Key Takeaways
- Sales velocity strong, revenue recognition lags: Ready-to-move-in inventory at Monte South and newly OC-received Millennium are selling well, but percentage-completion accounting means revenue will follow in coming quarters.
- Realization dip is a mix shift, not a price cut: Average commercial and residential realizations fell because lower-priced projects (Millennium, Nexzone) made up a larger share of the quarter's sales. Underlying project-level prices are rising 5-10% as construction progresses.
- Bhandup SRA project enters the listed entity: The 14-acre slum rehabilitation project in Bhandup will be consolidated this quarter, with numbers visible next quarter. The company plans to launch at least 1 acre per year from this land parcel.
- Pipeline of ₹4,660 crores over 12-36 months: Five upcoming projects totaling 31.5 lakh sq ft are slated to launch, with approximately ₹1,200 crores of launches planned in 2024 alone.
- What to watch next quarter: The Bhandup project's contribution to the listed entity's financials, the pace of new launches from the ₹4,660 crore pipeline, and whether the mix-driven realization dip reverses as higher-priced projects regain share.
Sales & Revenue Recognition
- Monte South driving ready-to-move-in demand: Tower A has topped out at 64 levels with part occupancy given up to the 51st floor, creating near-ready inventory that is seeing great velocity. Tower 2 is also seeing good movement, while Tower C's lower ticket size means it does not compete with Tower A.
- Millennium selling well post-OC: The project has seen very good traction after receiving its occupancy certificate.
- FutureX benefiting from infrastructure: The Lower Parel bridge, closed for many years, finally reopened last quarter, providing a significant infrastructural benefit to the project.
- Revenue recognition lags sales: The company follows the percentage completion method, so revenue is recognized as additional work is completed. Strong sales velocity adds to new bookings and will reflect in cash flow and collections over the next few quarters.
- Quarterly volatility is structural: Management cautioned that real estate should not be seen quarter-on-quarter due to long gestation timelines; some quarters will not align, but on an annual basis the company expects to do much better than last year.
Management: "real estate due to its nature of business ideally should not be seen quarter-on-quarter while I think we have done much better than the last Q2, there will be one or two quarters where things may not align because sometimes these deals are long gestation timelines and things like that, but overall on an annual basis, I think we should more than or if not cover up and do much better than last year."
Realizations & Pricing
- Commercial realization dip is a mix effect: Average commercial realization fell because Q2 had a higher proportion of sales from Millennium (Mulund, ~₹12,000-13,000/sq ft) versus FutureX (Lower Parel, higher price), while Q1 had the opposite mix. Individual project prices did not decline.
- Residential realization dip also mix-driven: Panvel residential (Nexzone) contributed a higher ratio compared to the previous quarter, pulling down the blended average.
- Underlying prices rising 5-10%: Price increases are tied to construction progress: nearing OC commands the highest increase, while nearing foundation gets lower increases. The overall uptick is 5-10%.
- No inventory hoarding: The company does not hold inventory to increase prices; it sells at the best rate available. The 5-7% price uptick is a natural consequence of higher percentage completion, not a deliberate holding strategy.
Management: "As a policy, we are not holding the inventory to increase the prices. So, we would sell at whatever best rate that we can get and even though we have seen 5% to 7% uptake because we are in the making of constructing of the premises and if we sell faster, we will launch another project faster."
Project Pipeline & Launches
- Top five upcoming projects: Total 31.5 lakh sq ft saleable area with an estimated sale value of ₹4,660 crores, most likely launching in 12 to 36 months with completion in 36 to 48 months.
- 2024 launch target: Approximately ₹1,200 crores of launches planned in 2024 from the ₹4,600 crores pipeline.
- Near-term launch cadence: In the next one year: Monte South targeting 3,00,000 sq ft, Bhandup targeting 1,80,000 sq ft, Nexzone targeting 2-3 lakh sq ft.
- Phase-3 launches: Monte South Tower 4 and commercial are 1.5 to 2 years away.
- FutureX unsold inventory: Not all unsold inventory is available for sale; one-third was already leased by end of Q2, providing a pre-lease sales opportunity.
Bhandup SRA Project
- Consolidation imminent: The 14-acre slum rehabilitation project in Bhandup will come into the listed entity this quarter (Q3 FY24), with numbers visible next quarter.
- Progress update: The slum rehabilitation building has been constructed and slum residents have moved into the new SRA building. The sale building ground is vacant with excavation work ongoing.
- Launch cadence: The company intends to launch at least 1 acre per year from the 14-acre parcel year-on-year.
Kaivalya Shah: "we intend to launch year-on-year at least 1 acre year-on-year project. So, that way you can kind of understand how soon we'll be wrapping"
Redevelopment & Business Development
- Redevelopment scouting active: The company is actively looking at Worli, Walkeshwar, and Pedder Road areas for redevelopment, with 4-5 proposals already on the drawing board under discussion.
- No project taken on hand yet: No redevelopment project has been finalized; management expects at least another two quarters before any news can be out due to due diligence.
- Joint development model: Currently most projects are in a joint development format, but the company is open to looking at projects with other land bank owners beyond Marathon Realty.
Balance Sheet & Regulatory
- Debt target: The company targets a debt-to-equity ratio of around 1.0. Over the next two years, debt is likely to reduce. Leveraging is seen as helpful because the cost of debt is much lower than the profits generated, but post-pandemic caution keeps the ratio controlled.
- BMC pollution order: Compliance requirements include a 20-25 ft periphery wall with cladding, water sprinkling on dust from RMC plants, and covered debris transport. These are doable with marginal cost increase and are not a major hindrance.
- Commercial office market normalizing: In Mumbai, almost 100% of employees have returned to office, creating a normal occupancy environment.
Management: "That's how the policy has been because the cost of debt is much lower than the profits that we are generating. So, in that sense, leveraging is helping us. However, after seeing the pandemic situation where the debt was the one that was impacting badly on everybody's balance sheet, we try to keep it under control by keeping a 1.0 debt-to-equity ratio around 1.0 as our target."
Guidance & Commitments
| Commitment | Specifics | Timeline |
|---|---|---|
| Bhandup project consolidation | 14-acre SRA project enters listed entity, numbers visible | Q3 FY24 consolidation; Q4 FY24 numbers visible |
| Bhandup launch cadence | At least 1 acre launched per year | Year-on-year from the 14-acre parcel |
| 2024 launches | Approximately ₹1,200 crores from the ₹4,660 crore pipeline | Calendar 2024 |
| Pipeline launch window | 31.5 lakh sq ft, ₹4,660 crores sale value | Launch in 12-36 months; completion in 36-48 months |
| Monte South Phase-3 | Tower 4 and commercial launch | 1.5 to 2 years away |
| Debt target | Debt-to-equity ratio around 1.0, debt likely to reduce | Over the next two years |
| Redevelopment announcement | First news on redevelopment projects | At least two quarters away |
| Annual performance | Do much better than last year | Current fiscal year |
Key Metrics
| Metric | Q2 FY24 |
|---|---|
| Revenue | ₹129 cr, fell sharply QoQ |
| Net revenues (H1 FY24) | ₹339 cr, vs ₹268 cr in H1 FY23 |
| EBITDA (H1 FY24) | ₹146 cr, vs ₹99 cr in H1 FY23 |
| Profit before tax (H1 FY24) | ₹80 cr, vs ₹30 cr in H1 FY23 |
| Profit after tax (H1 FY24) | ₹78 cr, vs ₹27 cr in H1 FY23 |
| Net debt | ₹851 cr as on 30 Sep 2023 |
| Debt-to-equity target | ~1.0x |
| Equity increase rate | ₹20–25 cr per quarter |
| Area sold (H1 FY24) | 2,62,900 sq ft |
| Booking value (H1 FY24) | ₹384 cr |
| Collections (H1 FY24) | ₹301 cr |
| Average realization – commercial (H1 FY24) | ₹18,580 per sq ft |
| Average realization – residential (H1 FY24) | ₹12,666 per sq ft |
| Price increase realized (last 1 year) | 5% to 7% on existing ongoing projects |
| Upcoming project pipeline – saleable area | 31.5 lakh sq ft, estimated sale value ₹4,660 cr |
| 2024 planned launches | ~9 lakh sq ft, value ~₹1,200 cr |
| Unsold ready-to-move-in inventory – Monte South | ~47,000 sq ft, ~₹100 cr |
| Unsold ready-to-move-in inventory – Nexzone | ~61,000 sq ft, ~₹38 cr |
| Unsold ready-to-move-in inventory – FutureX | ~1.6 lakh sq ft; ~55,000 sq ft leased in Q3 |