Key Takeaways
- Guidance withdrawn, quarter hit by rain and payments: Revenue fell 12% YoY as unprecedented rainfall and elongated payment cycles, especially in Jal Jeevan projects, choked execution. Management pulled FY26 guidance and will update only by March '26.
- Order book is large but mobilization is the question: The order book stands at INR71,957 crores, and October inflows pushed cumulative orders to INR17,420 crores. Yet management declined to quantify how much of the book is stuck awaiting clearances or right-of-way, frustrating analysts.
- JJM is the concentrated risk: The water segment holds ~INR7,000 crores of pending JJM work and INR1,700 crores in receivables that management insists are current, not overdue, because money is "churning." Payment traction is happening but is "quite confidential."
- Margins and returns compressed: Standalone EBITDA margin fell to 7.45% from 9.03% YoY on low fixed-cost absorption. ROCE halved to 9.82% from 14.61% at FY25-end, and EPS dropped to INR1.61 from INR2.55.
- What to watch next quarter: Whether the post-monsoon execution pickup materializes without guidance to frame it, any movement on the JJM receivable pile, and the pace of capex deployment against the revised INR1,050 crores budget after only INR169 crores was spent in H1.
The Guidance Withdrawal
- Why it happened: Management cited a "challenging external business environment and elongated payment cycles" as the reasons for pulling FY26 revenue and margin guidance. The decision was taken despite a large order book because low H1 turnover made fixed-cost absorption weak and H2 visibility poor.
- What replaces it: No interim qualitative steer. Management will "come back and update in March '26," and declined every request to characterize October-November trends or H2 expectations, calling it "not prudent to talk about H2."
- The margin floor: The lower band of the earlier guidance was 9% EBITDA margin. Management noted they are "very near" that lower band already, and whether they hit it depends entirely on Q3 performance, which they would not preview.
Neerad Sharma: "Due to the challenging external business environment and elongated payment cycles, we have decided to withdraw the guidance for the financial year '26 and will be able to share any update by March '26."
Jal Jeevan Mission: The Concentrated Exposure
- Execution backlog: JJM revenue was ~INR600 crores in Q2 and INR1,082 crores in H1. The order book at the start of the year was ~INR8,000 crores, leaving INR7,000 crores pending. Management expects a "substantial portion" of this to be executed in the current financial year, but gave no volume commitment.
- Receivables standstill: JJM receivables remain at INR1,700 crores, unchanged from last quarter. Management characterized this as money "getting churned" with billings and collections offsetting each other, so outstandings stay "latest" rather than overdue.
- Payment traction is opaque: When asked directly whether any of the INR1,700 crores had been collected, management said "some traction is happening" but declined to disclose details, calling client information "quite confidential given the situation."
- Working capital discipline: Management stated that if payments do not come, "there is no way we can continue to invest, borrow and invest," and confirmed measures are in place to limit working capital committed to businesses with held-up receivables.
Sanjay Pusarla: "Some traction is happening, but it is very, quite confidential to reveal anything about client information today given the situation."
Order Book & Inflows
- Order book composition: Total order book of INR71,957 crores is led by Buildings (31%), Transportation (24%), and Electrical (21%). Water & Railway and Irrigation together account for 17%, and Mining contributes 6%.
- Inflow momentum: Q2 standalone inflows were INR6,223 crores, mainly from Buildings, Water and Irrigation. Cumulative H1 inflows reached INR9,881 crores, and including October, total orders received touched INR17,420 crores, which management said is "moving in line with anticipation."
- The INR28,000-crore clarification: Management clarified that the INR28,000 crores of orders discussed previously were not held back by clearances but were March-end orders with normal mobilization periods. They did not quantify any other pool of orders stuck for approvals.
- Mining capex driver: A large mining order of INR6,800-odd crores received in October prompted the capex budget revision from INR750 crores to INR1,050 crores. Actual H1 capex was only INR169 crores, leaving significant deployment ahead.
Financial Health
| Metric | Q2 FY26 | Q2 FY25 / FY25 End | Movement |
|---|---|---|---|
| Consolidated revenue | Not disclosed (down 12% YoY) | — | ▼ |
| Standalone EBITDA margin | 7.45% | 9.03% | ▼ 158 bps |
| Consolidated EBITDA margin | 8.66% | 8.52% | ▲ 14 bps |
| EPS (INR) | 1.61 | 2.55 | ▼ 37% |
| ROCE | 9.82% | 14.61% (FY25 end) | ▼ |
| RoNW | 9.53% | 14.43% (FY25 end) | ▼ |
| Debt-Equity | 0.28x | 0.25x | ▲ |
| Working Capital Days | 110 days | — | — |
| Debtor Days | 78 | 65 (Q2 FY25) | ▲ 13 days |
| Unbilled Revenue (INR cr) | 6,662 | — | ▲ 41% |
- Debt and working capital strain: Debt rose INR263 crores during the quarter. Debtor days stretched to 78 from 65 YoY, and unbilled revenue jumped 41% to INR6,662 crores, reflecting billing delays compounding the payment-cycle problem.
- Consolidated profit bridge: The ~INR50 crores incremental profit in consolidated over standalone came from subsidiaries: Pachhwara Coal Mining, Urban, and smart meters. Smart meter profit is captured partly at the SPV level and partly at the NCC EPC level.
- AP receivables are healthy: Management clarified that Andhra Pradesh receivables are "very live," with projects being executed and billed receiving money on time.
Sanjay Pusarla: "But one thing is that we are very near to whatever lower band we have given. And it depends on how it will move in Q3, okay? If you see that the turnover revenue was low in the first half. And when the turnover is low, obviously, it is understood that absorbing the fixed cost will be low."
Segment & Subsidiary Updates
- Smart meters: Total investment so far is INR300 crores (INR70 crores up to March '25, INR230 crores in H1 FY26). Another INR280 crores is to be invested over the next 1 to 1.5 years. Execution happens at the NCC level as an EPC contractor.
- Vizag land deal: No money was received in H1. Management expects INR120 crores this year, with the remainder spread over the next 1.5 to 2 years.
- Private sector push: Management is actively looking at the private capital development space, including projects for private residential developers, signaling a diversification effort beyond public-sector dependence.
- Water segment beyond JJM: The water projects order book at the start of the year was ~INR8,000 crores, of which ~INR1,000 crores was executed in H1. The payment-cycle issue is specific to JJM; other water projects are not flagged for receivables stress.
The Analyst Frustration
- Repeated deflection: Across the call, management declined to provide any qualitative or quantitative steer on H2, current-quarter trends, JJM payment specifics, or the portion of the order book where work has not started. The consistent answer was to wait for March '26.
- Working capital scenario unanswered: When asked directly how the company would handle execution and order intake if receivables issues persist, management spoke about working capital discipline and that other projects are fine, but did not address the scenario of prolonged stress.
- The hope problem: One analyst summarized the mood: "It is not clear to me. We are only being hopeful now," after management's explanation about H2 execution expectations rested on the monsoon retreating rather than on concrete visibility.
Neerad Sharma: "If all the payments are not coming, there is no way we can continue to invest, borrow and invest, right? As an investor, that is in your ultimate interest. So we do have all those measures in place."
Guidance & Commitments
| Commitment | Specifics | Timeline |
|---|---|---|
| Guidance update | Management will share an update on FY26 guidance | By March '26 |
| JJM execution | Substantial portion of INR7,000 crores pending JJM order book to be executed | Current financial year |
| Vizag land recovery | INR120 crores expected | Current financial year |
| Vizag land balance recovery | Remaining amount after INR120 crores | Next 1.5–2 years |
| Smart meter investment | Incremental INR280 crores to be deployed | Next 1 to 1.5 years |
| Capex deployment | INR1,050 crores budgeted for regular projects (revised from INR750 crores) | FY26 |
Key Metrics
| Metric | Q2 FY26 |
|---|---|
| Revenue (consolidated) | ₹4,585 cr, down 12% YoY from ₹5,224 cr |
| Revenue (standalone) | ₹3,774 cr, down 16% YoY from ₹4,480 cr |
| EBITDA margin (consolidated) | 8.66%, vs 8.52% in Q2 FY25 |
| EBITDA margin (standalone) | 7.45%, vs 9.03% in Q2 FY25 |
| PAT margin (consolidated) | 3.37%, vs 3.12% in Q2 FY25 |
| PAT margin (standalone) | 2.68%, vs 3.58% in Q2 FY25 |
| EPS | ₹1.61, vs ₹2.55 in Q2 FY25 |
| Order book | ₹71,957 cr, vs ₹71,568 cr at beginning of FY26 |
| Order inflow (Q2) | ₹6,223 cr, mainly from Buildings, Water and Irrigation |
| Order inflow (cumulative, including Oct) | ₹17,420 cr |
| Net debt | ₹1,890 cr, up from ₹1,497 cr at beginning of Q2; debt-equity ratio at 0.28 |
| Working capital days | 110 days, 33% of turnover; debtors at 78 days vs 65 days in Q2 FY25 |
| Unbilled revenue | ₹6,662 cr, up 41% vs ₹5,937 cr at Q4 FY25 end |
| ROCE | 9.82%, vs 14.61% at FY25 end |
| Return on net worth | 9.53%, vs 14.43% at FY25 end |
| Capex incurred (H1 FY26) | ₹169 cr, vs revised full-year budget of ₹1,050 cr |
| JJM revenue (Q2) | ~₹600 cr; H1 FY26 JJM revenue at ₹1,082 cr |
| JJM pending order book | ₹7,000 cr, of which UP component is ₹3,840 cr |
| Smart meter investment (cumulative) | ₹300 cr, with incremental ₹280 cr to be invested over 1–1.5 years |