KNR Constructions Ltd Q2 FY2024 Concall Summary

Source transcript PDF: https://assets.stockscans.in/docs/cokpveikqp11aykm72kir0gx.pdf

Key Takeaways


Quarterly Performance: The Margin Miss

Reddy: "the new orders which we are going to start that Mysuru two projects and that Guntur one project they have little bit lesser margins than what we have expected earlier, so little bit decline is there Sir that we have to accept."

Order Book & Inflow: Waiting on NHAI

Reddy: "Our inflow from NHAI is completely getting postponed as we are well aware about that."

HAM Portfolio: Equity, Execution & Monetization


Diversification: Beyond Roads

Reddy: "Diversification is not merely a strategic choice it is a commitment to the future."

Balance Sheet & Working Capital


Guidance & Commitments

CommitmentSpecificsTimeline
FY2024 revenue₹4,100–₹4,200 CroresFY2024
FY2025 revenue growthAt least 15% growth, higher if new orders materializeFY2025
H2 FY2024 order inflow₹3,000–₹4,000 CroresBalance of FY2024
Full-year order book target₹4,500 Crores plus across sectorsFY2024
New HAM project appointment datesReceived during Q4 FY2024Q4 FY2024
HAM equity infusion (old 5 projects)₹95 Crores in FY2024, ₹180 Crores in FY2025FY2024–FY2025
HAM equity infusion (new 3 projects)₹130 Crores in FY2025, ₹65 Crores in FY2026, ₹55 Crores in FY2027FY2025–FY2027
Kerala HAM execution~₹800 Crores (50% of outstanding) in H2 FY2024H2 FY2024
Irrigation outstanding execution₹400–450 Crores in H2 FY2024, balance in FY2025H2 FY2024–FY2025
Telangana L1 irrigation projectsLOI expected post-electionsPost state elections
Palamuru Package 4 decisionDirection known within 20 days of election result~December 2023
HAM project monetizationOne project possibly in 2024, another next year2024 / FY2025
NHAI awarding normalizationExpected in second/third quarter of next yearFY2025
Capex₹100–120 Crores (FY2024), ₹100–130 Crores (FY2025 normal)FY2024–FY2025

Key Metrics

MetricQ2 FY24
Consolidated revenue₹1,038 cr, +8% YoY
Standalone revenue₹941 cr, +11% YoY
Consolidated EBITDA₹232 cr vs ₹263 cr in Q2 FY23
Consolidated EBITDA margin22.3% vs 27.3% in Q2 FY23 (per an analyst's math)
Standalone EBITDA margin17.7% vs 20.1% in Q2 FY23 (per an analyst's math); includes one-offs of ~₹22.7 cr for project descope and electoral bonds
Consolidated PAT₹143 cr vs ₹99 cr in Q2 FY23
Standalone PAT₹99.9 cr vs ₹107.6 cr in Q2 FY23
Order book (outstanding)₹5,673.2 cr, 72% roads and 28% irrigation; 55% third-party, 45% captive HAM
Order book (incl. 3 new HAM projects)₹7,453 cr, 79% roads and 21% irrigation
Order inflow target (balance of FY24)₹3,000–4,000 cr
Revenue guidance (FY24)₹4,100–4,200 cr
HAM project physical progressMagadi-Somwarpet 78%, Oddanchatram-Madathukulam 97%, Ramanattukara-Valancherry 45%, Valancherry-Kappirikkad 49%, Chittor-Thatchur 30%
Equity invested in HAM projects₹457 cr out of ₹992 cr revised requirement as of Sep 30, 2023
Consolidated debt₹734 cr as of Sep 30, 2023 vs ₹611 cr as of Mar 31, 2023
Consolidated debt-to-equity0.24x vs 0.22x in Mar 2023
Standalone working capital days65 days vs 62 days in Jun 2023
Toll collection (Muzaffarpur-Barauni)₹9.43 cr in Q2 FY24; ₹21.12 cr in H1 FY24