Megatherm Induction Ltd Q2 FY2027 Concall Summary

Source transcript PDF: https://assets.stockscans.in/docs/as-661fb1e8db205cc787b70492.pdf

Key Takeaways


The Gulf Disruption & Order Book

Chanda: "Yes, yes, actually we have been advised by a lot of people not to have those exact, you know, division-wise, because that gives a lot of information to competitors."

Transformer Vertical: The Investment Story

Chanda: "So in this first half report, it is all shown as cost. Nothing has been, uh, capitalized. Uh, if anything is, then that will appear in the, uh, second half, the audited, uh, uh, report. So broadly speaking, uh, not to look at the bottom line figures right now, especially considering growth in transformers and, uh, engineering verticals where a lot of R&D, training, manpower, marketing, all these things are going on."

Profitability: The Real vs Reported Picture


Market Positioning & Competitive Strategy

Chanda: "FY26 onwards- FY28, sorry- onwards, you are going to see most of the, uh, transformers stocks that are enjoying big profits and all that is going to again start squeezing because a lot of capacity enhancement is happening from everyone's side. So, so we are- we look at- Megatherm is looking at long-term businesses. We are not trying to capitalize on you know, any one area."

Guidance & Commitments

CommitmentSpecificsTimeline
FY27 revenueConfident of crossing ₹400 cr+ despite Gulf headwinds (original plan was ₹500+ cr)FY27
Transformer dispatchesAt least ₹80-90 cr of transformer dispatches targetedFY27
H2 revenue weightingH2 revenue expected to exceed H1, consistent with historical capital-goods seasonalityH2 FY27
Transformer undercuttingPhenomenon of deliberate price undercutting for market entry to last 6-10 months at most6-10 months from now
Phase 1 expansion revenue/EBITDARevenues and EBITDA from doubled transformer capacity to matureFY28 end onwards
Profitability normalizationTransformer vertical will not require undercutting; overall profitability may return to last FY levelsFY28
Steady-state EBITDA visibilitySteady-state EBITDA (transformers 12-15%, induction ~15%) becomes visible; EBITDA to grow faster than toplineFY29 onwards
NTPC approvalCommissioning of IDTs expected within 1-2 months, then 6 months of successful operation required for approval~7-8 months for full approval
Gulf order book conversionBig surge in orders expected once situation settles; ₹80-90 cr of orders already in handFY28
Inventory conversionManagement "pretty sure" of visible difference in inventory dispatches by H2 endH2 FY27 end
FY31-32 targets"Half" of the ₹950 cr topline / ₹150 cr EBITDA targets are "95%" confidentFY31-32

Key Metrics

MetricQ2 FY27
H1 FY27 revenue from operations₹195 cr
H1 FY27 growth~20% vs H1 FY26, despite Gulf headwinds
FY27 revenue target₹400 cr+, with original plan of ₹500+ cr; management confident of crossing planned targets
Missed turnover from Gulf region~₹40 cr lost, with ₹80-90 cr of orders stuck
Induction business growth~20% H1 FY27 vs H1 FY26
Additional export revenue from other markets₹10-12 cr from South America, Africa, etc.
Transformer dispatches target for FY27₹80-90 cr at least
Transformer production capacity₹120-150 cr depending on rating
H1 transformer revenue recognized~₹20 cr implied, with only 2-3 solar transformers dispatched in September at ₹80-90 lakhs each
Confirmed order pipeline for H2 transformers~₹50 cr at least
Spares after-sales and service EBITDA contribution28%
Steel side EBITDA contribution~10-12%
Transformer industry EBITDA range12-15%, with IDTs at ~12% and cast resin at ~15%
Current transformer overhead~18-20% vs typical 5-10% in steady state
Heating/hardening overhead~23% vs typical ~10%
Uncapitalized R&D/production/labor/marketing expenses in H1~₹2-2.5 cr for new product entries
Phase 1 project cost~₹39.7 cr including working capital, with CapEx of ₹25-27 cr
Total project cost (Phase 1 + Phase 2)~₹70 cr
Phase 1 capacity effectDouble transformer capacity from existing
Current finance cost~₹4-point-something cr, roughly 1-1.5% of turnover; may go to ~2%
Working capital inventory3-4 months of raw material
NTPC approval requirement6 months successful operation of minimum 40 MVA
Type test completed13.5 MVA; planned 20 MVA type test
Cast resin transformer capacity targetUp to 5 MVA in Phase 1, up to 12 MVA in Phase 2
HR increase in transformers3x
JV stake with SiCtech Spain49%
Previous FY27 revenue guidance (removed from presentations)₹450 cr revenue, ₹59 cr EBITDA
Previous FY28-29 revenue guidance₹605 cr revenue, ₹91 cr EBITDA
FY31-32 revenue guidance₹950 cr revenue, ₹150 cr EBITDA
Cast resin transformer market above 2.5 MVA~₹950 cr in India, growing fast
Solar transformer market~₹2,500 cr
Company transformer revenue target in 3-5 years₹250-300 cr
Legacy lower-price transformers remaining~10-odd transformers
CPRI test cost₹30-40 lakhs per test
Exhibition abroad cost~₹30 lakhs per exhibition
Transformer lead time1.5 to 2 months