Navkar Corporation Ltd Guidance Report - SOIC x StockScans Report
as of Oct 2026
- Kolkata Container Terminal - 6.3 mtpa, completion in H1 FY28
On track - In the Q4 FY26 PPT (May 2026), the Kolkata Container Terminal (0.05 crore TEUs / 6.3 mtpa, capex ₹740 crore) was slated for interim operations shortly and completion in H1 FY28, later revised to Q3 FY28 in Q1 and Q2 FY27 decks. Q2 FY27 shows interim operations commenced, RMQC and RTGC cranes under fabrication, and berth construction started.
- Kudathini (Ballari) MMLP - commercial operations in Q4 FY2026
Delivered - In the announcement of 16th October 2025, Kudathini (Ballari) MMLP commercial operations were expected in Q4 FY2026 with a phased ramp-up, on ₹380 crore of capex. Commercial operations were underway at the Kudathini Private Freight Terminal by Q4 FY26, and continued through Q1 and Q2 FY27.
- FY27 logistics EBITDA margin guidance of 28% and EBITDA of ₹400 crore
On track - At the Q2 FY27 call (Sep 2026), FY27 logistics EBITDA margin guidance was revised up to 28% from 24% (specialized rakes accounting), retaining the ₹400 crore EBITDA target; revenue guidance was cut to ₹1,400 crore from ₹1,650 crore on haulage netting. H1 FY27 delivered revenue ₹517 crore, EBITDA ₹153 crore at 29.7% margin, with full-year EBITDA seen slightly above ₹400 crore.
- FY27 consolidated operating revenue of ₹6,600-6,850 crore and EBITDA of ₹3,000 crore
On track - In the Q4 FY26 PPT (May 2026), consolidated FY27E guidance was operating revenue ₹6,850 crore (+28%) and EBITDA ₹3,000 crore (+15%); the Q2 FY27 PPT revised revenue to ₹6,600 crore (+23%), with EBITDA seen at ₹2,950-3,000 crore. H1 FY27 consolidated revenue was ₹2,926 crore (+18%) and EBITDA ₹1,348 crore (+13%), with management "broadly sticking to" the guidance.
- FY28 consolidated operating revenue of ₹10,800 crore and EBITDA of ₹5,000 crore
Pending - In the Q4 FY26 PPT (May 2026), consolidated FY28E guidance was operating revenue ₹10,800 crore (+58%) and operating EBITDA ₹5,000 crore (+67%), reiterated in Q1 and Q2 FY27 decks. No disclosed read yet; at the Q2 FY27 call management said a call on FY28 numbers will be taken at Q3 or Q4 results.
- FY27 ports revenue of ₹5,200 crore and EBITDA of ₹2,600 crore
On track - In the Q4 FY26 PPT (May 2026), FY27E ports guidance was revenue ₹5,200 crore and EBITDA ₹2,600 crore, reiterated through Q2 FY27. At the Q2 FY27 call, port EBITDA was seen ending around ₹2,550-2,560 crore; H1 FY27 ports revenue was ₹2,409 crore (+10%) with EBITDA ₹1,195 crore (+4%).
- FY28 ports revenue of ₹8,000 crore and EBITDA of ₹4,300 crore
Pending - In the Q4 FY26 PPT (May 2026), FY28E ports guidance was revenue ₹8,000 crore and EBITDA ₹4,300 crore, reiterated in the Q1 and Q2 FY27 decks. No disclosed read yet on the FY28 trajectory.
- FY28 logistics revenue of ₹2,800 crore and EBITDA of ₹700 crore
Pending - In the Q4 FY26 PPT (May 2026), FY28E logistics guidance was revenue ₹2,800 crore and EBITDA ₹700 crore, reiterated in Q1 and Q2 FY27 decks. No disclosed read yet; at the Q2 FY27 call FY28 logistics EBITDA margin guidance was left unchanged for now, with FY28 numbers to be called at Q3 or Q4 results.
- Rail rake fleet to 110 rakes by March 2027
On track - At the Q2 FY27 call (Sep 2026), the rail rake fleet was to increase from 78 rakes to at least 110 by March 2027, with 32 additional rakes expected over H2 FY27. As of Q2 FY27 the fleet stood at 78 rakes (44 owned, 34 on lease), 72 operational since October with the remaining 6 due in November-December.
- Port business capex of \~₹15,000 crore over next three years (by FY28)
On track - At the Q3 FY25 call (Dec 2024), port business capex of around INR 15,000 crores was planned over the next three years to be spent by FY '28, alongside \~INR 3,000 crores more for logistics; FY27-FY28 capex guidance was later reiterated at INR16,500 crore. Cumulative capex outlay reached \~₹8,250 crore to September 2026, with total committed expenditure \~₹14,250 crore.
- Slurry Pipeline Project - 30 mtpa, construction by March 2027
On track - In the Q4 FY25 PPT (May 2025), the Slurry Pipeline Project (30 mtpa, 302 km in Odisha, capex ₹4,000 crore) was to be completed by March 2027. By Q2 FY27, 263 km welding (87%) and 257 km lowering (85%) were done with testing commenced, and the project was on schedule for March 2027 commissioning at \~88% of scope.
- Jatadhar Port - 30 mtpa, construction by March 2027
On track - In the Q4 FY25 PPT (May 2025), Jatadhar Port (30 mtpa, capex ₹3,000 crore) was to be completed by March 2027, later framed at Q2 FY27 as mechanization works by March 2027 with cargo handling around end-March '27/April 2027. By Q2 FY27 the novation agreement was executed post Odisha Government approval and berth works were near completion.
- Dharamtar & Jaigarh brownfield expansion - 36 mtpa by March 2027
On track - In the Q4 FY25 PPT (May 2025), the Dharamtar & Jaigarh brownfield expansion (36 mtpa total; Dharamtar 21, Jaigarh 15; capex ₹2,359 crore) targeted completion by March 2027, later split as Dharamtar by March 2027 and Jaigarh by June 2027/Q1 FY28. By Q2 FY27 Jaigarh berth-side works were completed and Dharamtar berth construction was 65% done.
- Mangalore Container expansion from 4.2 to 6 mtpa by Q2 FY27
Delivered - In the Q4 FY25 PPT (May 2025), the Mangalore Container expansion from 4.2 to 6 mtpa (capex ₹150 crore) was expected complete by Q2 FY27. In Q1 FY27 the Mangalore Container Terminal capacity was expanded from 4.2 to 6.0 MTPA, confirmed in the Q2 FY27 deck within operational capacity of 186 mtpa.
- LPG terminal at Jaigarh - 2 mtpa, completion by June 2026
On track - In the Q4 FY25 PPT (May 2025), the Jaigarh LPG terminal (2 mtpa, capex ₹900 crore) targeted completion by June 2026, later revised to FY2027 and then marine operations by March 2027 with tank terminals by December 2027. By Q2 FY27 detailed engineering was complete, FAT for pumps done, and PESO approval received.
- Tuticorin 7 mtpa dry bulk berth completion
On track - In the Q3 FY25 and Q4 FY25 PPTs, the Tuticorin 7 mtpa dry bulk berth (capex ₹600 crore) was expected complete by Q4 FY26, later revised to Q1 FY27, then H2 CY26, then Q4 FY27. By Q2 FY27 foundation and piling were 100% complete, conveyor civil work 90%, with interim operations cargo of 1.63 MT in Q2 FY27.
- JNPA terminal commissioning in Q1 FY26
Delivered - At the Q3 FY25 call (Dec 2024), JNPA terminal commissioning was targeted in Q1 FY26, with the Liquid Terminal completion later revised to Q2 FY26 and then to Dec 2025. The 4.5 mtpa JNPA Liquid Terminal was completed with the Project Completion Certificate received 23rd February 2026, handling 1.30 MT in FY26.
- Keni Port - 30 mtpa greenfield, commercial operations in FY2029
On track - In the Q4 FY25 PPT (May 2025), the Keni Port (30 mtpa greenfield, capex ₹4,119 crore) was to see commercial operations in FY 2029, revised to FY 2030 in Q1 and Q2 FY27 decks. By Q2 FY27, Karnataka State Coastal Zone Management Authority recommendations had been sent to MOEFCC for further appraisal.
- FY26 consolidated operating revenue of ₹5,400 crore and EBITDA of ₹2,600 crore
Delivered - In the announcement of 16th January 2026, JSW Infrastructure targeted consolidated operating revenue of ₹5,400 crore and operating EBITDA of ₹2,600 crore for FY2026. FY26 actuals were revenue ₹5,361 crore and EBITDA ₹2,604 crore - within 0.7% of the revenue target and above the EBITDA target.
- Logistics segment top line of ₹8,000 crore with 25% EBITDA margin by FY30
On track - At the Q3 FY25 call (Dec 2024), management targeted a logistics top line of INR 8,000 crores by FY '30 with EBITDA margin approaching 25% on an asset-light model, with \~INR 9,000 crores of capex till FY '30. H1 FY27 logistics revenue was ₹517 crore (+72%) with EBITDA margin 29.7%, above the 25% target; no read yet on the ₹8,000 crore trajectory.
- Port capacity expansion to 40 crore tonnes (400 MTPA) by FY2030 or earlier
On track - At the Q3 FY25 call (Dec 2024), CEO Rinkesh Roy committed to completing expansion to 40 crore tonnes per annum by FY 2030 "or before"; the path was later stated as 186 MTPA (Q1 FY27) to 300 MTPA by FY28E and 400 MTPA by FY30. Operational capacity reached 186 mtpa by Q2 FY27, with 114.3 mtpa approved/under construction plus 90.0 mtpa pipeline.
- Port cargo growth of 15% CAGR to 40 crore tons and revenue CAGR north of 20-22% by FY30
Pending - At the Q3 FY25 call (Dec 2024), management committed to port cargo growth of 15% CAGR (17 crore to 40 crore tons) and revenue CAGR "north of 20% to 22%" by FY30. Cargo grew 9% in FY25 (117 MT), 4% in FY26 (122 MT) and 4% in H1 FY27 (60.5 MT), with H1 revenue up 18% - early growth trails the guided pace, but the FY30 horizon is unreached as of October 2026, so the outcome remains open.
- Port operational EBITDA margins to go from 52-53% to 58-59%
Pending - At the Q3 FY25 call (Dec 2024), the CFO guided port operational EBITDA margins from 52-53% to 58-59% as the cargo mix shifts toward greenfield ports along the 17.4-to-40 crore tonnes journey to FY30, with blended margins not below \~55% under the 40 crore tonnes plan. Margins have so far moved down, not up - ports operating EBITDA margin was 49.4% in Q2 FY27 and 49.6% in H1 FY27 (vs 53.1% and 52.4% a year earlier) - but the FY30 horizon is unreached, so the outcome remains pending.
- 10% volume growth guidance to continue until expansions come into picture
Missed - At the Q3 FY25 call (Dec 2024), the CFO reiterated guidance of 10% volume growth to continue until expansions come into the picture, for FY '25 and onwards. Cargo grew 9% in FY25 (117 MT), 4% in FY26 (122 MT), and 4% consolidated in H1 FY27 (60.5 MT), with India operations at +10%.
- FY2022 revenue growth of \~30% to just under ₹900 crore
Missed - In the announcement of 13th April 2022, FY2022 revenue was expected to grow \~30% to just under Rs. 900 crore, vs Rs. 483 crore in fiscal 2019. FY22 revenue came in at ₹453.14 crore, roughly half the target; FY23 revenue was ₹441.52 crore.
- Gearing and total outside liabilities to adjusted networth below 0.5x in FY2022
Delivered - In the announcement of 13th April 2022, gearing and total outside liabilities to adjusted networth (0.34x and 0.36x as on March 31, 2021) were estimated below 0.5x in fiscal 2022 and improving over the medium term. By end-FY23, Navkar Corporation was a debt-free company; no disclosed FY22 gearing figure is on record.