revenue | ₹830.2 cr, +8% YoY |
| Consolidated EBITDA | ₹196.8 cr, vs ₹139.6 cr in Q3 FY22 |
| Consolidated EBITDA margin | 22.5% |
| Consolidated PAT | ₹108.3 cr |
| Standalone 9M EBITDA margin | 19.9% |
| Consolidated 9M EBITDA margin | 23.8% |
| Exceptional item: profit on sale of 3 subsidiaries | ₹137.97 cr |
| Provision for income tax (reassessment FY17–FY22) | ₹24.75 cr |
| Provision for interest on income tax | ₹9.45 cr |
| Outstanding order book | ₹8,100 cr, as of Dec 31, 2022 |
| Order book mix: EPC roads & HAM | 77%; irrigation 23% |
| Order inflow target for FY23 | ₹4,000–₹5,000 cr; probability of achieving ₹4,000 cr described as challenging |
| FY23 revenue guidance | ₹3,000–₹3,500 cr |
| FY24 revenue guidance | ~₹4,000 cr |
| Irrigation receivables | ₹650 cr as of Dec 31, 2022 (₹335 cr receivables + ₹315 cr unbilled), down from ₹900 cr in Sep 2022 |
| HAM project physical progress: Oddanchatram–Madathukulam | 85.6% |
| HAM project physical progress: Magadi–Somwarpeth | 68.9% |
| HAM project physical progress: Valanchery–Kappirikkad | 16.8% |
| HAM project physical progress: Ramanattukara–Valanchery | 14.3% |
| Bihar toll collection (Muzaffarpur–Barauni) | ₹11.6 cr in Q3; ₹33.5 cr in 9M FY23 |
| Consol cash balance | ₹145 cr as of Dec 31, 2022 |
| Standalone cash balance | ₹125 cr |
| Capex incurred till date in FY23 | ~₹110 cr |
| FY23 capex guidance | ₹140–₹150 cr |
| Sustainable EBITDA margin expectation | 18–18.5%; guidance 16–17% but could achieve 18–19% |
| NHAI bid pipeline (pan-India) | ~₹35,000 cr; management focusing on ~₹17,000 cr |
| NHAI planned award | 14,000 km |
| Irrigation revenue contribution in Q3 | ~23% of total revenue, ~₹190 cr |
| Irrigation order book | ~₹1,800 cr |
| Expected claims from Odisha project | ~₹72 cr from court decision |
| Bonus: Palani project PCOD submitted | 32 days of bonus per original completion date |
| Inventory | ₹187 cr as of Dec 31, 2022 |
| Retention money | ~₹241 cr as of Dec 2022 |
| Total receivables | ₹626–₹627 cr (₹335 cr irrigation + ₹267 cr HAM) |
| Mobilization advance | ₹134 cr as of Dec 2022 |
| Unbilled revenue | ₹490 cr |
| Trade payables | ₹211 cr |
| Steel price | ₹70,000–₹72,000/tonne currently; was ₹56,000–₹57,000 in Nov/Dec 2022 |
| Annual GST payments | ~₹275–₹300 cr |
| GST input recovery | ~99% |