Key Takeaways
- A tough year, not a broken model: Revenue fell to ₹195 cr from ₹217 cr and PAT halved to ₹4.74 cr, but management attributes the dip to identifiable, one-off execution bottlenecks rather than structural demand weakness.
- Stuck projects are the margin story: ₹20-30 cr of revenue went unrecognized because projects stalled on client-side land and approval delays, while fixed costs kept running with no escalation clause protection.
- The order book is a recovery bridge: An unexecuted order book of ₹389 cr, plus new wins in T&D, Reliance solar and Cameroon, sets the stage for a management-defined turnaround year.
- Saudi Arabia is the margin ambition: A newly incorporated JV targets 3 to 0.5 crore Saudi riyals of work this year, with management explicitly expecting better returns than domestic projects.
- What to watch next quarter: Whether the ₹117 cr of unbilled revenue converts to billed and collected, the pace of Saudi order inflow, and any disclosure on the stuck-project revival timeline.
What Went Wrong in FY25
- Execution bottlenecks, not demand failure: Projects stalled or were cancelled because of client-side land acquisition and approval bottlenecks, not because work dried up. PSU contracts lacked escalation clauses or damage recovery, so fixed costs for manpower, machinery and logistics were absorbed with zero corresponding revenue.
- Election-year deferral compounded the problem: Every five years, elections cause funding and spending decisions to be deferred; projects sat pending until the new governing body took over.
- One rare project hit profitability hard: Management flagged a specific, unusual project scenario (described as 1 in 100) that caused a disproportionate profitability dip; it declined to name the sector or client.
- Unbilled revenue piled up: ₹117 cr in other current assets is entirely unbilled revenue: work completed to milestone but not yet invoiced, concentrated in large projects at 80-85% completion where timelines extended and input costs rose.
- Debtor days stretched: Rose from 118 to 126 days, driven by slight recovery delays and the fact that the highest billing occurs in Q4.
Amish Shah: "There were few projects which got stalled and subsequently cancelled, due to factors which were beyond our control... these projects incurred substantial fixed cost across manpower, machinery and logistics, without having any corresponding revenue realization as most of these were governed by PSU contracts lacking escalation clauses or damage recovery mechanisms and we had to absorb the full financial impact."
The Turnaround Case
- Stuck projects are reviving: Projects that were stalled by approvals and elections are now being revived with new government decisions in place, and deferred revenue from those projects is expected to be recognized this year.
- Near-complete projects will drop margin straight to the bottom line: Projects at 85% completion will be finished with minimal incremental cost, creating a direct positive impact on EBITDA margins as they close out.
- New CEO installed: Mr. Jigar Shah has taken over as CEO and is now effectively managing operations, alongside a young team brought in for better delivery and payment/revenue recognition.
- Dashboard monitoring implemented: A new project-monitoring dashboard has been deployed to improve delivery discipline.
- Extended-delay mitigation process: The company is now flagging extended delays to clients through formal letters; where escalation clauses exist, it is putting claims forward; for government projects, it is trying to reduce costs during delay periods.
Amish Shah: "We've already seen, a lot of projects which have neared completion which have completed 85% and will be completed with minimal cost which will lead to direct positive impact on EBITDA margins."
New Verticals & Order Intake
- T&D entry via AVVNL: Awarded a ₹25 cr contract for segregating 11 KV mixed feeders in Rajasthan, with an ~18-month timeline; management is looking for similar jobs in other states.
- Reliance solar electrification: Received an order from Reliance Industries for electrification of PV factories; management sees a good chunk of business from this relationship, with other phases to follow.
- Cameroon opens Central Africa: Secured an international order from Pristine Limited in Cameroon, marking the company's entry into Central Africa.
- Railways MOU in progress: The company has identified railways as a segment and is executing an MOU to move forward and bid; it holds the necessary PQ credentials and is optimistic about a first order within FY26.
- PM KUSUM solar bids submitted: Bids submitted as a developer under the PM KUSUM scheme in Rajasthan; a tripartite land-lease agreement is expected in H1 FY26, with contract finalization to follow.
- Data center and water treatment pursuits: Actively pursuing EPC opportunities in data centers and taking measures toward water treatment and sewage treatment plant opportunities this year.
- Refinery maintenance expansion: Looking to expand maintenance-contract expertise to new refineries coming online.
Saudi Arabia & International Margins
- JV incorporated, bidding underway: A foreign JV entity has been incorporated in the Kingdom of Saudi Arabia with a partner that has presence in instrumentation, substation and automation; the company is already quoting for projects and expects orders within the next three quarters.
- Target: 3 to 0.5 crore Saudi riyals this year: Management set a work target of 3 to 0.5 crore Saudi riyals for the current financial year.
- Better margins than domestic: The explicit rationale for entering Saudi Arabia and other geographies is to earn better returns than domestic projects deliver.
- Consolidation coming: The Saudi JV will be actively consolidated in H1 of FY26.
- Cameroon and Saudi funded internally: No additional funding requirement is envisaged for either international venture; both will be funded from internal resources.
- Nigeria is an associate, not consolidated: Konstelec EPC Nigeria is an associate enterprise with common promoter holding; it helps generate business for Konstelec India but no direct revenue appears in consolidated statements.
Amish Shah: "We always look at different geographies for the reason of getting better returns than what we are getting in our own country, so we expect the returns would be better with better probability, bottom lines."
Margins & Competitive Position
- 10-15% EBITDA is the floor: Management stated that in the project business, any margin below 10-15% is not justifiable, and a return to that range is definitely possible this year.
- Most contracts are fixed-rate: Margins are protected by ensuring a +10% margin reflection at the bidding stage itself, with variations factored in upfront.
- Competition is local and geography-specific: Margins depend on the state and the local competitive set; the company competes with regional players in certain geographies.
- Larger projects offer healthier margins: Management is moving into larger segments (₹150-200 cr projects) where competition is thinner and margins are healthier.
- JV write-off was a cleanup, not a loss event: The Konstelec Hitech JV, incorporated in 2011 for a specific project completed in 2018-19, was kept alive for tax assessments that concluded this year; the ₹47 lacs investment was written off with no recovery possible.
Amish Shah: "In the project business anything, any margin which is below, you know, 10 to 15% is not justifiable. Definitely, there is a potential of 10 to 15%, definitely possible."
Unanswered Questions
- Order book breakup not provided: When asked for a sector and company-wise breakup of the ₹389 cr unexecuted order book, management offered to send details later but did not disclose them on the call.
- Nigeria consolidation remained unclear: Despite repeated questions, the analyst left unclear on what exactly is reflected in the presentation for the Nigeria entity; management reiterated it is an associate, not consolidated.
- April-May 2025 revenue declined: Management declined to disclose revenue for the first two months of FY26, saying it would be shared on a quarterly or six-month basis.
- Best-margin vertical not disclosed: When asked which vertical offers the best margins, management called it a business-specific question and declined to answer.
- L1 pipeline value withheld: Asked for the L1 value from a ₹1,000 cr pipeline, management deflected, saying projects are under evaluation and commercial bids are at the opening stage.
- Problem-project details withheld: Management declined to identify the sector or client of the specific project that caused the profitability dip, citing disclosure constraints.
Guidance & Commitments
| Commitment | Specifics | Timeline |
|---|---|---|
| Revenue growth | 20-30% growth over last financial year | FY26 |
| EBITDA margin recovery | Return to 10-15% EBITDA margin | FY26 |
| Saudi JV consolidation | Actively consolidated in consolidated financials | H1 FY26 |
| Saudi work target | 3 to 0.5 crore Saudi riyals of work | FY26 |
| Saudi order inflow | Orders from current bidding process to materialize | Next 3 quarters |
| PM KUSUM land agreement | Sign tripartite agreement to lease land | H1 FY26 |
| Railway first order | Secure first order in railway sector | FY26 |
| Stuck-project revenue recognition | Deferred revenue from revived projects recognized | FY26 |
| Quarterly reporting | Move to quarterly reporting | From next financial year |
| 220 KV transmission entry | Enter 220 KV transmission segment | "Years to come" |
| Larger-project bidding eligibility | Move into ₹150-200 cr project segments | No date given |
Key Metrics
| Metric | Q4 FY25 |
|---|---|
| Total income | ₹195 cr, vs ₹217 cr in prior year |
| PAT | ₹4.74 cr, vs ₹8.92 cr in prior year |
| ROE | 4.93% |
| ROI | 9.13% |
| Revenue growth target | 20–30% over FY25, expected in FY26 |
| Order book (unexecuted) | ₹389 cr, total orders under progress ₹720 cr |
| Orders received in FY25 | ₹231 cr |
| Orders received in Q1 FY26 | ₹35 cr |
| Domestic bid pipeline | ~₹1,000 cr of bids in process |
| Debtor days | 126 days, increased from 118 days |
| Unbilled revenue (other current assets) | ₹117 cr |
| Revenue stuck due to cancelled/stalled projects | ₹20–30 cr of revenue could not be booked in FY25 |
| Revenue mix by industry | 60% refinery, 13.7% steel, 25% other industries |
| Government vs private project split | 50% government, 50% private |
| AVVNL T&D contract value | ₹25 cr, timeline ~18 months, marks entry into T&D segment |
| Saudi JV work target for FY26 | SAR 0.5 cr to 3 cr of work expected this financial year |