National Aluminium Company Ltd Q3 FY2025 Concall Summary

Source transcript PDF: https://www.stockscans.in/document/n3zh2qpvad28ycz68yfbfrhp.pdf

Key Takeaways


Alumina: The Price Cycle and Realization Mechanics

Bijendra Pratap: "We are confident enough by December, we will be finishing and starting the trials of the commissioning."

The Expansion Roadmap: Refinery, Smelter, and Power

Bijendra Pratap: "we have requested EIL to make a study. It cannot come, as it is. We'll have to do some investment, maybe adding some pots and increasing maybe some captive power also. With small investment, we can have this increase in the capacity of the total overall cast metal."

Coal: The Quiet Margin Story

Bijendra Pratap: "So whatever coal we were taking through e-auction, that will not be required to take the auction coal, and all will be produced through this full Utkal D & E."

Financing the Growth: Debt, CAPEX, and Returns

Srimanta Panda: "if we are ending the FY with more than 17,000 or 17,500 net worth, the company will be in a very good position to finance the entire CAPEX up for, metal and, power plant expansion through external financing."

Market Context and Demand

Manie Ravi: "The consumption in India on 2023 - 2024 is about 0.49 crore tons and going by the estimates and the market analysis by 2030 in India is estimated that this particular consumption would increase to about 0.83 crore tons per annum."

Costs, One-Offs, and the Lithium Option


Guidance & Commitments

CommitmentSpecificsTimeline
Fifth-stream refinery commissioningTrial commissioning start; commercial volumes from AprilBetween September and December (FY25 end)
Pottangi mines startMDO appointment orders by May–June; mines operationalSeptember to December
Refinery expansion first-year output~5 lakh tons, ramping to 0.1 crore tons rated capacityFY27
Refinery expansion utilization60–70% utilization (7–8 lakh tons)FY27
Utkal D & E coal production~0.4 crore tons; e-auction coal eliminatedNext financial year
Smelter expansion commissioning0.05 crore tons per annumFY29–30
Captive power plant commissioning~1,200 MW at smelter locationFY29–30
Smelter CAPEX phasing~10–15% of totalFY27
Smelter CAPEX phasing25–30% per yearSubsequent two–three years
Total CAPEX next year~₹2,000 croresFY26
Maintenance CAPEX₹700–₹800 crores continuingOngoing
Debt-equity ratio for expansion70:30Through expansion period
KABIL lithium exploration resultsNon-invasive results25th March
KABIL lithium mining investment decisionSubject to exploration and pilot plantMid-2027
Volume growth5–10% increase via refinery modificationsNext year
Employee cost₹2,100–₹2,200 crores stableOngoing even after expansion

Key Metrics

MetricQ3 FY25
Revenue from operationsHighest ever, turnover ₹11,434 cr for nine months, +20% YoY
Profit after tax (standalone)₹1,583 cr, +224% YoY vs ₹488 cr in Q3 FY24
Profit before tax (standalone)₹2,122 cr, vs ₹668 cr in Q3 FY24
Cumulative PAT (nine months)₹3,246 cr, +211% YoY vs ₹1,044 cr
EBITDAHighest ever quarterly and nine-month EBITDA since inception
Interim dividend₹4 per share (second interim), total ₹8 per share for FY25, highest ever
Alumina average realization\$641 per ton, nine-month average \$562 per ton
Alumina sales volume0.38 crore tons (export 3.66 lakh tons, domestic 3.09 lakh tons)
Alumina cost of production₹21,000–₹22,000 per ton, including depreciation
Aluminium cost of production₹1,60,000–₹1,65,000 per ton, including depreciation, alumina transferred at cost
Employee cost₹2,000–₹2,100 cr annual run rate, nine-month cost down ~₹150 cr on one-time PRP provision
Coal sourcing mix (nine months)49% linkage, 47% captive, 4% e-auction
CAPEX incurred (current year)~₹1,500 cr expected, against plan of ~₹2,000 cr
Refinery expansion physical progress70% complete, ₹3,500 cr spent of ₹5,677 cr total
CWIP closing balance~₹4,500 cr as of 31st December
Depreciation (Q3)₹2.86 cr, includes ₹106 cr impairment provision for Rajasthan wind power plant