Motherson Sumi Wiring India Ltd Q1 FY2024 Concall Summary

Source transcript PDF: https://assets.stockscans.in/docs/6klijzoxoe89jnppweuidulm.pdf

Key Takeaways


Margin Walk

Sehgal: "By the time you get the recovery for the last thing, you already have another negotiation started for the next particular thing. There are many moving parts in that."

Customer Demand & Supply Chain

Sehgal: "There is no lack of intention by the customers to produce. If they can produce even one car more, they will. But there are so many moving parts, Kapil, and that is something that you have to understand."

EV & New Business


Cost Pass-Through & Negotiations


Guidance & Commitments

CommitmentSpecificsTimeline
EV revenue disclosureManagement will consider sharing EV revenue numbersFrom next quarter (Q2 FY24)
New plant utilisation improvementCapacities to start getting better utilised, subject to customer plans being metBy end of Q1 next year
Cost pass-through recoveryContinuous negotiation; best assessment point is year-endYear-end culmination

Key Metrics

MetricQ1 FY24
RevenueNot stated
Operating marginNot stated
Profit after taxNot stated
Raw material cost as a percentage of salesDeclined QoQ, driven by product and content mix
CAPEX guidance for FY24₹125 cr, excluding land and building
ROCE target>40%, achieved in the last financial year
New plant utilisation (Plant 1)~55%+, expected to add another 10%–15% in Q2
New plant utilisation (Plant 2)~80%
New plant utilisation (Plant 3)50%–55%, expected to grow in coming quarters
EV revenue shareNot disclosed, described as very small
Wage inflation impactEffective 1st April increase factored in; further state minimum wage changes uncertain
Commodity pass-throughCopper and exchange rate impacts passed through, with a quarter or half-year lag for some customers