KNR Constructions Ltd Q2 FY2027 Concall Summary

Source transcript PDF: https://assets.stockscans.in/docs/cku2osmltwhog2rpys5v6sh2.pdf

Key Takeaways


The HAM Exit & Balance Sheet Reset


The Strategic Pivot: Why City Works

K. Jalandhar Reddy: "Focusing in city of Hyderabad works is that the reduced order inflow from NHAI and other state governments, which has forced us to enter the city works. As a pattern change, because these are pattern changings only because to improve the business as well to survive in the risky times."

Order Book & Pipeline


Mining: The Next Leg, but Margins Are Thin

K. Jalandhar Reddy: "It's been a tough and competitive world, just to make some value and just to make ourselves a little bit comfortable due to other those, these works were quoted."

Margin Pressure & the Guidance Gap

K. Jalandhar Reddy: "The 13% cannot guarantee, sir, because now not only the overhead that is increasing, it is the input prices that are getting changed. Even food prices have gone up. Everything has gone up."

Project-Level Execution & Stalled Starts


Capital Allocation & the Buyback Question

K. Jalandhar Reddy: "Yes, actually, it's the right opportunity for us to take over certain stocks, because prices are tempting right now."

Guidance & Commitments

CommitmentSpecificsTimeline
Order inflow₹4,000–5,000 croresH2 FY27
FY27 revenue₹2,200–2,300 croresFY27
FY28 revenue₹3,000 crores+FY28
Mining revenue~₹100 croresH2 FY27
Irrigation execution₹50–60 crores from Package IIIH2 FY27
Pipeline execution~₹300 croresH2 FY27
Full-year capex~₹400 crores (₹300–320 crores mining)FY27
Banhardih mine capexAdditional ₹400–500 croresWhen mine starts
HAM equity infusion₹117 croresH2 FY27
HAM equity infusion₹85 croresFY28
Chennai & Telangana HAM equity~₹100 crores of ₹510 crores totalBy March 2027
Irrigation receivableMajor portion of certified billingsBy March 2027
Irrigation paymentSome money expectedDecember 2026
GHMC paymentPayment expectedBy next week
Telangana HAM appointed dateExpectedFirst/second week of December 2026
Tamil Nadu flyover appointed dateExpectedIn a couple of weeks
Mysore–Kushalnagar balance landBalance 8 km expectedIn two to three months
Kusmunda mine FY28 turnover~₹400 croresFY28
Banhardih mine FY28 turnover~₹300 croresFY28, if starts in Q1
Depreciation~₹30 crores per quarterQ3 and Q4 FY27

Key Metrics

MetricQ2 FY27
Consolidated revenue₹600 cr
Consolidated EBITDA₹147 cr, margin 24.6%
Consolidated net profit₹102 cr
Standalone revenue₹477 cr
Standalone EBITDA₹44 cr, margin 9.2%
Standalone net profit₹281 cr, including exceptional profit of ₹292 cr from sale of KNR Guruvayur Infra
Adjusted standalone PAT (excl. exceptional item)₹30 cr
H1 FY27 consolidated revenue₹1,188 cr, EBITDA margin 20.5%
H1 FY27 standalone revenue₹914 cr, EBITDA margin 12%
Order book (as of Sep 30, 2026)₹16,355 cr, including recently won HAM and HMDA projects; mix 43% road, 10% irrigation, 5% pipeline, 42% mining
Order inflow target for H2 FY27₹4,000–5,000 cr
Consolidated net debt to equity0.22x as of Jun 30, 2026, vs 0.49x as of Mar 31, 2026
Consolidated debt₹1,180 cr as of Sep 30, 2026, vs ₹2,438 cr as of Mar 31, 2026
Standalone working capital days104 days as of Sep 2026, vs 78 days as of Mar 2026
Capex incurred in H1 FY27₹220 cr, of which ~₹180 cr for mining assets
Full-year FY27 capex target~₹400 cr, of which ~₹300–320 cr for mining
Irrigation outstanding receivables~₹660 cr; total receivables with unbilled ~₹1,400 cr
Revenue guidance FY27₹2,200–2,300 cr, maintained
Revenue guidance FY28₹3,000 cr+, maintained
Mining revenue target for H2 FY27~₹100 cr
Kusmunda mine FY28 revenue target~₹400 cr
Banhardih mine FY28 revenue target (if starts Q1)~₹300 cr
Depreciation expectation for Q3 and Q4 FY27~₹30 cr per quarter
HAM project physical progress (as of Sep 30, 2026)Magadi–Somwarpet ~92%, Marripudi–Somavarappadu ~94%, Mysore–Kushalnagar IV 29%, Mysore–Kushalnagar V ~25%
Equity infused in four HAM projects (as of Sep 2026)₹193 cr out of revised ₹396 cr requirement
Remaining equity for four HAM projects₹202 cr, to be infused ₹117 cr in H2 FY27 and ₹85 cr in FY28
Additional equity requirement for Chennai and Telangana HAM projects~₹510 cr
Proceeds from KNR Guruvayur Infra monetization₹486 cr consideration on investment of ~₹193 cr
Proceeds from KNR Ramanattukara Infra monetization₹549 cr consideration on investment of ~₹226 cr
Withhold pending on three monetized assets~₹295 cr
Withhold expected on fourth monetized asset~₹130 cr
L1 projects as of call date~₹400 cr
Revenue split Q2 FY27Road EPC 28%, HAM 48%, irrigation 2%, back-to-back subcontract 21%