Key Takeaways
- Revenue surged 47% YoY, guidance held: Q3 revenue of ₹174.5 cr kept the company on track for its ₹700 cr-plus FY25 target, with Q4 expected to be even stronger.
- A ₹1,000 cr nuclear order pipeline is the story: Management expects orders of this magnitude over the next 3–6 months, spanning the Kaiga 5 & 6 new-build and five refurbishment reactors, a volume it says has never happened before.
- FY26 growth anchored at 30%: The company guided for 30% revenue growth next year, with Clean Energy alone set to execute over ₹430 cr, and laid out a three-year margin path to 28% EBITDA.
- New verticals are being seeded now for FY27 volume: First articles are underway for IAI, Fluence, and Weatherford, while a dedicated aerospace plant commissions this month; management points to FY27 for the major volume breakthrough.
- What to watch next quarter: Whether the promised ₹500 cr-plus Kaiga 5 & 6 order lands by end of March or early Q1, and the pace of the Q4 margin recovery toward the 24% exit rate needed to hit the full-year guide.
Nuclear: The Order Pipeline
- Kaiga 5 & 6: The LOA has been issued to Megha Engineering, and MTAR expects its orders by end of March or beginning of next quarter, worth more than ₹500 cr. Execution is a fast-track project with a maximum 3-year timeline.
- Refurbishment reactors: Tenders for five reactors (Tarapur 2, Rajasthan 1, Kaiga 1, MAPS 1) are being floated shortly, with MTAR quoting in the next month or two. Execution timeline is 18 months per reactor.
- Revenue phasing: Part of the nuclear revenue will grow in FY26, but the majority lands in FY27 and FY28. Management sees enough order books from the nuclear division over a 3–5 year roadmap.
- Capacity readiness: Existing capacities are already in place with only a few bottlenecks to address; the company is considering an exclusive plant for the nuclear division given the order flow.
Srinivas Reddy: "Overall, we're expecting close to 1000 Crs of orders, in history, it never happened, but finally, it's happening now. Close to about INR1,000 crores of orders, which can flow into MTAR over the next 6 months."
FY26 Growth Build-Up
- Clean Energy fuel cells: Over ₹430 cr execution expected in FY26, with the majority of orders already received and upside possible from Bloom Energy's AEP deal (up to 1 GW). Hot boxes alone are projected at close to ₹470 cr.
- MNC aerospace: ~₹125 cr projected for FY26, a mix of first articles and initial batch production. The dedicated Hyderabad aerospace facility commissions at the end of this month, with NADCAP and customer certifications underway.
- Products vertical: ₹170–180 cr revenue expected, continuing a significant growth trajectory after ~₹100 cr YTD in FY25.
- ISRO and Defence: ISRO projected at ~₹50 cr; Defence at ₹40 cr-plus with exponential growth starting from FY26, supported by L1 status in some projects and a development order for scramjet engine combustors.
- Civil Nuclear: ~₹75 cr projected for FY26, with work-in-progress already built for existing orders to be dispatched in the year.
Srinivas Reddy: "FY '27, you would really see a major volume breakthrough, especially in MNC aerospace sector, since our new plant is getting commissioned at the end of this month."
New Verticals: Seeding for FY27
- Oil & gas: Purchase orders received; an exclusive plant is being established requiring ₹60–80 cr capex over the next 9 months. Volume production begins partly in FY26 but mostly in FY27, with ₹150–180 cr expected in the first year.
- Battery storage with Fluence Energy: Purchase orders received for a new battery storage system; prototypes are expected to complete by June, after which the company will slowly move into volume production.
- IAI long-term agreement: A 15-year agreement signed; ₹28–30 cr in orders received so far this fiscal for first articles across various project groups.
- Weatherford and GKN: First articles underway for Weatherford; GKN is doing a combination of volume production and further first articles, with volumes expected to ramp significantly from FY26.
- Roller screws: Qualification completed; import substitution certification expected from next month, with final tests ongoing.
Margins & Balance Sheet
- Q3 margin and the Q4 bridge: EBITDA grew 39.4% YoY to ₹33.3 cr, but margins were impacted by mix. Q4 EBITDA margin is expected at 24% plus-minus 100 bps to achieve the full-year guidance of 21% plus-minus 100 bps.
- Three-year margin path: Management laid out a trajectory of 24% EBITDA in FY26, 26% in FY27, and 28% in FY28, a 200 bps improvement each year driven by operating leverage and scale.
- Employee cost leverage: The company has been investing in team leadership over the last year ahead of future growth; as revenues grow, employee benefit expenses will "drastically drop" as a percentage of revenue.
- Working capital and cash flow: Operating cash flow of ₹102 cr significantly outpaced FY24's full-year total of ₹57.4 cr, driven by ₹58 cr from reduced receivables and increased payable days. Net working capital days reduced to 222, in line with the FY25 target, with a projection of 225 days by year-end.
- Debt: Long-term debt reduced by ₹10 cr to ₹132.5 cr. The company will take ₹60–80 cr in debt next year for oil & gas and other areas, with the remainder funded from internal accruals; the aim is to reduce debt overall.
- Margin floor: Across all divisions, the company does not normally take less than 20% margins. Space carries 5–7% more due to free-issue raw material; Bloom was a lower-margin segment historically.
Gunneswara Rao: "Less than 20% margins we don't take normally. But in case of space, we have little bit more margins, say around 5% to 7% because of the free-issue raw material."
Clean Energy & Bloom Energy Dynamics
- Data center demand intact: Management dismissed any impact from DeepSeek on Bloom's data center business, stating Bloom is looking at improved volumes and that MTAR is increasing its wallet share by moving into the assembly mode.
- Fuel cell execution: ₹304 cr executed YTD in Clean Energy; Bloom's AEP deal (up to 1 GW) provides strong demand visibility, with AI data centers seen as a major growth driver.
- Electrolyzer timing deferred: Management acknowledged hydrogen will happen but said it will take time, offering no timeline and declining to comment further. On PLI scheme participation, the response was a non-committal "as and when we get the orders... probably yes."
Srinivas Reddy: "Absolutely not. And I have not heard anything of that. In fact, not only they are looking at improved volumes, which they will keep updating us from time to time. And also, we are increasing our wallet share within -- we're moving it to the assembly mode as well with that."
Guidance & Commitments
| Commitment | Specifics | Timeline |
|---|---|---|
| FY25 revenue | ₹700 cr-plus | FY25 full year |
| FY25 EBITDA margin | 21% plus-minus 100 bps | FY25 full year |
| Q4 FY25 EBITDA margin | 24% plus-minus 100 bps | Q4 FY25 |
| FY26 revenue growth | 30% growth | FY26 full year |
| FY26 Clean Energy execution | More than ₹430 cr | FY26 full year |
| FY26 MNC aerospace revenue | ~₹125 cr | FY26 full year |
| FY26 Products revenue | ₹170–180 cr | FY26 full year |
| FY26 EBITDA margin | 24% | FY26 full year |
| FY27 EBITDA margin | 26% | FY27 full year |
| FY28 EBITDA margin | 28% | FY28 full year |
| Kaiga 5 & 6 orders | More than ₹500 cr | By end of March or beginning of next quarter |
| Total nuclear orders | Close to ₹1,000 cr | Over the next 3–6 months |
| Oil & gas volume production | ₹150–180 cr in first year | Mostly in FY27 |
| Net working capital days | 225 days | By FY25 year-end |
| Oil & gas facility capex | ₹60–80 cr debt-funded | Over next 9 months |
Key Metrics
| Metric | Q3 FY25 |
|---|---|
| Revenue from operations | ₹174.5 cr, 47.4% YoY growth from ₹118.4 cr in Q3 FY24 |
| EBITDA | ₹33.3 cr, 39.4% YoY increase from ₹23.9 cr in Q3 FY24 |
| EBITDA margin | 19.1% (per an analyst's math), FY25 full-year guidance of 21% plus-minus 100 bps |
| Profit before tax | ₹21.4 cr, 66.3% YoY growth from ₹12.9 cr in Q3 FY24 |
| Profit after tax | ₹16 cr, 52.8% YoY increase from ₹10.4 cr in Q3 FY24 |
| FY26 revenue growth guidance | 30%, with similar growth expected for the next 2 years |
| FY26 EBITDA margin guidance | 24%, with 200 bps improvement each year to reach 28% by FY28 |
| Clean Energy fuel cells executed YTD | ~₹304 cr, comprising power units, heat cycle assemblies and enclosures for Bloom Energy |
| Clean Energy fuel cells FY26 projection | More than ₹430 cr, majority of orders already received |
| Space and MNC aerospace closing order book | ₹187 cr at end of Q3 |
| MNC aerospace FY26 execution projection | ~₹145 cr, combination of first articles and volume production |
| Civil Nuclear Power FY26 execution projection | ~₹75 cr, backed by work-in-progress for existing orders |
| Products vertical FY26 revenue projection | ₹170 cr to ₹180 cr |
| Operating cash flow | ₹102 cr positive in Q3 FY25, exceeding FY24 full-year operating cash flow of ₹57.4 cr |
| Net working capital days | 222 days at end of Q3, projected at 225 days by FY25 end |
| Long-term debt | ₹132.5 cr, reduced by ₹10 cr during the quarter |