National Aluminium Company Ltd Q1 FY2027 Concall Summary

Source transcript PDF: https://www.stockscans.in/document/k6xae13z5izdwslt5ccevoq9.pdf

Key Takeaways


Production & Cost Dynamics

Singh: "It is very difficult to exactly pinpoint the date of commissioning and all that, and it's a chemical process plant. So now our -- maybe by September end, we are targeting the mechanical completion will be there and we'll start. There is almost 2, 3 months delays there, not very huge delays there."

Alumina: The Surprise Offset

Singh: "We had a few tenders in which the percentage was very low. It was coming around 10% of the LME. That's why we canceled that tender because spot prices we are getting better."

Aluminum: Premiums, Prices & the Market

Behuria: "That premium increase was due to that war situation in the Middle East. Now since the war situation is easing out, we are expecting that it may remain the same or maybe it may go down also."

The Expansion Trifecta: Refinery, Smelter, Power

Singh: "Our target is next 3 to 4 months, we will be ready with the DPR and get the Board approval maybe October, November for the DPR for setting up this 0.05 crore ton smelter and also 1,000-megawatt power plant. After that, maybe we'll take 8 to 9 months to order the packages. By next year, August, September, we should order all the packages and start the groundwork maybe next year, October, November. And from there, it will take 3 to 3.5 years to set up this plant."

Capital Allocation & Balance Sheet

Behuria: "We have a balance of INR10,500 crores now every year, seeing our profitability and the PAT, we are adding INR3,500-plus crores... So, we need not go to the market for borrowing for our smelter expansion, see, our cash reserve and our future earning potential."

Guidance & Commitments

CommitmentSpecificsTimeline
5th Stream refinery mechanical completionAll packages mechanically complete; integrated water trials to followSeptember 2026
5th Stream first productionActual production start, stabilizing at 60–70% capacity over 3–4 monthsNovember–December 2026
FY27 alumina sales volume16 lakh tons (2 lakh tons extra from 5th Stream added to sales)FY27
FY27 alumina production from 5th Stream~2 lakh tonsFY27
Q2 alumina realization~$370/ton, based on July–August spot tenders at $370–$380Q2 FY27
Q2 metal cost of production₹1,70,000–1,72,000/tonQ2 FY27
Q2 alumina cost of productionWithin ₹21,000–₹22,000/tonQ2 FY27
Q2 caustic soda price~₹49,000/ton (up ₹3,000–₹4,000 from Q1)Q2 FY27
Smelter expansion DPR and Board approvalDPR ready; Board approval targetedOctober–November 2026
Smelter expansion package orderingAll packages orderedAugust–September 2027
Smelter expansion groundwork startGroundwork beginsOctober–November 2027
Smelter and power plant commissioningBoth commissionedDecember 2030 / H1 FY31
Captive coal EC approvalApproval from MoEFCCNext 2–3 months
FY27 captive coal production0.48 crore tonsFY27
Pottangi mines road construction8 km road construction (15–20 days)August 2026
Pottangi mines production startProduction beginsOctober 2026 onwards
FY27 capex₹1,500–1,800 croresFY27
FY28 capex~₹2,500 croresFY28
FY27 PAT₹6,000-plus croresFY27
FY27 aluminum production4.76–4.77 lakh tonsFY27
Q4 FY27 employee cost step-up~15% increase due to pay revisionQ4 FY27 (effective 1 Jan 2027)
LME aluminum price range$3,000–$3,200/tonRemainder of FY27
Post-expansion alumina production0.32–0.33 crore tons (vs rated 0.31 crore tons)From FY28 onwards

Key Metrics

MetricQ1 FY27
Total income₹5,400 cr, +39% YoY from ₹3,930 cr in Q1 FY26
PBT growth+88% YoY
EBITDA growth+78% YoY
Alumina realization\$323 per ton; Q2 expected ~\$370 per ton, up ~\$50
Alumina cost of production₹22,766 per ton, up from ~₹20,000 in FY26
Aluminum metal cost of production~₹1,70,000 per ton, up from ~₹1,57,000 average in FY26; Q2 expected ₹1,70,000–1,72,000
Domestic aluminum premium\$110 per ton, up from ~\$60 in prior tender 5–6 months ago
Alumina sales volume target (FY27)16 lakh tons, up from ~14 lakh tons in FY26
Captive coal production (Q1)8.80 lakh tons; FY27 target 0.48 crore tons, up from 0.4 crore tons in FY26
Employee count4,848, down from ~4,880 as of March 2026; ~170–200 reduction expected annually for next 3–4 years
Cash reserves₹10,500+ cr, zero-debt company
Q1 capex spent~₹350 cr; FY27 target ₹1,500–1,800 cr
5th Stream refinery commissioningMechanical completion targeted by September-end 2026; ~2 lakh tons alumina production expected in FY27
Smelter expansion capex (total)~₹25,000 cr for 0.05 crore ton smelter + 1,000 MW power plant; major capex from FY28 onwards
PAT expectation (FY27)₹6,000+ cr