Lemon Tree Hotels Ltd Q2 FY2026 Concall Summary

Source transcript PDF: https://assets.stockscans.in/docs/tgvdifgsjvbh5n21x019bw9f.pdf

Key Takeaways


The Renovation Overhang: Cost Today, Pricing Power Tomorrow

Patanjali Keswani: "I urge you to look at how it will be once the renovation is over because it will have a double whammy. You will have new rooms, very little future investment for the next 3 years."

Aurika Mumbai: The Scaling Story


Pipeline & Growth Levers

Patanjali Keswani: "I joke with a couple of my friends in the hotel industry that all the large hotel companies started in the mid-market and they acquired 5-star brands. In India, for whatever reason, we have been more 5-star driven and less mid-market driven."

Technology as a Moat


Margin Bridge & Recovery Path

Patanjali Keswani: "We would be very disappointed if by FY28, our net EBITDA without extraordinary expenses is less than 59%."

Q2 Softness: A Confluence of Transient Headwinds

Patanjali Keswani: "To give you an example, we had 2, 3 hotels in Gurgaon. And if I remember right, our rates were Rs. 9,000 and Rs. 10,000. And today, it is Rs. 7,000 - Rs. 8,000. So it is still a catch-up amazingly that after 17 years and inflation, the rate is still not caught up to the pre-global financial crisis rate."

Guidance & Commitments

CommitmentSpecificsTimeline
Q3 RevPAR growthMid-teens (minimum 15%) RevPAR growthQ3 FY26
Aurika Mumbai ARRCross ₹9,500 in Q3, north of ₹10,000 in Q4, ₹11,000-12,000 next winterQ3 FY26 through next winter
FY26 EBITDA marginSame as FY25; increased spend offset by 2x revenue growthFY26
FY28 net EBITDA marginAt least 59% (without extraordinary expenses)FY28
Renovation completionMost of portfolio fully renovated; another ₹130-140 crore spentEnd of next calendar year
Renovation spend normalizationDrops to 1.5% of revenue after cycle completes; 0.5% in FY28-30Post-renovation / FY28-30
Technology rolloutFully debugged, piloted, tested at scale and rolled outNext 12-18 months
Managed portfolio signing rate5,000 rooms next year, 7,000 the following yearNext year and year after
Room pipeline target35,000-40,000 rooms (double current, including operational)Next 2.5 years
Fleur demerger announcement"A bunch of interesting things to tell the market"Next 3 months
Maintenance capex post-renovation₹20-25 crore per yearAt least 5-6 years after renovation ends
Shillong hotel openingMid-20272027
Shimla hotel soft openingHalf the hotel opensNext year

Key Metrics

MetricQ2 FY26
Net EBITDA₹132.4 crore, grew 1% YoY
Net EBITDA margin43%, decreased by 306 bps YoY
Gross ARR₹6,247, increased 6% YoY
Occupancy69.8%, increase of 139 bps YoY
RevPAR₹4,358, increased 8% YoY
Profit after tax₹41.9 crore, increase of 20% YoY
Cash profit₹76.3 crore, increase of 9.2% YoY
Total management fees₹34.3 crore
Fees from Fleur Hotels₹19.9 crore, increase of 8% YoY
Debt₹1,610 crore as of 30th September, fall of ₹212 crore vs ₹1,822 crore on 30th September last year
Cost of borrowings7.72%, vs 8.68% in Q2 last year
Total inventory242 hotels and 20,074 rooms as of September 30, 2025; 10,956 rooms and 121 hotels operational, rest in pipeline
New management and franchise contracts signed15 contracts, adding 1,138 rooms to pipeline
Hotels operationalized5 hotels, adding 272 rooms to operational portfolio
Rooms renovated (cumulative)3,000 rooms out of 4,600 rooms needing renovation, spent a little under ₹300 crore
Renovation, technology and ex-gratia expenses8% of revenue in Q2, vs 5% last year
Aurika Mumbai occupancy71% in Q2
Aurika Mumbai overall ARR₹8,500
Loyalty members0.21 crore (0.21 crore), with a fair amount of duplication