- Flat top line, margin resilience: Revenue dipped ~1% YoY to ₹231 crore, yet EBITDA rose ~10% YoY, helped by a deliberate shift to higher recycled-scrap usage that cut raw material costs.
- The capex cycle is finally live: The wide plate mill and hot-extrusion seamless-tube line, inaugurated by the President in December, have shipped first products; the payoff is now a volume-ramp story, not a commissioning story.
- Order book is stuck in execution-gated limbo: The backlog has been flat since March because new bookings only match production; many export orders depend on quick delivery of a first order before a second will come.
- Titanium sponge supply is the quiet vulnerability: The Russia-Ukraine conflict has disrupted sponge supply from Russia, a large global producer; MIDHANI says it has filled the gap for now, but the scarcity on high-end materials is expected to continue.
- What to watch next quarter: Whether Q4, historically the best quarter, delivers the seasonal uplift management expects, and whether the new wide plate mill and Rohtak armor facility begin converting the cited ₹600 crore order visibility into booked revenue.
New Facilities: Commissioned, Now They Must Ramp
- Wide plate mill: The facility has produced nickel-based alloy (Hastelloy) plates, a product previously entirely imported, and cold-rolled sheets in similar grades; the capability to roll plates 2 meters and above puts MIDHANI among only four or five players globally.
- Seamless tubes by hot extrusion: The process was established and first dispatches made this quarter, opening a product category with applications across energy and aerospace.
- Armor and vehicles: Armor steel production is established, including very low-thickness plate; the vehicle armor facility is targeting 60–65 vehicles by Q4 end, with the team having participated in new tenders for very large quantities.
- Revenue ambition: Management is trying to target the previously indicated figure of ~₹500 crore per annum each from the wide plate mill and armor plant, but cites input-material availability and cost as the binding constraint on getting there.
- 10-ton VAR furnace: Still to be commissioned; once online, titanium manufacturing capacity will more than double.
Jha: "Prices of raw material I think it has established I mean stabilized, but there is some stabilization in the price, but today now only the price is a criteria in fact getting the raw material on time and getting the shipment and all is a big challenge and that also on the very high end materials definitely there is a scarcity and there is a problem in getting the materials in the future also and this is going to continue for some more time I do not know for how long..."
Order Book & Demand Visibility
- Flat backlog: The order book has stayed at a similar level from March to date because order booking has only matched production; many export orders are structured so that a second order will not arrive until the first is executed quickly.
- ₹600 crore visibility: Management cited visibility of another ~₹600 crore of orders across different directions, though segment-wise breakup was not provided.
- Where orders are expected: Energy, defense, aerospace, railways, armor, commercial, and 3-meter-wide stainless steel plate applications in oil and gas.
- Railway axles: 500 axles already supplied, another 1,000 under execution; a tender from CONCOR has been participated in; another ~18,000 axle numbers are floating in the market.
- Boeing certification unlocked: Boeing has assessed MIDHANI's capability and told its MSME and industrial partners they can buy raw material from MIDHANI; some parties have recently interacted and may come forward.
- Rolls Royce and Pratt & Whitney: Discussions ongoing; small orders are expected to start, though not in large volume initially.
- Lockheed Martin: Discussions continue but the company is not in a position to invest in the technological areas MIDHANI wanted to pursue; no indications of orders or raw material buying yet.
Jha: "we are depending on that how quickly you can executed the one order so that second will come. So, many orders are like that today"
Raw Material & Supply Chain
- Scrap strategy shift: Scrap usage in operations increased from ~40–45% to ~60% this quarter as part of a deliberate initiative to consume reverts and recycled material, saving on imported pure raw materials; scrap valuation has risen because underlying raw material costs have risen.
- The scrap floor: Management cannot push scrap levels much lower in the immediate future; certain strategic scraps cannot be recycled or sold due to national security considerations, and in high-end applications (satellites, missiles, aerospace) you cannot risk a mission to save a small raw material cost.
- Titanium sponge: Supply from Russia, a large global producer, has been disrupted by the conflict; MIDHANI says it has not been adversely affected yet because of persuasion and initiative at the right moment to fill the gap with other resources, and is getting good response from overseas OEM suppliers.
- Broader scarcity: High-end material supply problems are expected to continue for some more time, impacting any manufacturing industry dependent on imports.
Jha: "you cannot risk a satellite with just small saving because of raw material, you cannot take the risk on the missile by saving the small cost in the raw materials and same is the case for the aerospace also any aircraft."
Competition & Pricing
- Competitive intensity rising: Many players have entered special steel and nickel-based alloys; MIDHANI remains the only domestic player in titanium, but many orders are now taken on competitive bidding rather than nomination basis.
- Response: Management acknowledges the need to improve efficiency and cut production costs to stay competitive, while pointing to export potential and growing overall volumes as offsets.
- Product widening as defense: The company is deliberately entering new product segments so that dependency on one or two segments does not constrain future business; the wide plate mill, seamless tubes, and Super Alloy 276 are all part of this push.
Jha: "I will tell you many orders MIDHANI is now taking on the competitive bidding. We are not taking like on the nomination basis. So, we know that where we are today in terms of the price, in terms of our..."
Exports & New Product Opportunities
- Export target: Reach over ₹250 crore in exports in another two years; management calls it achievable but acknowledges brand-building in international markets requires credibility on quality, competitive pricing, and on-time delivery.
- Super Alloy 276: A grade developed for the energy sector; about ₹400 crore of this material is imported by BEHL, representing a direct import-replacement opportunity for MIDHANI.
- 3-meter stainless plates: The market for 3-meter-width stainless steel plates is assessed at ~₹2,000 crore; picking up even a part of that would be good value, with applications in gas walls and oxygen plants.
- Alloys Indianization: Many alloys have been developed for aircraft fleets of both Russian and Western origin; business is already coming up and expected to grow, with a big opportunity if those developments convert to orders.
- Space sector: The budget cut is for R&D only; space business is moving toward privatization (e.g., the L&T and HAL consortium taking an order for 5 PSLV), and new ISRO projects will flow to MIDHANI, which retains exclusive capability on many materials.
Jha: "In fact if you have might have seen the space budget is only for the R&D. What the space today policy is that they are diverting now the space business towards the private sector so I feel that as far as the investment in space is concerned it cannot be benchmark with the government allocation allocating the funds."
NALCO JV & Strategic Review
- Status: A reputable consultant was appointed to reassess market potential for the 60,000-ton flat products facility; a brief report has been submitted and more studies have been allotted.
- Decision path: The entire scenario will be reviewed at the highest level in the ministry before the JV's direction is decided; no timeline was given.
Guidance & Commitments
| Commitment | Specifics | Timeline |
|---|---|---|
| Q4 seasonal uplift | Q4 is historically the best quarter; management expects to achieve more business with additional facilities (WPM, Rohtak) and hopes to beat last year | Q4 FY23 |
| Vehicle armor production | Targeting 60–65 vehicles by Q4 end; new large-quantity orders participated in | Q4 FY23 |
| Export revenue | Reach over ₹250 crore in exports | Within two years |
| Titanium capacity | 10-ton VAR furnace to be commissioned, more than doubling current titanium manufacturing capacity | Not specified |
| Railway axles | ~18,000 additional axle numbers floating in the market; orders to be communicated as received | As and when orders come |
| NALCO JV decision | Consultant studies to be reviewed at highest ministry level before deciding JV direction | After consultant completes studies |
| Wide plate mill and armor plant revenue | Trying to target previously indicated ~₹500 crore per annum each, subject to input material availability and cost | FY24 (aspirational, not guided) |
Key Metrics
| Metric | Q3 FY23 |
|---|---|
| Revenue | ₹231 cr, vs ₹234 cr in Q3 FY22 |
| EBITDA growth | ~10% YoY |
| PBT | Slightly decreased YoY, higher financial costs and depreciation from new equipment commissioning |
| Value of production | Increased QoQ, decreased YoY |
| Scrap usage in alloy-making | ~60%, up from ~40–45% earlier |
| Order book visibility | ₹600 cr additional visibility exists |
| Order book – Space | ~50% of order book |
| Order book – Defense | ~30–35% of order book |
| Order book – Energy and exports | Balance of order book |
| Axles supplied to date | 500 axles supplied, another 1,000 under execution |
| Vehicle armor execution target | 60–65 vehicles by Q4 end, out of >100 on order |
| Export revenue target | Over ₹250 cr in another two years |
| Wide plate mill market opportunity | ~₹2,000 cr assessed Indian market for 3-meter width stainless plates |
| Super Alloy 276 import replacement opportunity | ~₹400 cr material imported by BEHL, direct replacement potential |
| Titanium capability post 10-ton VAR | More than 2x current manufacturing |