Key Takeaways
- Landmark year, growth decelerating: FY26 delivered a 92% 5-year sales CAGR and a doubling of the balance sheet to ₹9,882 cr, but forward revenue guidance was walked down from 50%–60% to 40%–50% YoY, which management frames as "less acceleration" rather than a slowdown.
- The IPP transition is the margin story: IPP assets earn 85%–90% EBITDA margins and require no working capital, so as they scale toward a 1.7 GW target this year, the mix shift should lift profitability and cash flow, even while the EPC order book (₹5,246 cr) strains working capital.
- Interest cost has not yet peaked: Finance costs rose ~130% to ₹182 cr as new capacity was added, and management sees a peak of ~₹300 cr before IPP cash flows turn strongly positive from FY27-28.
- Inventory is a deliberate hedge, not a red flag: Inventory jumped to ~₹1,400 cr (30%–40% of the order book) because management stockpiled panels and turbines to protect EPC margins against rising input costs and geopolitical supply risk.
- What to watch next quarter: Whether the Khavda substation is completed and full IPP revenue begins, the pace of ROE recovery after this year's targeted stabilization, and any concrete Maharashtra project announcements.
Growth Trajectory & Guidance
- 5-year CAGR: Sales grew at 92% CAGR and profit at 104% CAGR over the past five years, with total assets more than doubling each year to reach ₹9,882 cr in FY26.
- Guidance walk-down: Management had earlier guided 50%–60% YoY growth; the current commitment is 40%–50%, with the CMD publicly stating the company is "binded" to that range. When pressed on the reduction, management said 50% is common to both ranges and characterized the change as "less acceleration" rather than a slowdown.
- Capacity vs. revenue guidance: Management declined to give a MW capacity addition target, stating only revenue growth can be guided because capacity recognition depends on project completion timing, which can be lumpy.
- Post-FY27 confidence: Management expressed confidence in sustaining 40%–50% YoY growth through FY28 and FY29, driven by a large CPP market, a substantial order book, and new tenders. The 10 GW target by 2030 is on track and expected to be reached ahead of schedule.
Salim Yahoo: "It's a less acceleration, I would say -- I won't say slowdown. It's a less acceleration compared to what acceleration was there earlier."
IPP Scale-Up & Margin Mechanics
- IPP margin profile: IPP assets deliver ~85%–90% EBITDA margins and require no working capital, generating strong net cash accruals. As IPP capacity increases in the revenue mix, consolidated profitability should improve, though the growing EPC business (₹5,000+ cr order book) strains working capital and dilutes the blended margin.
- Capacity milestones: IPP capacity crossed 1 GW post-March 2026, and the company is targeting 1.7 GW this financial year. Key projects include 250 MW (COD October '26), 370 MW (COD October '26), 150 MW wind (COD November '27), and 300 MW from SJVN (PPA yet to be signed; 18–24 months post-signing).
- Revenue phasing benefit: PPAs with government entities like GUVNL allow plants to be set up in batches of 25–50 MW, so 50%–60% of a plant can start generating revenue before final COD, reducing the interest burden during construction.
- Khavda delay: Revenue billing was delayed ~6–7 months because GSECL's government substation (in their scope) was not completed. GSECL agreed to extend PPA terms; partial revenue has started, and the remaining substation capacity is expected this quarter end, after which full revenue will begin.
- ROE recovery target: Management aims to curtail the ROE decline this year and see ROE return to earlier levels next year, though no specific EPS breakeven point for the IPP transition was provided.
Salim Yahoo: "Though maybe the COD of that will be in the end of '27. But before that, 50%, 60% of the plant has already started generating revenue. So you'll see a mixed impact on the financial."
Order Book & Project Wins
- Order book: Stands at ₹5,246 cr, with inventory of ~₹1,400 cr deliberately built to cover 30%–40% of it, hedging against rising panel, turbine, steel and copper prices and geopolitical supply disruptions.
- FY26 wins: 150 MW wind (GUVNL), 445/890 MWh and 120/240 MWh stand-alone BESS projects, 142 MW floating solar, 250 MW solar (SJVN), 1.13 GW solar balance of plant (Adani Group), 300 MW wind (SJVN), plus orders from Aditya Birla and Adani Green.
- Bid pipeline and selectivity: The company is participating in 4–5 GW of bids but will be increasingly selective, prioritizing high-margin tenders and faster-execution opportunities. Past win ratio was ~75%.
- EPC margin detail withheld: Management declined to break the EPC order book into with-material vs. without-material segments, calling it competitively sensitive. EPC EBITDA margin was disclosed as ~16%–18%, varying by project type; combined company EBITDA is ~33%–36%.
Salim Yahoo: "In the past, our win ratio has been at 75%. But going forward, we'll be very selective. We'll select high-margin kind of tenders, and we'll try to gain as much as the faster execution kind of tenders."
Balance Sheet, Cash Flow & Capital Structure
- Interest cost trajectory: Finance costs rose ~130% to ₹182 cr because FY25 benefited from a QIP that repaid loans, while FY26 added 250 MW, 370 MW and 240 MW of capex-heavy IPP capacity. Peak interest cost is estimated at ~₹300 cr.
- Operating cash flow: Grew ~100% to ~₹400 cr, driven by IPP cash accruals that require no working capital. Capex is funded from long-term investments only.
- Debtor and inventory days: Debtors stayed at similar absolute levels while revenue grew, so days appear lower. Inventory days rose because of the deliberate stockpiling strategy tied to the order book.
- Green bond: Listed India's first externally credit-enhanced green bond: ₹670 cr, 5-year, 8.50% coupon, quarterly amortization, 65% partial guarantee from GuarantCo, rated AA+(CE).
- Promoter pledge: Promoter shares were pledged pre-IPO as collateral. SBI has sanctioned ₹3,000 cr and approved release within 3 months after COD of the 250/370 MW projects; all pledge should be released by March '27.
New Business Segments
- BESS: Two major orders signed (445/890 MWh and 120/240 MWh, end-customer GUVNL), to be completed this financial year with revenue recognized in FY27-28. Margins are decent but not as lucrative as IPP; depend on tender pricing and technology (lithium vs. sodium). The market is at a nascent stage with state-level policies emerging in Rajasthan, Maharashtra and Gujarat.
- Trading licenses: Received both interstate (CERC) and intrastate (GERC) trading licenses, enabling participation in pan-India power exchanges and bilateral contracts.
- Sundrops Energia IPO: DRHP filing imminent; the IPO will fund battery energy storage and manufacturing. Listing targeted this financial year.
- Botswana expansion: A step-down subsidiary via GIFT City has been set up; all ODI/FEMA approvals obtained, office and team in place. PPAs in Botswana and neighboring countries to be signed shortly, with a first commitment of 500 MW by end-December 2027.
- Future segments: Management flagged green hydrogen, floating solar, offshore wind, pump storage and energy trading as areas of capability-building.
Regulatory & External Risks
- Grid stabilization charges (Maharashtra): Newly introduced charges are under evaluation; no such charges exist in Gujarat or other states yet. The impact on the CPP segment is uncertain pending detailed assessment. KPI does not do rooftop projects but is exploring a new policy with a 50% base-compatible mandatory requirement.
- Curtailment risk: Curtailment of renewable energy during peak hours is under active discussion at CERC, but no concrete decision or deadline exists. Green corridors, proper evacuation, and load flow studies are being considered; most CTU projects are expected in 2028–2030.
- REIA consolidation: The government consolidated four REIAs into one (SECI), which management views as a positive directive creating a single-point tendering body. Dr. Alok Das attended the MNRE meeting and expressed confidence in SECI's ability to move the process forward.
- Evacuation growth questioned: An analyst noted evacuation grew only ~10% YoY (3.26 GW to 3.59 GW) versus 100% the prior year. Management said multiple evacuations have been applied for in different companies and will be transferred to KPI later, but did not explain the reported slowdown.
Alok Das: "So, this is the coming time, probably some solution will come, how fast that the project can come. Today, most of the CTU projects, they are coming '28, '29, 2030. So that kind of... augmentation of power evacuation systems are just a way to create all sort of facilities to address that curtailment issue. So that is a dynamic situation."
Guidance & Commitments
| Commitment | Specifics | Timeline |
|---|---|---|
| Revenue growth | 40%–50% YoY | Ongoing; sustained through FY29–FY30 |
| IPP capacity target | 1.7 GW | This financial year (FY27) |
| IPP project CODs | 250 MW and 370 MW: October '26; 150 MW wind: November '27 | Specific dates |
| Khavda full revenue start | Remaining GSECL substation capacity completed | This quarter end |
| Peak interest cost | ~₹300 cr | Not specified (implied near-term peak) |
| ROE recovery | Curtail decline this year; return to earlier levels next year | FY27–FY28 |
| Promoter pledge release | All pledge released by SBI | By March '27 |
| Sundrops Energia IPO | Listing | This financial year (FY27) |
| Botswana first commitment | 500 MW | End-December 2027 |
| BESS revenue recognition | Two GUVNL projects completed and revenue booked | FY27-28 |
| 10 GW target | On track, expected ahead of schedule | By 2030 |
| EPC order book breakup | Will not disclose with-material vs. without-material | No timeline (declined) |
Key Metrics
| Metric | Q4 FY26 |
|---|---|
| Total income | ₹810 cr |
| EBITDA | ₹305 cr |
| PAT | ₹155 cr |
| Total income (FY26) | ₹2,742 cr, +56% YoY |
| EBITDA (FY26) | ₹1,006 cr, +73% YoY |
| PAT (FY26) | ₹509 cr, +57% YoY |
| Revenue growth guidance | 40% to 50% YoY, maintained |
| Installed capacity | Over 1.62 GW as of March 31, 2026 |
| IPP capacity | Crossed 1 GW post March 31, 2026 |
| Work-in-progress capacity | Over 4.64 GW |
| Installed plus upcoming portfolio | Approximately 6.26 GW (2.57 GW IPP, 3.69 GW CPP) |
| CPP order book | ₹5,246 cr |
| Cash flow from operations (FY26) | ₹424 cr, vs ₹208 cr in FY25 |
| Net worth (FY26) | ₹3,273 cr, vs ₹2,630 cr in FY25 |
| Total assets (FY26) | ₹9,882 cr, vs ₹4,792 cr in FY25 |
| Combined EBITDA margin | 33% to 36% |
| IPP EBITDA margin | 85% to 90% |
| EPC EBITDA margin | 16% to 18% |
| Interest cost (FY26) | ₹182 cr, up ~130% YoY |
| Peak interest cost estimate | Approximately ₹300-odd cr |
| Green bond issued | ₹670 cr, 5-year, 8.50% coupon, AA+(CE) rated |
| Sundrops Energia PAT (FY26) | ₹97 cr, on top line of ₹586 cr |
| Land bank | 7,210 acres (800–1,000 acres owned, rest on 26–27 year lease) |
| Bid pipeline | 4 to 5 GW |
| Historical win ratio | 75% |
| 10 GW target | By 2030, ahead of schedule |