Midwest Ltd Q2 FY2027 Concall Summary

Source transcript PDF: https://assets.stockscans.in/docs/kprc2g4c5zrdqjd0thdbjj60.pdf

Key Takeaways


Quartz: The Inflection Quarter

Ram Kollareddy: "But our concern, frankly, for this quarter was the oil tariff that U.S. was going to impose on India and China. And keeping that in mind, we started positioning the product to other countries also. We're not waiting for that."

Rare Earth: Three Projects, One Timeline

Ram Kollareddy: "even if the world doubles their production, they'll be only able to meet that increase. They'll still not be able to touch the baseline."

Granite & Base Business


Margins, Costs & Pricing

Uma Kollareddy: "In fact, because we've increased this pricing, and post settling down, post the US elections and post, if the fuel prices come back to the ordinary range, we will not roll back on the pricing. So that positive impact in pricing is there to stay."

Cash Flow & Working Capital


Sustainability & Cost Transformation


Guidance & Commitments

CommitmentSpecificsTimeline
Quartz PAT profitabilityQuartz business to be PAT positive for full yearFY27
Quartz Q3 monthly volume12,000–15,000 tons per monthQ3 FY27
Quartz Q4 monthly volume35,000–40,000 tons for the full quarterQ4 FY27
Quartz FY27 revenue~₹90 cr, could reach ₹100 cr if 15,000-ton mark hit early JanuaryFY27
Quartz Phase 2 regular commissioningBuilding started, machinery orderedQ2 next year
Quartz Phase 2 HPQ commissioningHPQ line operationalQ3/Q4 next year
Phase 2 capex spendEntire ₹120 cr spentNext four quarters
Granite revenue growth~14%–15% (10%–12% volume + 3%–4% currency)FY27
Sri Lanka ground breakPermissions expected this quarter, building start next quarterNext quarter onwards
Indonesia definitive agreementOn track to signThis quarter
Indonesia ground workStart after agreement signedNext quarter
Electric fleet conversionEntire fleet to electric trucksNext 24 months
Solar power expansionIncrease by several megawatts via group captive modelOngoing, plant completing this FY
Mine rectificationHigh-wall issue at Galaxy mine resolved5–6 weeks from now
Working capital daysCome down as no additional domestic credit extendedComing quarters
3–4 year targets2.5x revenue growth, 3x profitability, 35% ROCE, backed by ₹300 cr capex3–4 years

Key Metrics

MetricQ2 FY27
Revenue₹182 cr, +15% QoQ and +9% YoY
H1 FY27 revenue growth24% YoY
H1 FY27 PAT growth18% YoY
Consolidated PAT margin16.37% (H1), dragged by negative contribution from quartz
Granite standalone H1 PAT margin~18%
Leverage ratio0.2x
Granite volume growth~7% YoY (Q2); 14% (H1)
Granite revenue growth expectation (FY27)14%–15% (volume 10%–12% plus currency 3%–4%)
Quartz volume16,000 tons (Q2); Q3 estimate 25,000–30,000 tons; Q4 estimate 35,000–40,000 tons
Quartz revenue₹13.5 cr (Q2); FY27 guidance revised to ~₹90 cr
Quartz realization~₹8,500/ton (Q2); full-year average expected ₹9,500–₹9,600/ton
H1 quartz EBITDA margin~12%
Granite realization – Black Galaxy export~₹88,000/cubic meter
Granite realization – Absolute Black~₹39,000–₹40,000/cubic meter
Granite realization – Black export (higher grade)~₹1 lakh/cubic meter
Working capital cycle127 days (H1 FY27), up from 104 days in FY26
Cash flow from operationsNegative (H1 FY27), driven by ~₹25 cr receivables, ~₹14 cr inventory build, ~₹20 cr trade payable settlements
Electric truck fleet10 trucks deployed, saving ₹2–2.5 cr/year; total fleet ~50–60 trucks in granite mines
Captive solar power6 MW tied up, saving ~₹2 cr/year; combined savings with trucks ₹4–5 cr/year
Capex plan₹300 cr total; Phase 2 quartz ~₹120 cr to be spent over next four quarters
Natural stone share of H1 revenue19%
Fuel cost increase (H1 FY27 vs H1 FY26)30%–35%; passed on to customers via pricing, dollar added ~4% extra realization