Key Takeaways
- Worst-ever order drought: Management called this the worst time ever faced, with NHAI and state governments barely awarding work; the road order book has shrunk to 29% of the total, its lowest in a decade.
- Revenue set to shrink for 3–4 quarters: Low job inflow means turnover will be down until new orders, which take 9–10 months to convert, begin contributing; H2 FY26 guided at just ₹800–900 cr.
- One-offs hit margins: Standalone EBITDA margin fell to 10.9% in Q2, dragged by ₹10 cr in variable director pay and a ₹10 cr provision for the Ramanattukara project.
- Asset monetisation is the near-term catalyst: A deal to monetise four assets is at a very advanced stage, with an SPA draft circulated and closure expected by month-end.
- What to watch next quarter: Whether NHAI tenders actually restart in January as management hopes, the closure of the asset sale, and any progress on the ₹758 cr of stuck irrigation receivables.
The Order Inflow Drought
- NHAI has ground to a halt: Bids are being postponed, with 3–4 November tenders pushed to January due to PMO sanction and estimate approval issues; management hears tenders could start from January to March.
- State governments are absent: State governments are only "little little" coming forward with orders, and state payments carry risk; the company is bidding wherever there is a job, a sharp reversal from when it could choose its clients.
- Crowded bidding at the lower end: A very large crowd is competing for projects ₹1,000 cr and below due to changed norms, though NHAI’s tightening of RFP provisions favours proven contractors.
- Roads in a downcycle: The road order book is at its lowest share in 10 years, and total order book is lower than FY21 levels; management says it is "quite difficult to say anything" about when a sustainable upcycle might begin.
- Tie-ups as a workaround: The company is tying up with larger players like Adani, IRB and Cube for EPC work on their projects, rather than depending entirely on NHAI bids.
Reddy: "According to my inquiry, yes, sir, this is the right word, which you used, this is the worst time ever faced by us, such a situation."
Order Book & Bid Pipeline
- Order book composition: 41% mining, 29% road, 18% irrigation, 12% pipeline; 81% from third-party clients (76% state government, 3% central, 2% private), 19% captive HAM.
- Execution timeline: The current order book, excluding mining, will be executed over 1.5 to 2 years.
- Order inflow target: Aiming for ₹8,000–10,000 cr by FY26-end, split as NHAI ~₹5,000 cr (mainly HAM), state governments ~₹3,000–4,000 cr, and the balance from other areas.
- Recent wins: Two EPC projects won in Telangana: a ₹72 cr flyover at Kukatpally and a ₹459 cr multilevel flyover at Khajaguda and IIIT junctions.
- Bids in play: A ~₹1,200 cr mining bid placed in Odisha (not yet opened); participating in ~₹600 cr tenders in Greater Hyderabad, plus projects in MP, Maharashtra and Tamil Nadu.
- MSRDC order: For the Bhandara-Gadchiroli project where KNR was L1, a bank guarantee extension has been submitted; 60% of land to be awarded by November-end, balance in December; LOA may come in Q4, subject to CMO approvals.
- Diversification push: A new CEO has been appointed for solar and battery bids, and outside consultants have been hired to assist with bidding.
Irrigation: The Receivables Overhang
- ₹758 cr stuck: Irrigation receivables of ₹758 cr remain unpaid; the minister and finance minister have repeatedly promised payment within one month, but "every time he is saying that, but things are not happening."
- Loan renewal is the key: The loan part is closed; if renewed, things will be easy; otherwise state funds will pay in instalments.
- Execution winding down: Most irrigation work will be completed this year, with some portion of Package III spilling into next year; two smaller projects have land acquisition issues and have not taken off.
- Technical committee approval: A revised estimate order has been approved by a technical committee and will go to the government for approval.
- H2 irrigation revenue: Around ₹300–350 cr to be booked in H2, with the balance next year.
Reddy: "He said within 1 month the bill will be give. Every time he is saying that, but things are not happening. That is the major setback, which we are seeing there."
Project-Level Stress & Provisions
- Ramanattukara settlement: A settlement agreement with NHAI was signed on 16 October 2025; the company will construct the viaduct at its own cost and complete it by 20 February 2026, with a 90-day grace period; NHAI granted an extension of time without damage.
- Provision impact: ₹10 cr provision booked in Q2; the balance will be booked in Q3 and Q4 as the work is executed; completion targeted by February 2026.
- Debarment lifted: NHAI dropped all penalty and debarment proceedings; KNR Ramanattukara Infra and its promoter agreed not to participate in NHAI bids up to 30 November 2025, after which the company is free to bid again.
- Kushalnagara Package 5: Land acquisition is 85–88% complete, but 8–8.5 km are stopped because locals demanded service roads not provided in the greenfield highway design; all other portions are under progress.
- Provisional completion certificates: Received for both KNR Ramanattukara Infra (18 July 2025) and KNR Guruvayur Infra (17 July 2025).
Revenue & Margin Outlook
- H2 FY26 revenue: ₹800–900 cr expected; new orders won now will take 9–10 months minimum to contribute, with only 5–10% possible from Q4.
- Revenue breakdown by segment: Pipeline project: ₹300–350 cr this year, ~₹600 cr next year; Mysore two packages: ~₹300 cr in H2, ₹600–700 cr in FY27; irrigation: ₹300–350 cr in H2, balance next year.
- Mining revenue timeline: Development period work of ~₹90 cr in the next 1 year; operation period revenue initially ₹300–400 cr, starting 9–12 months from now.
- Margin target: New projects are being bid at 13–14% EBITDA margin.
- Bonus projects: A bonus on the Cheyyur-Vandavasi project has already been accounted; no further bonuses expected to be booked in H2 from the other three projects.
- Capex: Not expecting much; maximum ₹30–40 cr for the balance six months.
Asset Monetisation & Balance Sheet
- Four-asset deal at advanced stage: Monetisation of four assets is at a very advanced stage; an SPA draft has been circulated and closure is expected by month-end.
- NHAI monetisation backdrop: NHAI has lined up big-ticket asset monetisation as part of its ₹40,000 cr target for FY26 to recycle capital and fund new infrastructure.
- Return-to-peak timeline: Management expects a return to peak levels in about 4 quarters, "if our assumptions goes well, and our efforts could take a shape."
Reddy: "Some fake news, which is getting roamed around. It is not in the mainstream media. It is all in the thing. Even tomorrow if I win, they will blame me that I have not taken it like that, so kind of that. Things are not like that, sir."
Guidance & Commitments
| Commitment | Specifics | Timeline |
|---|---|---|
| Order inflow | ₹8,000–10,000 cr total, with ~₹5,000 cr from NHAI and ₹3,000–4,000 cr from state governments | By FY26-end |
| NHAI bidding restart | Free to participate after silent period ends; expecting big rally from NHAI | From December 2025; tenders January–March 2026 |
| H2 FY26 revenue | ₹800–900 cr | H2 FY26 |
| Ramanattukara completion | Viaduct construction at own cost, balance provisions in Q3 and Q4 | Complete by 20 February 2026 |
| Asset monetisation | Four-asset deal closure | By month-end (current month) |
| Mining revenue start | Development work ~₹90 cr in 1 year; operations revenue ₹300–400 cr initially | 9–12 months from now |
| Return to peak | Back on track to prior peak levels | ~4 quarters, conditional on assumptions and efforts |
| New project margins | 13–14% EBITDA margin target on new bids | On projects being bid now |
| Capex | Maximum ₹30–40 cr | Balance six months of FY26 |
Key Metrics
| Metric | Q2 FY26 |
|---|---|
| Consolidated revenue | ₹646 cr |
| Consolidated EBITDA margin | 29.8% |
| Consolidated PAT | ₹105 cr |
| Standalone revenue | ₹493 cr |
| Standalone EBITDA margin | 10.9% |
| Standalone PAT | ₹28 cr |
| H1 FY26 consolidated revenue | ₹1,259 cr |
| H1 FY26 consolidated EBITDA margin | 29.8% |
| H1 FY26 consolidated PAT | ₹228 cr |
| H1 FY26 standalone revenue | ₹976 cr |
| H1 FY26 standalone EBITDA margin | 12.2% |
| H1 FY26 standalone PAT | ₹79 cr |
| Total order book | ₹8,748 cr, 29% roads, 18% irrigation, 12% pipeline, 41% mining |
| Order inflow target for FY26 | ₹8,000 cr to ₹10,000 cr |
| Consolidated net debt to equity | 0.49x, vs 0.41x as of Mar '25 |
| Consolidated debt | ₹2,338 cr, vs ₹1,865 cr as of Mar '25 |
| Standalone debt | ₹74 cr |
| HAM projects equity invested | ₹698 cr out of ₹991 cr revised requirement |
| Irrigation receivables (incl. unbilled) | ₹1,350 cr from Telangana government |
| H2 FY26 revenue expectation | ₹800 cr to ₹900 cr (standalone, per management) |
| One-off employee cost (variable pay to director) | ₹10 cr |
| One-off expenditure for Ramanattukara Kerala project | ₹10 cr |