Key Takeaways
- Strong operational quarter, project delays persist: Generation rose 5% YoY in H1, driving 12% revenue and PAT growth, but key projects Subansiri and Parbati-II saw timelines slip again due to weather and geology.
- Receivables ballooned, but quality is intact: Trade receivables jumped to ₹5,854 Cr from ₹4,621 Cr in six months, yet only ₹113 Cr is overdue beyond 45 days and bill discounting provided ₹1,114 Cr in relief.
- NHDC delivered a standout performance: The subsidiary’s generation surged 138% YoY in H1, with Q2 hitting its highest ever, contributing significantly to consolidated PAT.
- The project pipeline is deepening, not just widening: CCEA recommendation for the giant Dibang project, NCLT acquisitions of Teesta-VI and Rangit-IV, and a 10,000 MW Rajasthan renewables MoU all advanced this quarter.
- What to watch next quarter: Whether the non-monsoon concreting run-rate at Subansiri actually hits 40,000 cubic meters/month, and if the geology at Parbati-II improves enough to accelerate the painfully slow 2-3 meters/day tunneling pace.
Operational Performance
- Generation drove the top line: H1 FY23 generation rose 5% YoY (893 MUs higher) on better water availability and the restoration of the Sewa-II Power Station, which had been shut since September 2020. Revenue from Operations grew 12% YoY to ₹5,482 Cr, with ~₹450 Cr from higher generation and ₹111 Cr from increased power trading.
- Plant availability hit near-perfection: H1 PAF reached 99.23%, up from 95.74% a year ago, which lifted PAF-based incentive income by ₹40 Cr. Total incentive income for H1 rose ₹74 Cr YoY to ₹472 Cr.
- Costs were a mixed bag: Generation expenses rose ₹59 Cr YoY in H1 due to new water cess in Uttarakhand and Sikkim, while employee costs fell ₹25 Cr on superannuation and finance costs fell ₹24 Cr on loan repayments. These savings were overwhelmed by a ₹264 Cr spike in Other Expenses, driven by a ₹106 Cr impairment provision for the Loktak Downstream investment and a ₹124 Cr fair value loss on financial assets.
- MAT Credit recognition boosted reported profit: H1 FY23 PAT rose 12% YoY to ₹2,483 Cr, with ₹127 Cr of the increase coming from MAT Credit recognition. Without it, underlying PAT growth was slimmer, as the fair value loss and higher other expenses ate into operational gains.
- Other income fell on improved collections: H1 Other Income declined 11% YoY to ₹332 Cr, almost entirely because Late Payment Surcharge dropped by ₹126 Cr, a positive signal that beneficiaries are paying more promptly.
R.P. Goyal: "Actually, earlier we were having over staffing. So, now we have entered in the ideal situation, but of course, due to coming of new projects, we require further manpower."
Project Execution: Delays & Milestones
- Subansiri Lower slipped again, but the end is in sight: Two units are now expected by June 2023, a three-month delay from the prior March 2023 target, after a landslide in the diversion tunnel area and extended monsoon halted restoration work for two months. Full commissioning of all units is still targeted for March 2024. Management stated the delay will only increase IDC and establishment costs, not hard costs.
- Parbati-II HRT is crawling through bad rock: Only 550-560 meters of tunneling remain from 31.54 km, but progress is just 2-3 meters per day (60-70 meters/month) because the heading is in a poor-geology zone. Management expects the pace may improve once this band is crossed and still targets a December 2023 project completion, with concreting and lining work proceeding in parallel.
- Subansiri dam concreting poised to accelerate: 89% of total concrete is already placed. The monsoon run-rate of ~12,000 cubic meters/month is expected to quadruple to ~40,000 cubic meters/month in the non-monsoon period, a critical ramp to watch.
- NHDC delivered a generational quarter: Generation in Q2 hit 2,715 MUs, up from just 426 MUs a year ago, the highest ever. H1 generation rose 138% YoY to 3,188 MUs, driving Q2 PAT to ₹305 Cr from ₹105 Cr.
Y.K. Chaubey: "Although project hit by flood and extended monsoon in last two months, but I am very hopeful that we can commission two units by June'23."
Receivables & Working Capital
- Debtors swelled, but the aging is clean: Trade receivables stood at ₹5,854 Cr as of 30 September 2022, up from ₹4,621 Cr at March-end. Unbilled debtors accounted for ₹2,751 Cr. Critically, only ₹113 Cr of billed debtors were overdue beyond 45 days, with ~₹3,000 Cr under 45 days.
- Bill discounting and securitization provided liquidity: Bill discounting realization of ₹1,114 Cr reduced net receivables to ₹1,989 Cr. Separately, ~₹1,250 Cr of J&K dues were securitized through PFC and REC, with inflows of ₹50 Cr per month.
- Overdue settlement agreements provide visibility: J&K overdues of ~₹1,400 Cr are being paid in 28 monthly installments of ₹50 Cr, while Tamil Nadu’s ₹20 Cr is spread over 40 installments.
Pipeline & New Opportunities
- Dibang Multipurpose Project crossed a major hurdle: The PIB recommended the proposal for CCEA consideration on 11 October 2022, and a draft CCEA note was submitted to the Ministry of Power on 28 October. This is India’s largest hydro project and a potential game-changer for NHPC’s portfolio.
- NCLT acquisitions add 620 MW: NHPC acquired the 500 MW Teesta-VI project (Lanco) and the 120 MW Rangit-IV project (Jal Power Corp) through the NCLT route. Mergers of both entities with NHPC are under examination or in process. Teesta-VI has a 40-year Bulk Power Supply Agreement already signed with Chhattisgarh.
- Siang and Subansiri Basin projects allotted: The Ministry of Power allotted Subansiri Upper (2,000 MW) and Subansiri Middle (1,800 MW) on a standalone basis, and Upper Siang (10,000 MW) and Siang Lower (2,700 MW) in JV mode, adding 16,500 MW to the future pipeline.
- Renewables ambition scales up: NHPC Renewable Energy Limited signed an MoU with the Rajasthan government for 10,000 MW of Ultra Mega Renewable Energy Power Parks. On the solar front, 265.6 MW of the Avaada project was commissioned in September, with the balance 54.4 MW expected by November 2022.
- Pumped storage exploration begins: NHPC is studying feasibility for projects across six states, including the 525 MW Indrasagar Omkareshwar PSP and 800 MW Tekwa-2 PSP in Madhya Pradesh.
- Nepal MoUs expand the international footprint: MoUs were signed for the 750 MW West Seti and 450 MW SR-6 projects, along with a power sales arrangement with PTC India. Discussions for the 480 MW Phukot Karnali project are in the final stage.
Guidance & Commitments
| Commitment | Specifics | Timeline |
|---|---|---|
| Subansiri Lower first two units | Commission two units | June 2023 |
| Subansiri Lower full commissioning | All units operational | March 2024 |
| Parbati-II project completion | Complete remaining tunneling and project | December 2023 |
| Lanco Teesta-VI project commissioning | Project completion | July 2025 |
| Jal Power Corp Rangit-IV project completion | Project completion | August 2024 |
| Ratle HE Project completion | Project completion | February 2026 |
| Pakaldul HE Project (1,000 MW) completion | Project completion | July 2025 |
| Kiru HE Project (624 MW) completion | Project completion | July 2025 |
| Kwar Hydro Electric Project (540 MW) completion | Project completion | November 2026 |
| Kalpi Solar Power Project full capacity | 65 MW fully commissioned | 31 December 2022 |
| Avaada Solar balance capacity | 54.4 MW commissioned | November 2022 |
| Dugar project decision | PIB/CCEA clearance for EPC award | By March 2023 |
| Sawalkot project award decision | Award decision | FY 2023-24 |
| Annual CAPEX run-rate | ~₹8,000 Cr per year | Coming years |
Key Metrics
| Metric | Q2 FY23 |
|---|---|
| Revenue from Operations | ₹2,888 cr, +5% YoY; higher generation contributed ₹137 cr, power trading +₹7 cr |
| Other Income | ₹115 cr, -33% YoY; late payment surcharge fell by ₹102 cr |
| Generation Expenses | ₹367 cr, +₹51 cr YoY; water cess in Uttarakhand and Sikkim |
| Employee Cost | ₹291 cr, -₹15 cr YoY; superannuation partly offset by DA increase |
| Finance Cost | ₹107 cr, -₹27 cr YoY; lower interest rates and loan repayments |
| Depreciation & Amortization | ₹284 cr, +₹4 cr YoY; additional capitalization at certain power stations |
| Other Expenses | ₹352 cr, +₹69 cr YoY; fair value loss on financial assets of ₹38 cr, higher R&M, security, CSR |
| Profit After Tax | ₹1,433 cr, +10% YoY; includes net MAT credit impact of ₹123 cr |
| Generation | 9,980 MUs, marginal increase vs 9,912 MUs in Q2 FY22 |
| Plant Availability Factor (PAF) | 99.87%, vs 99.00% in Q2 FY22, ~1% higher |
| PAF-based Incentive | ₹181 cr, vs ₹187 cr in Q2 FY22, marginal decrease of ₹6 cr |
| Deviation Charges | ₹47 cr, flat vs Q2 FY22 |
| Total Incentive (PAF + Deviation) | ₹228 cr, vs ₹234 cr in Q2 FY22 |
| Trade Receivables (as of 30 Sep'22) | ₹5,854 cr, vs ₹4,621 cr as of 31 Mar'22; includes ₹2,751 cr unbilled debtors |
| Billed Debtors >45 days | ₹113 cr, out of ₹3,103 cr total billed debtors; ~₹3,000 cr is less than 45 days |
| CAPEX Incurred (H1 FY23) | ₹2,646 cr, against full-year target of ₹8,061 cr on consolidated basis |