KPI Green Energy Ltd Q1 FY2026 Concall Summary

Source transcript PDF: https://assets.stockscans.in/docs/sptgqq6scpawm9z4igs7onm5.pdf

Key Takeaways


IPP Execution & Project Pipeline

Faruk Patel: "the government of Gujarat, they have already planned for the five years Rs. 1 lakh crores investment in the transmission line and all over India also the government are thinking on this way only and they are making the very heavy infrastructure for the transmission line because the transmission line is not the new issue, it is a from the beginning it's like a road. You are manufacturing a car but if your road is not there who will be there, there will be the traffic."

Revenue Mix & Margin Dynamics

Salim Yahoo: "IPP has an EBITDA of around 85% to 90%, the upcoming IPP project, which I have already set up now, and the new upcoming projects also. So, IPP adds to the bottom-line."

Order Book & CPP Business


BESS, New Ventures & Subsidiary Structure

Salim Yahoo: "If you look at any of the bigger players, whether it is Adani, whether it is Adani Green Energy or whether it is Mahindra Renewables or Aditya Birla Renewables, these people have separate SPVs which you can call them as a subsidiary, 100 percent SPVs."

Balance Sheet & Capital Management

Salim Yahoo: "Max to max I said, it is not our target. We will try to keep it below that only. But max to max, we might reach up to 2:1 with the existing tie-ups and that the project that are coming. Whereas industry if you are seeing, industry are at 5, 6, big players are at 6 to 7 kind of."

SBI Pledge Release & Governance

Salim Yahoo: "Sir, SBI, see, I cannot control the board meeting of SBI. So, I can assure you what we see that by next quarter, I think we will have constructive at least approvals and sanctions from SBI."

Guidance & Commitments

CommitmentSpecificsTimeline
Topline growth50% to 70% growth over FY25 (~₹1,700 cr base)FY26
Topline growth~60% growth over FY26FY27
PAT marginMaintain 16% to 18% rangeOngoing through growth cycle
IPP capacity commissioningAt least 600 MW (half of 1.2 GW) commissionedBefore FY26 year-end
IPP project completion250 MW solar + 370 MW hybrid fully completeSeptember 2026
IPP revenue shareMove from 10% to 17-18% of revenueBy FY26 year-end
SBI pledge releaseConstructive approvals and sanctions expectedNext quarter (Q2 FY26)
Debt-to-equity ceilingNot to exceed 2:1, try to stay belowNext 2-3 years
Equity dilutionNone required from promoterNext couple of years
Promoter holdingStable at 48.70%Next couple of years
BESS ordersMajority of tenders expected; orders anticipatedThis quarter (Q2 FY26)
Sun Drop IPODRHP filingProcess underway, no date given
Panel cost hedging1.7 GW hedged at current ratesCovers near-term pipeline

Key Metrics

MetricQ1 FY26
Total revenue₹614 crores, 75% growth YoY over ₹350 crores in Q1 FY25
EBITDA₹217 crores, 64% increase YoY
PBT₹149 crores, up 64% from ₹91 crores in Q1 FY25
PAT₹111 crores, 68% growth from ₹66 crores in Q1 FY25
Basic EPS₹5.28, 44% growth from ₹3.66
Cash profit₹163 crores, 92% YoY growth
PAT margin16% to 17% currently, guidance range of 15% to 20%
Revenue growth guidance50% to 70% topline growth for FY26, on track
IPP EBITDA margin85% to 90% for upcoming IPP projects
CPP EBITDA margin~20%
Blended EBITDA margin30% to 32%
Installed and upcoming IPP capacity1.7 GW
Installed and upcoming CPP capacity2.3+ GW
Total cumulative portfolio4 GW
IPP portfolio (operational)503+ MW DC capacity
CPP order book1.8 GW, approximately ₹4,000 crores
Orders in handExceeds 3 GW, including capacities where LOI is awaited
IPP projects under execution250 MW AC solar, 370 MW AC hybrid, 150 MW wind, total execution size ₹5,000 crores
Land bank6,275 acres
Power evacuation capacityOver 3.2 GW
IPP-CPP revenue mix10% IPP, 90% CPP this quarter; last year was 12% to 13% IPP vs 86% to 87% CPP
Units generated this quarter6.9 crore units from existing 171 MW capacity
Debt-to-equity ratio0.5:1 currently; will not cross 2:1 with NCD and upcoming projects
Promoter holding48.70%, expected to remain stable for next couple of years
Workforce800 to 900 people total; around 560 in KPI
BESS tender pipeline₹3,000 crores to ₹4,000 crores of tenders identified for bidding
Solar and hybrid tender pipeline₹4,000 crores to ₹5,000 crores at any given point
Success ratio on bids80% to 90%
New green bonds expected rate~8.8%
IPP revenue realization₹3.5 to ₹3.6 per unit for existing 1,511 MW DC capacity; targeting ₹3 per unit average for 10 GW portfolio
10 GW portfolio target IPP shareAt least 25% revenue from IPP, 75% from CPP
FY26 year-end IPP revenue share target17% to 18%
Revenue growth trajectory FY2760% growth expected from FY26 to FY27