Mazagon Dock Shipbuilders Ltd Q4 FY2024 Concall Summary

Source transcript PDF: https://www.stockscans.in/document/ryn6ni94oehvn4imgrrmymn3.pdf

Key Takeaways


Delivery Pipeline & Revenue Trajectory

Singhal: "Incidentally, this was our 250th year. So on 14th of May, 2024, we have celebrated our 251st Foundation Day. This has been a long and phenomenal journey, starting from a small dry dock in 1774 and today, reaching to these heights, when our revenue from operations is significantly higher than \$1 billion."

Order Pipeline: The Next Wave

Singhal: "Both have a totally different scenario with respect to how many players are there in competition or if the order is on nomination, then the margins are predefined. So, lot many factors would come into play when these orders actually crystallize."

Margins: Current Strength, Future Uncertainty


Capacity Expansion & Capex


Balance Sheet & Cash

Singhal: "A substantial amount of this cash which is visible in our balance sheet belongs to Navy against the project. So, this is not free cash. Free cash which belongs to MDL would be around INR4000 crores."

Guidance & Commitments

CommitmentSpecificsTimeline
Destroyer delivery4th P-15B destroyer delivered significantly ahead of contractual scheduleContractual delivery Feb'25
Frigate deliveryFirst Project 17A frigate delivered; possibly two if on planFY25
Submarine deliveryLast P-75 submarine deliveredFY25
Revenue peakFY25 to be the highest revenue year on current order bookFY25
Add-on submarine orderThree additional P-75 submarines with AIP finalizedDuring FY25
P-75I awardAward expected in normal course; beyond FY26 is a delayFY26
ONGC first order execution₹1,142 crores order completedThis financial year
Capacity doublingAt least doubled capacity when three facilities are in placeNo date (development over next 2-4 years)
Capex outlayINR2,500 to INR3,000 crores incurredNext 3 to 4 years

Key Metrics

MetricQ4 FY24
Revenue from operationsSignificantly higher than \$1 billion for FY24, best ever performance since inception
Liquidated damages (LD) write-back~₹141 cr in Q4, corresponding to one submarine
LD write-back for full year~₹300 cr for FY24, corresponding to two submarines
Additional interest income~₹400 cr in FY24 vs FY23, from improved rates and higher deposits
Pending execution – Destroyer project₹11,216 cr, out of total order value of ₹32,081 cr; three destroyers already delivered
Pending execution – Frigate project~₹17,000 cr, out of total order value of ₹27,000 cr for four frigates; ~₹10,000 cr already booked
Pending execution – Submarine and spares~₹3,000 cr for the submarine to be delivered this year
Total order book₹38,000 cr as of Q4 FY24
Revenue target for MoU excellent rating~₹10,000–₹10,500 cr for FY25
Free cash~₹4,000 cr belonging to MDL, out of total cash of ~₹15,000 cr+; substantial portion belongs to Navy against projects
Capex plan₹2,500–₹3,000 cr over the next 3 to 4 years, for adjacent 15-acre land and Nhava yard development
Ship repair revenue share expectation5% to 7% of total revenue, even after infrastructure capex; new build remains primary focus
Base and depot spares plus warranty charges12%–15% of total project cost
P-75I AON cost (2018)₹43,000 cr for six submarines, published in 2018; six years dated
ONGC order under execution₹1,142 cr, received December 2023