National Aluminium Company Ltd Q1 FY2026 Concall Summary

Source transcript PDF: https://www.stockscans.in/document/rnuvt2wqodgakc30fo9i398l.pdf

Key Takeaways


Production & Volume Growth

Singh: "Whatever commitment we have given earlier that we will be starting the commissioning, all mechanical jobs will be completed may be by March, 26 and we will try to start all commissioning thing after that and try to start the production by June, 26. That is the commitment we have given earlier also and we stand by it."

5th Stream Refinery: The Margin & Volume Catalyst

Singh: "cost of the alumina produced in this new, our new 5th stream refinery expansion, that will be almost similar to the cost which we are producing now. Because, of course, interest is not there. We are not taking any loan for that. Depreciation will be loaded, but that will be made offset by the industry technology."

Alumina & Aluminium Markets


Value-Added Product Strategy

Singh: "if you are selling ingots we are heavily dependent on the LME. So if you want to insulate ourself from the LME the fluctuations of the LME and get the premium in the market it is very important that we go in for increasing the volumes of wire rods, rolled products and also going into the foil markets."

Costs: Coal Advantage, Caustic Soda Pressure & RPO

Behuria: "We expect reduction in our cost because our performance parameter has improved well. The key consumables caustic soda is the other parameter we have a great control over that. So, we expect that our cost will come down at the end of the year."

Growth Projects & Renewable Energy

Singh: "after that only this overall turnover of the company will go above 25,000 to become a Maharatna company, that is our target and with all the things going we are hoping whatever we are planning we'll be able to do it."

Guidance & Commitments

CommitmentSpecificsTimeline
5th stream refinery mechanical completionAll mechanical jobs completedBy March 2026
5th stream refinery commercial productionProduction startJune 2026
5th stream FY27 outputAt least 5 lakh tonnes (50% of rated capacity)FY27 (9 months of operation)
5th stream full ramp-upReach rated capacity of 10 lakh tonnesWithin 3–6 months of start
Pottangi bauxite mines operationalCapacity increase of 0.35 crore tonnesFebruary/March 2026, latest May/June 2026
FY26 alumina production~23 lakh tonnes (vs 22.5 lakh tonnes planned)FY26
FY26 alumina exports41–42 shipments (vs 36 last year)FY26
Brownfield smelter land acquisitionAll formalities completed4–6 months
Brownfield smelter DPR consultant appointmentConsultant onboarded2–3 months
Brownfield smelter DPR completionReady for Board approval7–8 months
New wire rod mill1 lakh tonne capacity, ₹200–300 crores CAPEX~2 years
Rolled product annealing furnaceProduction increase from 2,000 to 3,000 tonnes/monthMarch 2026
Aluminium foil entryConsultant appointed, ₹150–200 crores investmentPresence in 2–3 years
Wind power commissioning10 MW at KayatharSeptember/October 2025
Hybrid renewable roadmapSolar + wind + battery storage plan fixed3–4 months
Green power portfolio targetAt least 15–20% of totalBy 2030
Brownfield smelter & CPP onlineFull project commissioningFinancial year 2030
Maharatna turnover thresholdOverall turnover above ₹25,000 croresNo date; contingent on smelter expansion

Key Metrics

MetricQ1 FY26
Revenue growth33% YoY
PAT growth77% YoY
Other expenses₹707 cr, elevated due to RPO obligations of ~₹70–75 cr, higher coal transportation, and increased repair maintenance
Final dividend recommended₹2.50 per share
Alumina cost of production₹20,000–21,000 per ton, 60% variable, balance fixed
Aluminium cost of production₹1,55,000–1,60,000 per ton average, varies by product basket
Caustic soda landed cost₹44,301 per ton, up from ₹36,300 in Q1 FY25
Alumina realization~$416 per ton average; spot currently ~$400, expected $400–$450 in coming quarters
Bauxite production growth6.6% YoY
Alumina Hydrate production growth35% YoY, partly due to base effect
Metal production growth3% YoY
Metal sales growth9% YoY
Alumina run rate~23 lakh tons
Aluminium run rate4.6 to 4.7 lakh tons
Bauxite run rate~76 lakh tons
Captive coal production~4 MT (Utkal D&E mines), total requirement ~7.2 MT, balance from MCL
Coal cost advantage (own vs MCL)~₹400 per ton plus transportation savings
RPO obligation cost~₹70–75 cr for FY25, obligation 29.4% of electricity consumption; FY26 obligation 33%
Alumina export spot vs long-term mix80% spot, 20% long-term
Domestic alumina sales share~15% of total volume
5th stream refinery expansion progress74–75% physical progress; commissioning targeted June 2026
Pottangi bauxite mines capacity addition0.35 crore tons, operations expected by May–June 2026
Green power target15–20% of portfolio by 2030