Mazagon Dock Shipbuilders Ltd Q3 FY2024 Concall Summary

Source transcript PDF: https://www.stockscans.in/document/zwp4hxztckbfqbewl3k76ygp.pdf

Key Takeaways


Profit Drivers: A Quarter of One-Offs

Singhal: "One is the refund of the liquidated damages for the one number of submarine in quarter 3 and second our delivery of the third destroyer almost 5 months ahead of schedule. So, these two have been the major factors which have contributed to better margins."

Order Book & Pipeline: Visibility Without Clarity

Singhal: "So, even if the orders are getting finalized the expenditure would be flowing in over next couple of years. So, during this particular financial year or Financial Year 2025 we don't expect a significant buildup of expenditure. So, the budget would not be a constraint in that regard."

Delivery Schedule: The Real Margin Engine


P-75I & Add-On Submarines: The Big Prize, Still Distant


Guidance & Commitments

CommitmentSpecificsTimeline
Fourth destroyer (15 Bravo) deliveryTargeting deliveryFY25, possibly Q2 or early Q3
First frigate (17A) deliveryTargeting deliveryFY25, before December 2024
Margin sustainabilityExpect current margins to sustainNext 2-3 quarters
Fourth submarine LD refundExpect positive resultPossibly Q4 FY24
P-75I AIP technical conclusionField Evaluation Trials in a few months; DAP 2020 timeline ~8-10 months to concludeNo award date given

Key Metrics

MetricQ3 FY24
RevenueNot stated
Operating marginNot stated
Profit after taxHighest-ever quarterly profit and highest-ever 9 months profit
Order book₹38,389 cr as of 31 December
Order inflow (FY24 up to January)More than ₹7,000 cr, including orders from Coast Guard, ONGC, and export segment
Liquidated damages refund receivedApprox ₹160 cr in Q3
Liquidated damages refund expected₹150–160 cr expected in Q4
Cash balance (net of advances)Slightly in excess of ₹3,000 cr as of 31 December
Contract liabilitiesApprox ₹9,000–10,000 cr, largely offset by work in progress
P-15B destroyer deliveryThird destroyer Imphal delivered in October 2023, almost 5 months ahead of schedule
P-15B fourth destroyer delivery targetQ2 or Q3 FY25
P-17A first frigate delivery targetBefore December 2024
P-75 sixth submarine delivery target2024
CAPEX (annual, including Nhava yard)Approx ₹300–350 cr per annum for infrastructure including Floating Dry Dock and maintenance CAPEX
Floating Dry Dock costApprox ₹500 cr over ~2.5 years (32 months)