KNR Constructions Ltd Q4 FY2023 Concall Summary

Source transcript PDF: https://assets.stockscans.in/docs/itrunt0w94vb6s1wj0chsya2.pdf

Key Takeaways


The NHAI Bidding War & Competitive Reality

Reddy: "National Highways Authority of India tenders are going at very unhealthy pricing. I can straightaway say it is unhealthy and due to which, I think it's overcrowded also today. There is a cutthroat competition which is happening."

Order Inflow & Diversification Strategy

Reddy: "Sir, actually, it is not that we will not be taking more than that. It's the minimum target what we had in that mind. See, once the market is bad, if we go with our minimum target, that is better. If you take projects which are high competition in the huge order in size, then there will be every scope that you will go wrong, and you will end up with lesser margins."

Revenue & Margin Dynamics


Balance Sheet & Asset-Light Pivot


Claims, Receivables & Vivad Se Vishwas

Reddy: "There is a Vivad Se Vishwas. There is some circular which has come today, just today it has come. We are examining that. Definitely, that is under progress. I think NHAI or Ministry takes it very serious and implement that. Definitely, at least we'll realize our -- 50% of our claims will be realized."

Project Execution & Milestones


Guidance & Commitments

CommitmentSpecificsTimeline
Standalone revenue₹4,000 crores plus (internal target)FY24
Order inflow₹4,000–5,000 crores (over and above the ~₹2,000 crores already won)FY24; balance ₹2,000–3,000 crores expected in 3–4 months
EBITDA margin14–16% levels, internally targeting as good as deliveredFY24
Irrigation revenue~₹900–1,000 croresFY24
Incremental HAM equity infusion₹260 croresFY24
Capex₹130–140 croresFY24
Working capital daysMaintain current level (~67 days)Next 1 year, per Atmanirbhar circular extension
Vivad Se Vishwas claim realizationAt least 50% of claimsConditional on NHAI/Ministry serious implementation
Asset-light policyContinue monetizing project assetsAll coming years

Key Metrics

MetricQ4 FY23
Consolidated revenue₹1,245 cr, +13% YoY
Standalone revenue₹1,175 cr, +63% YoY
Consolidated EBITDA₹245 cr, vs ₹278 cr in Q4 FY22
Consolidated EBITDA margin19.8%
Standalone EBITDA margin18%
Consolidated PAT₹141 cr
Standalone PAT₹128 cr, +14% YoY
FY24 revenue guidance₹4,000 cr plus (internal target)
FY24 order inflow target₹4,000 cr to ₹5,000 cr
Outstanding order book₹7,092 cr, EPC Road and HAM 77%, litigation 23%
Consolidated net debt-to-equity0.22x, vs 0.55x as of 31 Mar '22
Consolidated debt₹610 cr, vs ₹14,028 cr as of Mar '22
Standalone debtAlmost 0 as of 31 Mar 2023
Working capital days67 days, vs 63 days in Mar '22
Telangana receivables (work done plus unbilled)~₹650 cr as of date
Bihar toll collection (Muzaffarpur to Barauni)₹10.24 cr in Q4, ₹43.71 cr in FY23
HAM project physical progress: Oddanchatram to Madathukulam90.1% as of 31 Mar 2023
HAM project physical progress: Magadi to Somwarpet72.2% as of 31 Mar 2023
Unbilled revenue₹450 cr
Retention money₹237 cr
Mobilization advance₹156 cr
FY23 full-year capex~₹140 cr, Q4 capex ~₹40 cr
FY24 planned capex₹130 cr to ₹140 cr
Incremental HAM equity requirement for FY24₹260 cr, out of total ₹437 cr remaining
Expected equity investment in 3 newly won HAMs~₹240 cr total, ~₹80 cr each, subject to financial closure
Q4 revenue split: irrigation25.73%
Q4 revenue split: HAM40%
Q4 revenue split: other EPC22%
Q4 revenue split: back-to-back12.5%
FY24 irrigation revenue expectation₹900 cr to ₹1,000 cr
Expected free cash flow on ₹4,000 cr turnover~₹550 cr (PAT plus depreciation)