- BSE/NSE fines for delayed committee compliance - reconstitution completed
Delivered - The December 2025 announcement noted BSE/NSE levied fines for delayed constitution of Committees under Regulations 18(1), 19(1)/(2), 20(2)/24 for quarter ended September 2025. Committees were reconstituted with effect from 1 October 2025 (approved 25 September 2025), with the delay stated as purely procedural/timing.
- FY2023-24 product launches - Visistha (PPC) and SteelKrete (green cement)
Delivered - The FY24 Annual Report noted NCL launched two cement products under the Nagarjuna banner in FY2023-24: Visistha (PPC) and SteelKrete (green cement). Both were launched as stated; by FY26 blended cement share of sales was 55% vs 54% in FY25.
- Two mini hydel projects - 15.75 MW installed
Delivered - The FY22 Annual Report noted two mini Hydel Projects commissioned - 7.5 MW at Srisailam Right Main Canal and 8.25 MW on Tungabhadra Right Bank High-Level Canal. Both were commissioned, installed capacity 15.75 MW; FY21-22 generation was 38.94 MU, up 5% YoY.
- Boards division second plant at Paonta Sahib - 30,000 tpa
Delivered - The FY22 Annual Report noted the Boards division second plant of 30,000 tpa was set up at Paonta Sahib, Himachal Pradesh, plus one more 30,000 TPA plant near Mattapalli, Telangana. Total capacity of all three plants reached 90,000 TPA; Boards FY21-22 revenue was Rs 157.84 crore, up 20% YoY.
- Mr. Utkal B Goradia - Executive Director for 5 years
Delivered - The FY22 Annual Report noted Mr. Utkal B Goradia was appointed Executive Director for 5 years w.e.f. the date of the FY22 AGM, on the Board's recommendation. The appointment was completed as stated.
- Mr. K Ravi - Executive Vice Chairman for 5 years from 1st October 2022
Delivered - The FY22 Annual Report noted Mr. K Ravi, MD since 1995, steps down as Managing Director, appointed Executive Vice Chairman for 5 years w.e.f. 1st October 2022 to ensure smooth transition to Mr. K Gautam. The appointment was completed as stated, alongside Mr. Utkal B Goradia as Executive Director.
- CRISIL rating upgrade - Long-term to CRISIL A/Stable
Delivered - The 16th September 2021 announcement noted CRISIL upgraded Long-term ratings to CRISIL A/Stable from CRISIL A- and Fixed Deposits to FA+ Stable, on rated facilities of Rs 396.00 crore and fixed deposits of Rs 75.00 crore. The upgrade was completed as stated; the CRISIL A/Stable rating was maintained through Q1 and Q2 FY27.
- Rs 75 crore Kotak Mahindra term loan - cement capacity augmentation at Suryapet
Delivered - The FY22 Annual Report noted a term loan of Rs 75.00 crore sanctioned by Kotak Mahindra Bank for cement capacity augmentation at Suryapet, with Axis Bank adding Rs 13.50 crore under ECGLS. Line 1 upgradation at Mattapalli was completed and commenced operations from 1st May 2022.
- Final dividend of 30% for FY 2021-22
Delivered - The FY22 Annual Report proposed a final dividend of 30% for FY 2021-22, including the 15% interim already paid. FY22 dividend was Rs 3.00/share vs Rs 4.00 prior year, on record gross revenue of Rs 2,265.08 crore and PAT of Rs 9,364 lakh.
- Dividend - Rs 3.50 per share (35%) for FY26
Delivered - The FY26 Annual Report noted the Board recommended a dividend of Rs 3.50 per share (35%). The recommendation was completed as stated - Rs 3.50 per share (Interim & Final) vs Rs 3.00 in FY25, with interim dividend of Rs 678.48 lakh deducted from retained earnings.
- Doors Division - discontinued during FY26
Delivered - The FY26 Annual Report noted the Board approved discontinuance of the Doors Division, presented as discontinued operations under Ind AS 105, with a one-time charge of Rs 28.36 crore fully absorbed during the year. The Division was discontinued during FY26 after review of operational and commercial challenges; it had been loss-making in FY25 despite higher volumes.
- Modular Containers (P) Ltd JV - terminated to conserve resources
Delivered - The FY22 Annual Report noted the JV with Moravia Containers a.s (Czech Republic), incorporated November 2021, would be terminated to conserve resources and concentrate on existing lines of business. The termination was completed as stated.
- NCL Guangzheng Structures Ltd - striking off application under process
Pending - The FY22 Annual Report noted NCL Guangzheng Structures Ltd exists as a 100% subsidiary without operations, with the striking off application under process. No further disclosure on the striking off appears in the record.
- Two RMC units at Visakhapatnam and Hyderabad - completed and in operation
Delivered - The FY22 Annual Report noted two RMC units at Visakhapatnam and Hyderabad were completed and now in operation. The RMC footprint has since grown to 10 plants - 6 in Hyderabad, 4 in Visakhapatnam - at 60 Cu.M./hr per plant.
- Line 1 upgradation at Mattapalli - operations from 1st May 2022
Delivered - The FY22 Annual Report noted the Line 1 upgradation at Mattapalli (Suryapet district, Telangana) was completed and commenced operations from 1st May 2022. The upgradation was completed and operational from that date as stated.
- NCL Buildtek JV - APSHCL order of Rs 1,863 crore
Missed - The FY22 Annual Report noted the APSHC JV had received orders worth Rs 45.72 crore and supplied Rs 15.93 crore under the Rs 1,863 crore order. By FY26 only Rs 46.07 crore of orders were received and executed to date; the JV is in ongoing closure/dissolution with a Rs 4.14 crore diminution provision booked as an exceptional item.
- Sandwich Panel Board facility at Malkapur - one more being set up
Pending - The FY22 Annual Report stated that, given strong market reception and demand potential, one more Sandwich Panel Board facility was being set up at Malkapur near Hyderabad. The same report confirms lamination lines at Malkapur and Paontasahib were commissioned and operational, with total Boards capacity of 90,000 TPA; no completion disclosure for the additional Malkapur facility appears in the cited sources.
- Cement Bonded Particle Boards - evaluating opportunities to add capacity
Pending - The FY26 Annual Report stated the Boards division is evaluating opportunities to add capacity for Cement Bonded Particle Boards. No further disclosure appears in the record; Boards division currently has 3 facilities with 90,000 tons p.a. capacity.
- Vizag grinding unit - 0.66 MTPA, production expected shortly
Delivered - In the FY25 Annual Report MD message, management stated the second cement grinding unit near Visakhapatnam was nearing completion and expected to begin production shortly, taking capacity to approximately four million tons. The 0.66 MnTPA unit at Thallapalem was commissioned in November 2025 and capitalized during FY26, lifting total cement capacity from 3.30 MTPA to 4.00 MTPA; it ran at 77% utilization in Q2 FY27.
- Vishwamber Cements Ltd merger - amalgamation with NCL for captive limestone
Pending - The Q1 FY27 PPT guided a planned merger of Vishwamber Cements Ltd with NCL to create a captive limestone source via a 322-acre mining lease, reiterated in the 13th November 2026 announcement. VCL had no business operations in FY26 and was acquired for the 322.06-acre lease; no merger completion or approval is disclosed.
- Orissa cement plant - exploring setup, preliminary stage
Pending - At the Q2 FY27 call, management stated the company is exploring setting up a cement plant in Orissa, approaching government for applications/approvals, at a preliminary stage subject to approvals and evaluation. No further disclosure on the Orissa plant appears in the record.
- Coats division assets held for sale - realization approximately at balance sheet value
Pending - At the Q2 FY27 call, management stated realization from the closed Coats division's assets held for sale should "in all probabilities" approximately match the balance sheet amount. The division closed on March 31st of last financial year; sale is advertised with inquiries started, against Rs 318 Mn held for sale on the FY26 balance sheet, and no sale is completed yet.
- Cement EBITDA/tonne - H2 FY27 up Rs 50-60 over H1's Rs 475; full year not more than Rs 550
On track - At the Q2 FY27 call, management guided H2 FY27 cement EBITDA/tonne to improve by Rs 50-60 over H1's Rs 475/tonne, with the full year "cannot be more than Rs 550 kind of thing". Q2 FY27 cement EBITDA/tonne was Rs 480 and H1 Rs 475, on H1 cement sales of 14.59 lakh tonnes vs 12.63 lakh tonnes YoY; H2 FY27 is not yet reported.
- 130 MW hybrid renewable project - commissioned by end February 2028
On track - At the Q2 FY27 call, management guided the full 130 MW hybrid renewable project at Tuticorin, Tamil Nadu to be commissioned by end February 2028 in one phase, at \~Rs 987 crore with \~70% debt and Rs 675 crore sanctions from HDFC Bank and ICICI Bank, revising earlier phasing-by-FY28 guidance and a Rs 919 crore cost estimate after a Rs 68 crore DCR-driven escalation. As of Q2 FY27, \~418 acres of land are in possession, the \~7 km transmission line contract is finalized with substation work started, and debt sanctions of Rs 675 crore are received.