Key Takeaways
- Generation down, revenue up on arrears: Generation fell ~5% YoY on lower water availability, but revenue rose ~3% YoY because of ₹70 Cr in tariff arrears from the 2014-19 period.
- Parbati-II slips, Subansiri on track: Floods in Himachal Pradesh pushed Parbati-II’s first unit out of FY24, while Subansiri Lower is set to commission two units in January and February.
- Pumped storage is the new mainstay: NHPC signed MoUs for ~7,000 MW in Maharashtra and entered agreements with three other states, calling pumped hydro “the most emerging opportunity in the power sector.”
- Capex acceleration promised: Management targets 25-30% more capex than last year’s ~₹7,700 Cr, driven by uninterrupted execution across all under-construction projects. [4-5]
- What to watch next quarter: The post-monsoon reassessment of Parbati-II’s timeline, the restart of Subansiri Lower construction in November, and any draft regulations on returns.
Generation & Operational Performance
- Water availability drove the top-line split: Generation was ~5% lower YoY because of lower river water availability, a factor management called beyond its control. Plant availability remained strong at 94%, so machines were ready when water was not.
- Tariff arrears masked the volume drop: Revenue rose ~3% YoY despite lower generation, lifted by a ₹70 Cr increase in Interest from Beneficiaries on finalization of the 2014-19 tariff rate. Other income also jumped 29% YoY on higher dividend income from NHDC (₹28 Cr) and a ₹34 Cr insurance claim for business interruption at Sewa-II.
- Cost movements were mixed: Generation expenses rose ₹248 Cr on new Water Cess applicability in Uttarakhand, Sikkim and Himachal Pradesh. Employee costs dipped from ₹307 Cr to ₹297 Cr, finance costs fell ₹22 Cr on loan repayments and a lower average interest rate, and depreciation decreased as Sewa-II completed 12 years of life in FY23.
- PAF incentive recognition moved to the back end: Management voluntarily changed the methodology so PAF incentive is recognized only after a station’s capacity charges are fully recovered, avoiding the reversals that hit Q3 in prior years when NAPAF was not achieved. This quarter’s PAF incentive was nil as a result.
- Debtors position improved: Net trade receivables stood at ₹1,728 Cr as of 9 August 2023, with only ₹230 Cr in dues older than 45 days.
- July rains cut both ways: Torrential rains forced some plants to shut down for a week to 10 days, impacting plant availability, but PLF is not expected to drop because higher water availability drove good generation in July.
Project Execution: Subansiri Lower & Parbati-II
- Subansiri Lower is the near-term certainty: Physical progress is complete, work was paused for the monsoon, and construction restarts in November. Management proposes to commission two units in FY24, in January and February, with “no uncertainty as such.”
- Cost overrun at Subansiri is minimal: Hardly any cost overrun is expected except for 3-4 months of interest during construction.
- Parbati-II was derailed by Himachal floods: Torrential rains described as “almost a disaster kind of a situation” disturbed all approaches and access routes. Tunnel excavation was nearly complete, with only 65 meters left before the floods hit.
- First unit now likely in early FY25: Management sees “very little possibility of commissioning the first unit in this financial year” and will reassess the situation after the monsoon. If it slips, it will be early FY25 (April).
- Flood damage costs are manageable: Some additional costs will be incurred for making flood damage good, expedited lining, and non-conventional construction technologies, but management said these are not substantial enough to materially impact tariff.
Vishnoi: “We were left with hardly anything now, I think 65 meter is the only portion which is left for excavation now and we have made preparations to start lining immediately and we have also planned to do lining in an expeditious manner by deploying the most efficient construction technology.”
Pumped Storage: The New Growth Engine
- Pumped hydro is now NHPC’s declared mainstay: Management is entering the space “very aggressively,” calling it “one big business opportunity for NHPC in the near future” and “the most emerging opportunity in the power sector.”
- MoUs signed across four states: NHPC signed an MoU for four projects (~7,000 MW) in Maharashtra and entered agreements with Gujarat, Odisha and Andhra Pradesh for pumped storage development.
- The business model is multi-revenue-stream: Management outlined several use cases: combining with renewables for round-the-clock power to railways and industries, providing grid stability by injecting or absorbing power for the transmission system, and monetizing ancillary services. Returns will be regulated at 16.5% ROI on a cost-plus basis.
- First commissioning not before FY29: Pre-construction investigation and scheme optimization will take 1-1.5 years, followed by another agreement with the state government for construction permissions. Construction itself takes 4-5 years, putting the earliest Maharashtra project commissioning around FY29.
- Ancillary services monetization is still undefined: Government has issued guidelines allowing bilateral agreements with industry or exchange sales for round-the-clock power, but NHPC has not yet quantified bids, saying the first focus is on starting the project.
Vishnoi: “It is not only generation alone, it is the conversion of electricity from one form to the other and that could happen in many ways.”
Regulated Equity, Capex & Financial Outlook
- Capex target raised 25-30%: NHPC aims to beat last year’s ~₹7,700 Cr by ensuring constant, uninterrupted execution at all under-construction projects. [4-5]
- Regulated equity stays flat in FY24: Regulated equity will remain at the present ~₹13,000 Cr level, with only a possible small addition from Subansiri Lower in the last 1-2 months of the fiscal year.
- FY25 regulated equity jump is locked in: Management stated that reaching ₹22,600 Cr by end-FY25 is “for sure.”
- Solar is selective, not scaled: NHPC will only take solar projects that can achieve at least 12% ROE, so it has not set a higher capacity target. Current pipeline includes 300 MW (Bikaner, Tata Power) in FY24, 700 MW in FY24-25, 200 MW Gujarat solar across FY23-24 and FY24-25, and 88 MW of floating solar (NHDC) in the current FY.
- Clean energy arm IPO is not on the table: Management will only consider it if capacity is added in solar or wind, transferred to a 100% subsidiary, and resources are required. No plan exists at present.
Goyal: “That is for sure.”
New Projects & Regulatory Environment
- Subansiri Upper and Middle capacities revised upward: Earlier figures of 1,500 MW (Upper) and 1,720 MW (Middle) have been revised to 2,000 MW and 1,800 MW respectively, subject to DPR updates. NHPC will update and review the DPRs itself rather than rely on earlier work by EY.
- Takeover capex is for reimbursement: The capex mentioned for Subansiri Upper and Middle covers reimbursing earlier developers for amounts already spent on visible or meaningful site development, under a Government of India scheme.
- Sawalkot tender imminent: The tender document is ready and the NIT for civil works and other packages will be issued very shortly, with last-stage state government clearances almost through.
- 10 GW renewable bidding mandate: NHPC has been mandated to roll out 10 GW of capacity in FY24, with 3 GW already bid out and 7 GW to follow gradually. NHPC acts only as an intermediary and bears no capex.
- New regulations: guarded optimism, no specifics: Management expects not to be a loser from upcoming regulations and sees possible benefit, but is waiting for draft regulations and has demanded more Return on Equity. No quantified impact was provided.
- IEGC code impact is an open question: Management declined to comment on how the code effective 1 October 2023 might affect earnings via PAF or DSM, saying it will make a statement only after ascertaining what will happen.
Goyal: “In nutshell, we will not be loser on account of new regulations to come. There may be some benefit, but we are waiting for the draft regulations as of now. We have given our comments. We are demanding more Return on Equity but that is to be seen.”
Guidance & Commitments
| Commitment | Specifics | Timeline |
|---|---|---|
| Subansiri Lower commissioning | Two units commissioned | January and February 2024 |
| Parbati-II first unit | Reassess after monsoon; if delayed, early FY25 | April 2024 (if FY24 slips) |
| Capex growth | 25-30% more than last year’s ~₹7,700 Cr | FY24 [4-5] |
| Regulated equity | Remain at ~₹13,000 Cr, possible small Subansiri addition | FY24 |
| Regulated equity | Reach ₹22,600 Cr | End-FY25 |
| 10 GW renewable bidding | Full rollout achieved | FY24 |
| Pumped storage first commissioning | Maharashtra project earliest | FY29 |
| Solar project commissioning | 300 MW Bikaner, 88 MW floating solar (NHDC) | Current FY |
| Solar project commissioning | 700 MW | FY24-25 |
Key Metrics
| Metric | Q1 FY24 |
|---|---|
| Revenue from Operations | ₹2,571 cr, +3% YoY |
| Other Income | ₹279 cr, +29% YoY |
| Generation Expenses | ₹518 cr, up from ₹270 cr YoY |
| Employee Cost | ₹297 cr, down from ₹307 cr YoY |
| Finance Cost | ₹115 cr, down from ₹137 cr YoY |
| Depreciation and Amortization | ₹276 cr, down from ₹287 cr YoY |
| Other Expenses | ₹370 cr, down from ₹507 cr YoY |
| PAT | ₹1,053 cr, marginally higher vs ₹1,050 cr YoY |
| Generation | 778.7 crore units, -5% YoY |
| Plant Availability Factor | 94.13%, vs 98.57% YoY |
| PAF-based Incentive | nil, vs ₹171 cr YoY; recognition methodology changed to back-ended |
| Deviation Charges | ₹12 cr, vs ₹72 cr YoY |
| Consolidated Capex | ₹1,906 cr, vs ₹1,161 cr YoY |
| Trade Receivables (30 Jun'23) | ₹6,736 cr, vs ₹5,887 cr as on 31 Mar'23 |
| Net Trade Receivables (9 Aug'23) | ₹1,728 cr, of which >45 days dues ₹230 cr |
| Realization from Beneficiaries | ₹1,647 cr, vs ₹1,357 cr YoY |
| FY24 Capex Target (consolidated) | ₹10,857 cr, +25-30% vs FY23 actual of ~₹7,700 cr |
| Average Cost of Borrowing | ~7.7% |