Key Takeaways
- Record revenue, margin still resetting: Consolidated revenue hit an all-time high of ₹385 crores (25.4% YoY), while EBITDA margin at 10.6% reflects older orders still working through the mix.
- The order book is the growth engine: Orders on hand reached ₹1,109 crores (19% YoY), and two large post-quarter wins in data centers and high-rise buildings are not yet in that number.
- Capacity expansion is now live: Sanand Phase 1 brownfield commenced commercial production in October, adding 20,000 metric tons of PEB capacity, with Cheyyar Phase 2 already underway.
- Exports are scaling, with a margin tailwind: H1 export revenue jumped 68% YoY, freight costs are cooling from peak, and management expects a "much bigger jump" in H2 dispatches.
- What to watch next quarter: Revenue contribution from the first hyperscaler data center order, the pace of export inquiry conversion after a 5–6 month slowdown, and any margin lift as older orders consummate.
Revenue & Order Book
- Broad-based volume growth: Q2 revenue of ₹385 crores was the highest ever, with Phenix contributing 77% (22% YoY growth) and Proflex 23% (37% YoY growth), driven by strong execution of a healthy order book across both divisions.
- Order inflows stayed strong: Q2 secured ₹441 crores in new orders (12% YoY), split between Phenix at ₹335 crores (including ₹61 crores exports) and Proflex at ₹106 crores, sustaining the ₹1,109 crore order book.
- Two large post-quarter wins: A data center order from a hyperscaler and a high-rise building order of similar quantum were secured after Q2, so neither is included in the reported order book; the data center win is Phase 1 of a larger plan with follow-on tonnage likely.
- Export order conversion slowed: Over the last 5–6 months, closing of inquiries into orders happened at a slower pace, though management expects this pace to quicken and notes a revival in Canadian inquiries after a tariff-driven slowdown.
- Domestic inquiry depth: Phenix inquiries in excess of 2.5 lakh tons are expected to close in the next couple of quarters, while North American export inquiries of 40,000–50,000 tons are expected to convert in the next few months.
Sanjay Majmudar: "I think what is more significant is the fact that our design breakthrough has happened and we have received this order. We believe that this will unfold several new opportunities and we are working on it. This was an important breakthrough."
Capacity Expansion & Certifications
- Sanand Phase 1 is live: Commercial production commenced effective October 26, 2026, adding 20,000 metric tons of PEB capacity and taking the Sanand facility from 72,000 to 92,000 tons per annum and total PEB capacity to 124,000 metric tons.
- Cheyyar Phase 2 expedited: Implementation has started on an additional 20,000 tons per annum, expected operational in Q3 FY28, which will take combined PEB and structural steel capacity to 154,000 metric tons.
- Structural steel capacity also expanding: A 10,000 tons per annum project at Sanand is expected on stream by Q1 FY28, increasing structural steel capacity to 22,000 metric tons.
- CE certification unlocks Europe: Sanand received CE certification from TÜV Nord Systems, an essential prerequisite for exporting PEBs and structural steel to the UK and European markets, with a target to commence UK business in FY28.
- AISC certification supports US push: Cheyyar already holds AISC certification; a dedicated sales team is being created for the West Coast of the USA, with intent to service the region from Cheyyar through the Pacific route starting next fiscal.
Export Trajectory
- H1 exports surged 68% YoY: Q2 export revenue was ₹67 crores (17% of total, 25% YoY growth), and H1 reached ₹95 crores, with management fully booked for the current fiscal and part of next year.
- H2 dispatch jump expected: A large ₹212 crore export order has the rest of its revenue recognition lined up for H2 dispatches, and management stated "we should see a much bigger jump in the export dispatches" in the second half.
- Freight costs are easing: Container freight has cooled from a peak of ~$12,000 to ~$7,000–$8,000, though it remains above originally costed levels; customers are supporting by absorbing part of the freight, and further correction is a margin tailwind.
- Export incentive timing: The incentive is based on dispatch, not billing, so some of the ₹67 crore export booked in Q2 had its incentive already booked in an earlier quarter; H2 incentive will "definitely be higher."
- Geopolitical watchpoints: The US midterm elections are a "wait-and-watch situation" with no immediate duty reduction expected (25% duty remains), while any improvement in the Iran situation could ease freight further and improve order generation and conversion at better pricing.
Malav Patel: "Domestic gives you volume and international business gives you margins. So that is how we are able to strike a fine balance between the volume and the bottom line."
Data Center & High-Rise Breakthroughs
- First hyperscaler data center order: A single-story, primarily PEB structure marks the company's entry into the data center segment; revenue will start hitting the top line towards the end of this quarter, beginning of next quarter, with the major part coming in Q4.
- Follow-on pipeline is material: Multiple expansions are expected in the next 3–4 quarters, and once this order is executed, other hyperscalers are expected to come for order closure; a large possibility exists of similar tonnage repeating at the same premise in coming months.
- High-rise building order: A multi-storied building order of similar quantum to the data center order was also secured post-Q2, strengthening presence in that segment.
- Data center margin profile: Slightly better margins are expected on such large orders due to economies of scale at a single location, and India's installed data center capacity is projected to increase to 6 GW by 2029, creating significant opportunities across the construction ecosystem including pre-engineered steel structures.
- Order size undisclosed: Management declined to disclose the quantum of either order, stating details will be shared in the current quarter's results, and deflected a question on per-megawatt steel tonnage, calling it "very, very difficult" to generalize given variability in racking systems.
Margins & Profitability
- EBITDA margin at 10.6%: Q2 EBITDA grew 17.6% YoY to ₹43 crores and PAT grew 32.8% YoY to ₹29 crores, but the margin partly reflects older orders still in the mix; management is targeting improvement as those orders get consummated.
- Gross margin held at ~32% in H1: Slightly impacted by steel price variation, but PAT was not impacted because of overall volume and a good mix of domestic and export turnover; new orders booked in Q2 already factored in the steel price rise that occurred during the quarter.
- Export margin tailwind building: Better margin is expected in the coming two quarters versus the first two, with freight correction and customer cost-sharing both contributing.
- Proflex capacity utilization at ~99%: Improved through a conscious focus on securing larger project sites that reduce travel time and maximize output; similar utilization is expected through the fiscal end based on orders on hand.
- Steel price outlook: Some softening of steel prices is expected, and new orders already account for the Q2 price rise, which should support margin recovery as older, lower-margin orders roll off.
Malav Patel: "We are targeting. Of course, that is always an endeavour to improve the margins. So, at least this much is what we are committing, but our try is going to be to improve this."
Strategic Positioning & Ambition
- From building supplier to engineered steel solutions company: Management's stated ambition is to become one of the most profitable, technically differentiated, and execution-reliable steel building companies at scale, shifting the business model toward engineering certainty into every project.
- Proflex growth intact: Revenue grew 37% YoY in Q2, three additional mobile units were commissioned over the last three quarters, and management is evaluating one specialized seam technology with a much wider span, with a decision expected this quarter.
- IPO proceeds 60% utilized: ₹155.27 crores of the ₹259.32 crore raise has been deployed as of September 30, 2026, with ₹8.58 crores utilized during the quarter, primarily toward the capacity expansion program.
- Capex run-rate: Q2 capex was ₹43 crores, taking H1 FY27 capex to ₹70 crores, consistent with the expansion cycle across Sanand and Cheyyar.
Malav Patel: "While M&B is committed to growing in tons and square meters, our true ambition is far greater, to become one of the most profitable, technically differentiated, and execution-reliable steel building companies at scale in the industry."
Guidance & Commitments
| Commitment | Specifics | Timeline |
|---|---|---|
| FY27 revenue growth | Over 25% YoY growth | FY27 full year |
| Medium-term growth | More than 20% CAGR | Next 3 to 4 years |
| Sanand structural steel capacity | 10,000 tons/annum on stream, taking total to 22,000 metric tons | Q1 FY28 |
| Cheyyar brownfield expansion | Additional 20,000 tons/annum operational, taking combined capacity to 154,000 metric tons | Q3 FY28 |
| UK/Europe market entry | Commence business in the region | FY28 |
| US West Coast servicing | Service region from Cheyyar through Pacific route | Next fiscal (FY28) |
| Data center revenue recognition | Major part of first hyperscaler order to hit top line | Q4 FY27 |
| Export dispatches | "Much bigger jump" in H2 vs H1 | H2 FY27 |
| Export incentive | "Definitely be higher in H2" | H2 FY27 |
| Proflex equipment decision | Decision on specialized seam technology | Current quarter (Q3 FY27) |
Key Metrics
| Metric | Q2 FY27 |
|---|---|
| Revenue from operations | ₹385 cr, +25.4% YoY |
| H1 FY27 revenue from operations | ₹676 cr, +24.1% YoY |
| EBITDA | ₹43 cr, +17.6% YoY |
| EBITDA margin | 11.2% |
| Profit after tax | ₹29 cr, +32.8% YoY |
| H1 FY27 profit after tax | ₹51 cr, +27.5% YoY |
| Gross margin (H1 FY27) | ~32%, impacted by steel price variation |
| Order book | ₹1,109 cr, +19% YoY |
| Order inflows (Q2) | ₹441 cr, +12% YoY |
| Phenix division revenue | ₹298 cr, 77% of total, +22% YoY |
| Proflex division revenue | ₹87 cr, 23% of total, +37% YoY |
| Domestic revenue | ₹317 cr, 83% of total, +25% YoY |
| Export revenue | ₹67 cr, 17% of total, +25% YoY |
| H1 FY27 export revenue | ₹95 cr, +68% YoY |
| Total PEB manufacturing capacity | 124,000 MT/annum, up from 104,000 MT/annum post Sanand Phase 1 expansion |
| Cheyyar plant capacity utilization | 55–60% |
| Proflex capacity utilization | ~99% |
| Capex (Q2) | ₹43 cr |
| H1 FY27 capex | ₹70 cr |
| IPO proceeds utilized | ₹155.27 cr of ₹259.32 cr, 60% utilized as of Sep 30, 2026 |
| Peak freight cost | ~$12,000/container, now ~$7,000–$8,000 |