Key Takeaways
- Asset monetization cleans the balance sheet: All four HAM assets sold to Indus Infra Trust, slashing consolidated debt from ₹2,438 crores to ₹1,180 crores and net debt/equity from 0.49x to 0.22x.
- A forced pivot to city works: A ~19% YoY decline in national highway construction and reduced NHAI order inflow pushed KNR into Hyderabad city projects, a segment it frames as survival, not ambition.
- Order book hits a milestone at ₹16,000 crores, lifted by a ₹1,395 crore HMDA elevated corridor win, but the mix is shifting toward shorter-duration city and mining work.
- Margins under multi-front pressure: EBITDA is squeezed by war-linked input inflation, low equipment utilization, and rising overheads on a smaller turnover base; management refuses to guarantee a 13% FY28 exit.
- What to watch next quarter: Whether the ₹660 crore irrigation receivable actually lands in December, the appointed date for the Tamil Nadu flyover, and any progress on the Banhardih mine start.
The HAM Exit & Balance Sheet Reset
- Monetization complete: KNR Guruvayur Infra transferred in September (₹193 crores invested, ₹486 crores received) and KNR Ramanattukara Infra in October (₹226 crores invested, ₹549 crores received), closing out all four HAM asset sales to Indus Infra Trust.
- Debt nearly halved: Consolidated debt fell from ₹2,438 crores (March 2026) to ₹1,180 crores (September 2026), and net debt/equity improved from 0.49x as of March 2026 to 0.22x as of June 2026, driven by monetization proceeds.
- Standalone working capital stretched: Working capital days increased to 104 days from 78 days as of March 2026, reflecting the shift to city works where no mobilization advance is given and payments lag.
- Equity still to deploy: Additional ₹202 crores equity is required for four HAM projects (₹110 crores in H2 FY27, ₹85 crores in FY28), and a further ~₹510 crores may be needed for Chennai and Telangana NHAI HAM projects, with ~₹100 crores of that due by March.
- Receivables remain the overhang: Irrigation receivables stand at ~₹660 crores, primarily from Kaleshwaram Package 4, and HAM receivables at ₹330 crores; the Ministry of Finance has asked for billing details and management expects payment in a couple of weeks or by the first or second week of December.
The Strategic Pivot: Why City Works
- Forced, not chosen: Reduced order inflow from NHAI and state governments pushed KNR into Hyderabad city works (HMDA, GHMC) as a pattern change to sustain business through a lean highway-award cycle.
- Competition is thin for a reason: Most contractors avoid Hyderabad city projects because payments are delayed and no mobilization advance is offered; KNR sees this as an opportunity to bid at better prices, with less competition.
- Working capital is the trade-off: GHMC payments are already three to four months due, and management acknowledges capitals are blocking there, though it expects payment by this weekend or next week.
- The ₹1,400 crore HMDA win: Agreement time is almost a month, after which work can start, but land problems may limit initial progress to the 50% of the stretch that is already clear; meaningful execution expected only in Q4.
K. Jalandhar Reddy: "Focusing in city of Hyderabad works is that the reduced order inflow from NHAI and other state governments, which has forced us to enter the city works. As a pattern change, because these are pattern changings only because to improve the business as well to survive in the risky times."
Order Book & Pipeline
- Order book at ₹16,000 crores: The milestone was reached after the ₹1,395 crore HMDA elevated corridor win; excluding mining, the book will be executed over 3 to 3.5 years.
- FY27 inflow target: Management is targeting ₹4,000–5,000 crores of order inflow in H2 FY27, with most expected from highways; it has studied almost 20 to 28 projects recently.
- L1 status: Currently ~₹400 crores worth of projects sit in L1 position.
- Highway bids coming: HAM projects of ₹2,000–3,000 crores and above are expected to be bid in a couple of months; Andhra and Telangana tenders, including RRR in Hyderabad and Amaravati outer ring road, are expected in Q4 with ticket sizes above ₹3,000 crores, mostly HAM.
- Mining pipeline: Gevra mine bid to be placed by 1st or 2nd December; Banhardih mine expected to start in 4–5 months, with court pushing for an immediate start and high-level pursuance underway.
- MSRDC and railways: Old cancelled MSRDC tenders have resurfaced as new tenders; railways not being pursued aggressively because structural teams are fully occupied and recent bids opened at deeply negative levels.
Mining: The Next Leg, but Margins Are Thin
- Revenue yet to materialize: No mining revenue in H1 because the project had not started; Kusmunda mine clocked ~₹17 crores in October, targeting ~₹20 crores in November, with a FY28 turnover ambition of ~₹400 crores for Kusmunda.
- Banhardih could add another ₹300 crores in FY28 if it starts in Q1, but mobilization has not begun because land handover timing is unknown and equipment manufacturers are taking long to supply, so orders are being placed now.
- Capex is mining-heavy: Of ₹220 crores H1 capex, ₹180 crores went into mining assets; full-year FY27 capex is guided at ~₹400 crores, of which ₹300–320 crores is mining; Banhardih will require an additional ₹400–500 crores when it starts, taking total mine capex to ~₹1,000 crores for the two mines.
- Margins are survival-level: Management expects a net 5% profit from mining, describing it as a tough and competitive world where works were quoted just to make some value and stay comfortable.
- Depreciation watch: Equipment in the mine runs almost 20 hours a day; management took a five-year depreciation life for competitiveness but feels it is on the higher side; per-quarter depreciation is guided at ~₹30 crores for Q3 and Q4 FY27, with a six-to-seven-year assumption suggested.
K. Jalandhar Reddy: "It's been a tough and competitive world, just to make some value and just to make ourselves a little bit comfortable due to other those, these works were quoted."
Margin Pressure & the Guidance Gap
- Multiple headwinds converging: EBITDA levels have fallen due to war situation, dollar fluctuation, and inflation; overheads have increased while turnover is lower, and equipment utilization has been unutilized for longer periods, with 100% utilization not happening in the past two years.
- H2 margins seen flat to H1: Management expects a similar margin pattern in H2 FY27 as in H1, with no near-term relief from input price or overhead pressures.
- FY28 13% EBITDA not guaranteed: An analyst asked if 13% is doable; management declined to confirm, stating input prices and even food costs are rising, and more calculation is needed before committing.
- Equipment utilization turning: Management noted equipment is rolling back into action from upcoming days after two years where 100% utilization has not happened, a potential tailwind if sustained.
K. Jalandhar Reddy: "The 13% cannot guarantee, sir, because now not only the overhead that is increasing, it is the input prices that are getting changed. Even food prices have gone up. Everything has gone up."
Project-Level Execution & Stalled Starts
- Two HAM projects near completion: Magadi–Somwarpet at 92% and Marripudi–Somavarappadu at 94% physical progress; two Mysore–Kushalnagar packages are at 29% and 25%.
- Mysore–Kushalnagar land clarity: Earlier downsizing concerns have eased; most of the area is now clear except around 7–8 kilometers, which is expected in another two to three months; full project value is expected with only minor scope changes.
- Telangana HAM appointed date stuck on royalty: A zero-royalty GO issued during bid time was not communicated to the concerned department, blocking material movement; the Revenue Ministry has cleared it and the document is with the Chief Secretary; appointed date expected by first or second week of December.
- Tamil Nadu flyover: A government change triggered a committee review; the committee has recommended the project is required and the final meeting was held last week; appointed date expected in a couple of weeks.
- Irrigation winding down: Q2 irrigation revenue was only ₹10 crores because most projects are completed; only Package III has remaining work and land was only recently provided; H2 execution guided at ₹50–60 crores.
Capital Allocation & the Buyback Question
- Buyback is wanted but unfunded: Management is eagerly interested and calls current stock prices tempting, but cannot take the call due to capital requirements for mining projects, irrigation receivables, and city work working capital.
- Promoter-level funds are tight: A family settlement for the father and certain real estate purchases have created tightness at the promoter level, leaving very less funds available.
- No commitment on timing or mechanism: When pressed on whether a buyback could happen at the promoter level, tender level, or market level, management deflected to capital requirements and gave no clear answer.
K. Jalandhar Reddy: "Yes, actually, it's the right opportunity for us to take over certain stocks, because prices are tempting right now."
Guidance & Commitments
| Commitment | Specifics | Timeline |
|---|---|---|
| Order inflow | ₹4,000–5,000 crores | H2 FY27 |
| FY27 revenue | ₹2,200–2,300 crores | FY27 |
| FY28 revenue | ₹3,000 crores+ | FY28 |
| Mining revenue | ~₹100 crores | H2 FY27 |
| Irrigation execution | ₹50–60 crores from Package III | H2 FY27 |
| Pipeline execution | ~₹300 crores | H2 FY27 |
| Full-year capex | ~₹400 crores (₹300–320 crores mining) | FY27 |
| Banhardih mine capex | Additional ₹400–500 crores | When mine starts |
| HAM equity infusion | ₹117 crores | H2 FY27 |
| HAM equity infusion | ₹85 crores | FY28 |
| Chennai & Telangana HAM equity | ~₹100 crores of ₹510 crores total | By March 2027 |
| Irrigation receivable | Major portion of certified billings | By March 2027 |
| Irrigation payment | Some money expected | December 2026 |
| GHMC payment | Payment expected | By next week |
| Telangana HAM appointed date | Expected | First/second week of December 2026 |
| Tamil Nadu flyover appointed date | Expected | In a couple of weeks |
| Mysore–Kushalnagar balance land | Balance 8 km expected | In two to three months |
| Kusmunda mine FY28 turnover | ~₹400 crores | FY28 |
| Banhardih mine FY28 turnover | ~₹300 crores | FY28, if starts in Q1 |
| Depreciation | ~₹30 crores per quarter | Q3 and Q4 FY27 |
Key Metrics
| Metric | Q2 FY27 |
|---|---|
| Consolidated revenue | ₹600 cr |
| Consolidated EBITDA | ₹147 cr, margin 24.6% |
| Consolidated net profit | ₹102 cr |
| Standalone revenue | ₹477 cr |
| Standalone EBITDA | ₹44 cr, margin 9.2% |
| Standalone net profit | ₹281 cr, including exceptional profit of ₹292 cr from sale of KNR Guruvayur Infra |
| Adjusted standalone PAT (excl. exceptional item) | ₹30 cr |
| H1 FY27 consolidated revenue | ₹1,188 cr, EBITDA margin 20.5% |
| H1 FY27 standalone revenue | ₹914 cr, EBITDA margin 12% |
| Order book (as of Sep 30, 2026) | ₹16,355 cr, including recently won HAM and HMDA projects; mix 43% road, 10% irrigation, 5% pipeline, 42% mining |
| Order inflow target for H2 FY27 | ₹4,000–5,000 cr |
| Consolidated net debt to equity | 0.22x as of Jun 30, 2026, vs 0.49x as of Mar 31, 2026 |
| Consolidated debt | ₹1,180 cr as of Sep 30, 2026, vs ₹2,438 cr as of Mar 31, 2026 |
| Standalone working capital days | 104 days as of Sep 2026, vs 78 days as of Mar 2026 |
| Capex incurred in H1 FY27 | ₹220 cr, of which ~₹180 cr for mining assets |
| Full-year FY27 capex target | ~₹400 cr, of which ~₹300–320 cr for mining |
| Irrigation outstanding receivables | ~₹660 cr; total receivables with unbilled ~₹1,400 cr |
| Revenue guidance FY27 | ₹2,200–2,300 cr, maintained |
| Revenue guidance FY28 | ₹3,000 cr+, maintained |
| Mining revenue target for H2 FY27 | ~₹100 cr |
| Kusmunda mine FY28 revenue target | ~₹400 cr |
| Banhardih mine FY28 revenue target (if starts Q1) | ~₹300 cr |
| Depreciation expectation for Q3 and Q4 FY27 | ~₹30 cr per quarter |
| HAM project physical progress (as of Sep 30, 2026) | Magadi–Somwarpet ~92%, Marripudi–Somavarappadu ~94%, Mysore–Kushalnagar IV 29%, Mysore–Kushalnagar V ~25% |
| Equity infused in four HAM projects (as of Sep 2026) | ₹193 cr out of revised ₹396 cr requirement |
| Remaining equity for four HAM projects | ₹202 cr, to be infused ₹117 cr in H2 FY27 and ₹85 cr in FY28 |
| Additional equity requirement for Chennai and Telangana HAM projects | ~₹510 cr |
| Proceeds from KNR Guruvayur Infra monetization | ₹486 cr consideration on investment of ~₹193 cr |
| Proceeds from KNR Ramanattukara Infra monetization | ₹549 cr consideration on investment of ~₹226 cr |
| Withhold pending on three monetized assets | ~₹295 cr |
| Withhold expected on fourth monetized asset | ~₹130 cr |
| L1 projects as of call date | ~₹400 cr |
| Revenue split Q2 FY27 | Road EPC 28%, HAM 48%, irrigation 2%, back-to-back subcontract 21% |