Key Takeaways
- Granite steady, Quartz drags consolidated PAT: Granite standalone PAT improved to 17.47%, but consolidated PAT fell to 16.49% as Quartz stabilization costs of ~INR6 crores weighed on the bottom line.
- Logistics snafu masks underlying demand: 4,000-5,000 CBM of granite (~INR25 crores) could not ship in the last week of Q4 due to war-driven logistics cost spikes and vessel shortages, depressing reported revenue.
- Quartz Phase 1 turns the corner: Full production began last month after resolving initial technical glitches; the plant is now ramping from 5,000 to a targeted 10,000 tonnes per month, with 60% capacity utilization guided for the year.
- The pipeline is now multi-project and multi-year: A new 30-year granite lease, the KMML Rare Earths pilot, the HPQ/Phase 2 plant build, and the Sri Lanka HMS license pursuit all advanced this quarter, laying the foundation for a stated 2.5x top-line ambition over 3-4 years.
- What to watch next quarter: Whether Quartz Phase 1 hits its 10,000-tonne monthly run-rate, any update on the Sierra Leone concessions, and the KMML pilot plant's progress once equipment orders land.
Quartz: The Inflection Quarter
- Phase 1 stabilized: The plant reached full production last month after resolving initial technical and quality issues that had forced reprocessing of early output. Only 1,000+ tonnes were sold in Q4 against 3,000-4,000 tonnes produced, resulting in turnover of just INR1.8 crores.
- Ramp is now the focus: Production is targeting 5,000 tonnes this month, 10,000 tonnes next month, and at least 60% of rated capacity (1.5 lakh tonnes) for the full year, with quarter-on-quarter improvement.
- Phase 2 construction underway: Building started in April; the plant adds 300,000 tonnes of capacity and includes HPQ for semiconductor and solar crucible industries. Commissioning is targeted by Q4 of this fiscal year, with revenue in Q1 next year.
- HPQ is market-ready: Crucible manufacturers in China have already approved the product for off-take. Management expects to start with 20,000 tonnes and can ramp fast post-commissioning, though India's market is 2-3 years away.
- Product mix shifts with Phase 2: Phase 1 is set for 70% engineered stone (INR9,000-14,000/tonne) and 30% solar glass (INR7,000/tonne). Phase 2 flips to 70% solar glass and 30% engineered stone, with flexibility to adjust.
- Margin trajectory hinges on utilization: Once Phase 1 crosses 60% capacity and approaches 70%, management expects healthier margins than the current business as fixed costs optimize. Phase 2 stabilization will be faster due to Phase 1 learnings.
Ram Kollareddy: "Technically, you don't need to specifically, though we have checked with couple of customers, this is a marketable product as it is as long as you're meeting those specs."
Granite: Demand Intact, Logistics Interrupted
- The Q4 miss was a shipment problem, not a demand problem: Granite segmental revenue fell YoY from INR226 crores to INR214 crores because 3,000+ CBM could not be shipped in the last week of March. War-driven logistics price increases and vessel shortages blocked conversion of production to sale.
- Underlying demand is strong: Management expects Galaxy and Black varieties to remain easily absorbed, guiding 10-13% consistent growth for the segment, with 10-12% on the pessimistic side.
- A new 30-year lease adds low-cost volume: The Galaxy quarry lease obtained in January started production and recognized revenue in the same quarter. It is a neighboring block sharing equipment, targeting 10,000-12,000 CBM and INR70-80 crores in revenue.
- Market repositioning is a tailwind: Post-tariffs, Egypt and Algeria have shifted from buying slabs to buying blocks directly from Midwest, removing an intermediary layer and creating direct export sales.
- Margins are stable and defended: Granite standalone EBITDA improved marginally to 27.55% (from 27.43%) on cost initiatives including renewable energy conversion. Management expects margins to be very stable, if not improving, year-on-year.
- Energy costs are being attacked structurally: Fuel costs rose 4-5%, but export prices have been renegotiated up 4% for the coming year, and management assumes dollar support will more than compensate. The company is also converting equipment to EV and building a 0.6 MW captive solar plant.
Ram Kollareddy: "in Egypt and Algeria are two countries we have seen aggressive buying of blocks which they were buying slabs otherwise. Now this is a direct sale to us."
Rare Earths & Heavy Minerals: The Strategic Optionality
- KMML pilot is a first-of-its-kind milestone: Midwest was selected as consortium partner by Kerala Minerals and Metals Limited for monazite Rare Earths, making it the first private company in India to handle monazite and produce Rare Earth oxides. The six-month pilot plant starts in July with an INR20 crores budget.
- Pilot paves the way for commercialization: The plant will be ready 4-5 months post-July, followed by 1-2 months of data and yield validation. Post-pilot, the state government is expected to commercialize immediately, with a commercial plant taking roughly a year and first oxides expected after that.
- Sri Lanka HMS is advancing through approvals: The exploration license has been submitted with all paperwork complete. Once the new government policy is approved (expected June), a mining license is targeted for July, and plant construction could start as early as August with a 9-month to 1-year build.
- The oxide gap is the strategic thesis: Management sees the world needing more and more oxides and views this as a niche space where significant unlock is happening in India. The focus is on oxide production rather than downstream magnets, though the PLI scheme for magnets is being studied seriously.
- Thorium is a longer-dated call option: Government clarity on whether to stockpile or commercialize thorium is expected in the next year. Midwest's ability to refine oxides gives it the capability to refine thorium as well.
Uma Kollareddy: "we are the first ones to put up our pilot plant in the country in for KMML. So we'll be the first person to... have the first right of refusal for a plant there."
Diamond Wire: Small but Profitable
- Revenue scaled meaningfully: Diamond wire revenue grew to INR25 crores from ~INR16 crores, with a ~15% PBT margin.
Costs, Energy & the Margin Bridge
- Consolidated PAT was dragged by Quartz: The ~INR6 crores of Quartz segment costs (technical glitches, fixed costs, depreciation, finance costs during stabilization) pulled consolidated PAT to 16.49% from 17.17% a year ago.
- Fuel is a headwind being offset: Fuel costs rose 4-5% overall. Management renegotiated export prices up 4% and expects dollar support to more than compensate.
- Structural cost reduction is underway: The company is converting dump trucks and equipment to EV, experimenting on excavators this year, and placing orders for a 0.6 MW captive solar plant with additional capacity under discussion. The flip to more green and less fossil may happen in the next two years.
The 3-4 Year Vision
- A 2.5x top-line ambition: Management laid out a 3-4 year vision targeting ~INR1,100 crores in revenue from three project clusters: Granite at ~INR1,000 crores, Quartz (two phases plus HPQ) at ~INR400 crores, Sri Lanka HMS Phase 1 at ~INR350-400 crores, and KMML at ~INR200 crores.
- The strategy rests on oxide scarcity: All pointers, per management, point toward the world needing more and more oxides, positioning Midwest in a niche space where significant unlock is happening in India.
Ram Kollareddy: "all the pointers are towards one direction, we need more and more oxides, the world needs more and more oxides. It's a niche space that we are in and lot of unlock is happening in India."
Guidance & Commitments
| Commitment | Specifics | Timeline |
|---|---|---|
| Quartz Phase 1 capacity utilization | Reach at least 60% of rated capacity (~1.5 lakh tonnes) | This fiscal year |
| Quartz Phase 1 monthly ramp | 5,000 tonnes this month, 10,000 tonnes next month | Current and next month |
| Phase 2 plant commissioning | Construction complete, revenue in Q1 next year | Q4 this fiscal year |
| Phase 2 peak production | 75-80% of rated capacity | Post-stabilization |
| HPQ first product | After Phase 2 commissioning; traditional engineered stone and solar first | Quarter after Phase 2 commissioning |
| Granite segment growth | 10-13% consistent growth (10-12% pessimistic) | Ongoing |
| KMML pilot plant | 6-month project; plant ready in 4-5 months post-July, then 1-2 months data validation | Starts July; oxides ~1 year after commercial plant |
| Sri Lanka HMS mining license | Targeted for July, subject to policy approval in June | June-July |
| Sri Lanka HMS plant construction | 9 months to 1 year build | Could start August |
| Granite margins | Very stable, if not improvement YoY | Ongoing |
| Quartz margins | Healthier than current business once crossing 60% utilization toward 70% | As utilization ramps |
| New Galaxy quarry lease | INR70-80 crores revenue from 10,000-12,000 CBM | Ongoing |
Key Metrics
| Metric | Q4 FY26 |
|---|---|
| Consolidated revenue | ₹215 cr, +3% YoY to ₹645 cr for full year |
| EBITDA margin | 27.0%, vs 23.7% in Q3 FY26; full year 27.01% vs 27.43% in FY25 |
| PAT margin | 17.16%, vs 13.48% in Q3 FY26; full year 16.49% vs 17.17% in FY25 |
| Granite standalone EBITDA margin | 27.55%, vs 27.43% in FY25 |
| Granite standalone PAT margin | 17.47%, vs 17.17% in FY25 |
| Granite segment revenue | ₹214 cr in Q4, down from ₹226 cr in Q4 FY25; full year ₹645 cr vs ₹626 cr |
| Quartz segment revenue | ₹1.8 cr in Q4, volume sold 1,000+ tonnes |
| Quartz cost drag on consolidated PAT | ~₹6 cr, reducing consolidated PAT from ₹112 cr (granite standalone) to ₹106 cr |
| Diamond wire segment revenue | ₹25 cr, vs ~₹16 cr in FY25; PBT margin ~15% |
| Debt reduction | ₹50 cr during FY26 |
| Working capital days | 104 days, improved from 122 days |
| Quartz Phase 1 production target FY27 | ~1.5 lakh tonnes (60% of 2.5 lakh-tonne benchmark capacity) |
| Quartz Phase 2 capex | ₹125–130 cr, commissioning expected Q4 FY27 |
| New Galaxy granite lease revenue potential | ₹70–80 cr annually, from 10,000–12,000 CBM |
| Export price increase negotiated for FY27 | 4% increase to offset fuel cost impact of 4–5% |
| KMML Rare Earths pilot plant budget | ~₹20 cr, 6-month project starting July 2026 |