Key Takeaways
- Profit surge driven by one-offs: Net profit grew 235% YoY to ₹334 crores, but this was powered by the Muzaffarpur Barauni settlement and an arbitration claim, not core operations.
- Core EBITDA flat, margin under pressure: EBITDA degrew 1% YoY to ₹165 crores; an analyst's math suggests adjusted EBITDA margin may be as low as 12.2%, though management disputes this.
- Order book is shrinking with no fresh inflow: The reported order book of ₹4,406 crores excludes ₹1,200 crores of stalled contracts; the company has won zero new orders this fiscal year so far.
- Irrigation receivables are a political hostage: ₹900 crores is stuck in Telangana, with ₹740 crores of billed work not even recorded by the client because a loan component is inaccessible.
- What to watch next quarter: Whether the promised ₹600 crores irrigation payment materialises in two months, whether NHAI tenders actually restart in January, and whether the AMRUT 2.0 project reaches its 15% revenue-booking milestone.
The Muzaffarpur Barauni Windfall
The quarter's headline numbers are dominated by a one-time settlement that closed out a troubled project. Consolidated revenue grew 87% YoY and EBITDA grew 226% YoY solely because of this item, which added ₹961.38 crores in revenue, a ₹342 crores EPC claim, and ₹49.67 crores in interest. The SPV repaid its entire debt obligation, toll collection was taken over by NHAI from 1st November 2024, and the company received ₹317.69 crores in cash including ₹142 crores of interest. An additional arbitration claim from an Orissa project contributed ₹28 crores in revenue and ₹43 crores in interest to other income. A ₹15 crores exceptional item included a ₹5.6 crores profit from a Patel KNR Infrastructures share buyback, partially offset by a ₹21 crores provision for receivables from CUBE Highways due to non-fulfilment of SPV conditions.
Reddy: "They say that the acquisition of land is not adequate. So until they achieve the 80% land position, they would like to hold these tenders. That is what NHAI is saying right now."
The Order Drought
The company has recorded no order inflow in the current fiscal year so far, and management acknowledges there is no considerable pipeline for new orders right now. The reported order book of ₹4,406 crores excludes ₹1,200 crores of contracts that lack an appointed date, implying a total potential book of ₹5,606 crores that will execute over one and a half to two years. Six HAM projects sit at various completion stages from 12% to 100%, with the company having invested ₹556 crores out of a revised ₹992 crores equity requirement. Management is targeting ₹6,000 crores to ₹8,000 crores of order inflow for the next year, with NHAI tenders expected to partially start from January and peak in February-March; the company has studied 80-85 NHAI tenders with project values ranging from ₹800 to ₹1,600 crores each. Two Maharashtra projects worth around ₹2,000 crores each are under discussion, one with Navayuga Constructions and one through an MOU with Patel Infra for pre-tender bidding, though the state election outcome creates uncertainty about whether these projects survive. Management expressed confidence in securing at least one Maharashtra project of about ₹2,000 crores, and at least ₹4,000 crores to ₹5,000 crores from the NHAI tenders studied.
Reddy: "So we were waiting this right election go because we don't know which government is going to come in Maharashtra. And so what would you say? Who's going to come? So if they like to continue then it is good otherwise if there is any shock that - they may scrap these projects because just before the election, they have already given LOAs on this."
The Telangana Irrigation Impasse
₹900 crores is outstanding from Telangana irrigation projects, of which ₹740 crores has been billed but the client has not recorded the bill because a loan component is inaccessible to them. Management describes the situation as "completely political" and is pursuing recovery through multiple channels: legal claims filed in court, discussions with the Chief Minister and ministry, and an expectation of receiving ₹600 crores in the next two months. The company cannot completely stop work despite the payment blockage because idling machinery would become a cost; it is continuing slow execution while the project sits at 85% completion. Separately, ₹435 crores is receivable from HAM projects but is not being drawn because the parent company has surplus cash flow; only ₹600 crores is certified receivables due.
Reddy: "Actually the irrigation, sir, it is completely political what is happening here is completely political."
Diversification That Failed
Management acknowledged that attempts to diversify beyond highways have failed across multiple sectors. The company examined solar, metro, and railways but "burned our hands" in all three, not even recovering tender money in some cases. A CETP project partnership with Mother Earth was terminated after management caught the partner showing wrong costs in maintenance; the valuation did not fit and the partnership was dissolved. The conclusion is stark: only the highway business has "little bit of life left" because of the company's domain expertise, and the strategy now is to stabilise through BOTs, tolls, and annuity projects rather than enter new sectors. A newly won ₹1,100 crores drinking water supply and sewage management project in Telangana under the AMRUT 2.0 scheme represents a cautious step into state-level water projects, with 25% central government funding confirmed.
Reddy: "I went in solar, I went in metro everywhere we burned our hands. Did not even get money of tender. The situation is that much worse over there. And even railways quoted us, railway is also worse. Little bit of life is left is because of our highway, because we know about everything."
HAM Portfolio: Sell-Down and Equity Needs
The company is actively discussing the sale of four HAM projects with prospective investors. One project, KNR, has already received PCOD and is expected to close by March; the other three are expected to receive PCOD in March, after which a further six months would be needed to complete any sale. Management expects to achieve better valuation than the previous deal. Equity infusion requirements stand at ₹200 crores for H2 FY25, ₹120 crores for FY26, and ₹116 crores for FY27. Two HAM projects are awaiting appointed dates, expected within two months, with environment clearance anticipated in one month. The company is also exploring BOT projects around ₹2,000 crores, where 30% equity would be required, and is in discussions with Adani and CUBE for potential partnerships, though management expressed a preference for EPC subcontracting with large players rather than equity partnerships where access to decision-makers may become difficult over a 20-30 year relationship.
Reddy: "That they were asking for that and I'm not a little bit picking on it, because there are big people so do a EPC, take-away your money and then that's better having 30 years, 20 years relations per BOT project is going to be a bit tough I think very big people now. So tomorrow we don't even get appointment to discuss anything further with them."
Revenue and Margin Trajectory
Standalone revenue for FY25 is guided to close between ₹3,500 crores and ₹3,600 crores, with H2 expected to deliver lower turnover than H1. Existing projects are 80% complete and all are expected to finish by March 2025. FY26 revenue is targeted at ₹4,500 crores, contingent on the order book reaching at least ₹5,000 crores to ₹6,000 crores, and the outcome depends heavily on the type of Q4 order inflow: EPC projects like MSRDC would enable faster execution in FY26, while HAM projects would require six months for financial closure and appointed date. On margins, management aims to exceed its 13-14% guidance but concedes it is very difficult to predict EBITDA margins on new orders; the first two quarters of FY26 carry no guarantee, while the second half is expected to be strong. An analyst computed adjusted EBITDA margin at 12.2% after stripping out one-offs; management did not confirm this figure, instead stating adjusted half-year EBITDA margin is 16.33%. Employee expenses rose this quarter due to ₹9.9 crores in variable pay to directors, with the normalised run-rate at ₹41-42 crores per quarter.
Reddy: "For first 2 quarters I am not guaranteeing, but the second-last two quarters, we will rock and we'll see that same kind of attitude."
Guidance & Commitments
| Commitment | Specifics | Timeline |
|---|---|---|
| Irrigation payment recovery | ₹600 crores expected from Telangana irrigation receivables | Next 2 months |
| Pipeline project milestone | Achieve 15% execution milestone, triggering revenue booking | Q4 FY25 |
| HAM project appointed dates | Two HAM projects to receive appointed dates; environment clearance in one month | Within 2 months |
| HAM project sale (KNR) | Sale of one HAM project with PCOD to close | By March 2025 |
| HAM project sale (remaining three) | Three projects to receive PCOD, then six months to sale | PCOD by March 2025; sale by September 2025 |
| Order inflow target | ₹6,000 crores to ₹8,000 crores of new orders | FY25 |
| FY25 standalone revenue | Close between ₹3,500 crores and ₹3,600 crores | FY25 |
| FY26 revenue target | ₹4,500 crores, provided order book reaches ₹5,000-₹6,000 crores | FY26 |
| NHAI tender participation | 80-85 tenders studied; awards expected to start partially | From January 2025, peaking February-March |
| Maharashtra project win | At least one project of ~₹2,000 crores from Maharashtra | Not specified |
| Andhra Pradesh tenders | Tenders expected; ₹20,000 crores of contracts may come up | By March-end 2025 |
| Amravati development bids | Bid calling expected | Within 2 months |
| HAM equity infusion | ₹200 crores (H2 FY25), ₹120 crores (FY26), ₹116 crores (FY27) | H2 FY25 through FY27 |
Key Metrics
| Metric | Q2 FY25 |
|---|---|
| Standalone revenue | ₹884 cr |
| Standalone adjusted revenue | ₹856 cr |
| Standalone EBITDA | ₹165 cr, 1% degrowth YoY |
| Standalone EBITDA margin | 18.6% |
| Standalone adjusted EBITDA margin | 16.12% |
| Standalone net profit | ₹334 cr, +235% YoY |
| Standalone adjusted PAT margin | 10.92% |
| Consolidated revenue | ₹1,945 cr, +87% YoY |
| Consolidated EBITDA | ₹870 cr, +226% YoY |
| Consolidated EBITDA margin | 44.7% |
| Consolidated PAT | ₹580 cr, +306% YoY |
| Total order book | ₹4,406 cr as of Sep 30, 2024; ₹5,606 cr including two HAM projects awaiting appointed date |
| Order inflow target | ₹6,000 cr to ₹8,000 cr for next year |
| Working capital days | 71 days, improved from 78 days as of Jun 24 |
| Consolidated net debt to equity | 0.33x as of Sep 30, 2024, vs 0.36x as of Mar 31, 2024 |
| Consolidated debt | ₹1,420 cr as of Sep 30, 2024, vs ₹1,258 cr as of Mar 31, 2024 |
| HAM project equity invested | ₹556 cr out of ₹992 cr revised requirement across eight projects |
| Irrigation receivables outstanding | ₹600 cr certified, ~₹1,000 cr including unbilled |
| Arbitration claim received (Orissa project) | ₹28 cr in revenue, ₹43 cr interest in other income |
| Exceptional item | ₹15 cr net charge: ₹5.6 cr gain on buyback, ₹21 cr provision for CUBE receivables |
| Muzaffarpur Barauni settlement received | ₹317.69 cr, including ₹142 cr interest on unsecured loan |
| Capex incurred | ₹4 cr in Q2, ₹13 cr in H1 FY25 |
| Standalone debt | ₹2.95 cr as of Sep 30, 2024 |
| Standalone cash | ₹247 cr; consolidated cash ₹460 cr; including investments ~₹520 cr |
| HAM project physical progress | Magadi–Somwarpet 87%, Oddanchatram–Madathukulam 100%, Ramanattukara–Valanchery 82%, Valanchery–Kappirikkad 84%, Chittor–Thatchur 77%, Marripudi–Somvarappadu 12% |
| FY25 standalone revenue guidance | ₹3,500 cr to ₹3,600 cr |
| Core EBITDA margin guidance | 13% to 14% |