Key Takeaways
- Weak quarter, hydro-driven: Generation fell 11% YoY in Q2 on poor water availability and the Parbati-III outage, dragging revenue down 12%. The bottom line was rescued by a large MAT credit and higher other income, keeping PAT flat.
- Teesta flood is a setback, not a disaster: The October flash flood hit 1,010 MW of capacity, but the physical damage is limited to debris and one store, estimated at Rs. 250 Crore, and is fully insured. Teesta-V is expected back in about a year.
- A commissioning wave is now visible and dated: Management laid out a clear, project-by-project timeline to add ~2,500 MW in FY25, ~2,600 MW in FY26, and ~2,900 MW in FY27, headlined by the first units of the long-delayed Subansiri Lower Project in Q4 this year.
- Incentive income is being deliberately back-ended: A change in accounting methodology means PAF-based incentives, which collapsed to near zero this half, will now only be recognized after a station recovers its full capacity charges, pushing that revenue into the second half of each year.
- What to watch next quarter: The pace of restoration at Teesta-V and TLDP-III, any further slippage in the Subansiri Lower Q4 commissioning target, and the actual incentive income booked in H2 under the new policy.
Operational Performance: A Dry Quarter
- Generation collapse: Q2 generation fell to 901 crore units from 1,013.8 crore units YoY, driven by lower water availability and intense rain and floods in Himachal Pradesh that forced the outage of all units at Parbati-III. H1 generation was down 8%.
- PAF plummeted: The Plant Availability Factor dropped to 89.78% in Q2 from 99.87% a year ago, with Parbati-III, Kishanganga and Chamera-II all contributing to the decline.
- Incentive income vanished: Total incentives fell from Rs. 228 Cr to just Rs. 16 Cr in Q2, as PAF-based incentives were nil under a new accounting methodology that recognizes them only after a station fully recovers its capacity charges, making the recognition back-ended.
- Cost headwinds emerged: Generation expenses rose Rs. 30 Cr in Q2 on the new Water Cess in Uttarakhand, Sikkim and Himachal Pradesh, though this is a pass-through item with no net profitability impact. Employee costs also rose Rs. 30 Cr on increments and promotions.
- The bottom-line rescue: PAT was flat YoY despite the revenue decline, supported by a 23% rise in other income (dividend income and a Sewa-II insurance claim) and a Rs. 442 Cr positive impact from MAT credit recognition in Q2.
RP Goyal: "We are not much aggressive on renewable energy front. We are basically a hydro company. But keeping at least 12% ROE, we will be taking solar or wind projects. Otherwise, we will not take up solar or wind project."
Teesta Flood: Damage, Insurance, and Restoration
- The event: A flash flood in North Sikkim on 3rd-4th October hit the operational Teesta-V (510 MW) and the under-construction Teesta-VI (500 MW), and also forced outages at TLDP-III and TLDP-IV.
- Recovery underway: TLDP-IV is already operational again, and TLDP-III is expected to be restored very shortly. Teesta-V restoration is planned in around one year.
- Damage is contained and insured: Management estimates the loss at around Rs. 250 Crore, limited to debris filling the reservoir and tunnel and the washing out of one store. There is no loss to the already constructed part of Teesta-VI. The entire loss is fully insured under a Contractors All Risk Policy with New India Assurance.
- Teesta-VI timeline: The under-construction project, being merged into NHPC via the Lanco Teesta acquisition, is still expected to commission by August 2026.
RP Goyal: "There is no loss to our already constructed part of the project. Only loss is in shape of filling up debris in our reservoir, our tunnel and washing out of our one of the stores. So there is no much loss. We estimate the loss at around Rs. 250 Crore and it is fully insured through our Contractors All Risk Policy."
The Commissioning Pipeline: A Project-by-Project Map
- The near-term catalyst: Subansiri Lower Project is in full-swing construction, with two units (500 MW) expected to be commissioned in Q4 of this financial year. The remaining six units will follow one-by-one, with 1,500 MW total expected by end of FY25 and the balance by May 2025.
- FY25 total: Management expects to commission around 2,500 MW in FY25, comprising 800 MW from Parbati-II (targeting September 2024 completion after a major tunnel milestone), 120 MW from Rangit-IV, and 1,500 MW from Subansiri Lower.
- FY26: 2,000 MW from the remaining Subansiri Lower units plus 624 MW from the Kiru HE Project, which is estimated for completion by March 2026.
- FY27: A large wave including Pakal Dul (1,000 MW, September 2026), Kwar (540 MW, November 2026), Ratle (850 MW, May 2026), and Teesta-VI (500 MW, August 2026).
- The long tail: The 2,880 MW Dibang Multipurpose Project is scheduled for 2031-32, with balance dam and hydro-mechanical packages to be awarded this financial year.
- Merger progress: The acquisition of Lanco Teesta (Teesta-VI) and Jal Power Corporation (Rangit-IV) is advancing, with the Rangit-IV merger expected to complete by August 2024.
Pumped Storage & Renewables: A Cautious Build-Out
- PSP momentum: NHPC signed MoUs with Maharashtra (four PSPs, 7,350 MW), Odisha, and Andhra Pradesh (Kamlapadu 950 MW and Yaganti 1,000 MW in the first phase) during the quarter. PFRs for several projects have been submitted to the CEA.
- Renewable energy is ROE-gated: Management was explicit that it is not aggressive on renewables and will only take solar or wind projects if they deliver at least a 12% ROE, framing NHPC as fundamentally a hydro company.
- Solar progress: The 300 MW Bikaner project is progressing well, while land acquisition is underway for 600 MW in Gujarat and 100 MW in Andhra Pradesh.
- PSP returns: For the Andhra Pradesh PSP joint venture, the return on equity will be as per hydro projects at 16.5%.
Financial Position: Funding, Costs, and the MAT Credit
- Funding is a non-issue: Management stated that the loan portion of its capex is fully tied up and internal accruals comfortably cover the equity requirement of Rs. 2,500-3,000 Cr per year, even after loan repayments and dividends.
- Cheapest-rate borrower: NHPC recently raised a Rs. 2,000 Crore loan at 7.54% per annum, variable, with a clause allowing prepayment at any time without charges.
- The MAT credit mechanics: The Rs. 519 Cr MAT credit recognized in Q2 pertains to NHPC only and is not a pass-through to beneficiaries. It arose because NHPC paid higher tax under MAT during tariff period 9-14, where the tax taken was treated as final, and is now able to recognize and utilize the credit.
- Cost pass-through: Management confirmed that cost escalations on projects are generally pass-through in the tariff.
- Capex target: The consolidated capex target for FY24 is Rs. 10,857 Crore.
RP Goyal: "We are raising loans at the cheapest rate. Recently we have raised Rs. 2,000 Crore loan at the rate of 7.54% per year, and that is variable. And we are keeping clause regarding prepayment at any time without any repayment charges. So, we are able to raise the loan at the cheapest rate in the market."
Guidance & Commitments
| Commitment | Specifics | Timeline |
|---|---|---|
| Subansiri Lower first units | Two units (500 MW) commissioned | Q4 FY24 |
| Subansiri Lower full capacity | Remaining six units online | By May 2025 |
| Parbati-II completion | 800 MW project completed | September 2024 |
| FY25 total commissioning | ~2,500 MW (Parbati-II, Rangit-IV, Subansiri partial) | FY25 |
| FY26 total commissioning | ~2,600 MW (Subansiri balance, Kiru) | FY26 |
| FY27 total commissioning | ~2,900 MW (Pakal Dul, Kwar, Ratle, Teesta-VI) | FY27 |
| Teesta-V restoration | 510 MW station back online | Around one year |
| Dibang Multipurpose Project | 2,880 MW commissioned | February 2032 |
| Rangit-IV merger completion | Jal Power Corporation merger closed | August 2024 |
| Teesta-VI (Lanco) commissioning | 500 MW project online | August 2026 |
| Ratle HE Project | 850 MW commissioned | May 2026 |
| Pakal Dul | 1,000 MW commissioned | September 2026 |
| Kiru HE Project | 624 MW commissioned | March 2026 |
| Kwar HE Project | 540 MW commissioned | November 2026 |
| FY24 consolidated capex | Rs. 10,857 Crore target | FY24 |
Key Metrics
| Metric | Q2 FY24 |
|---|---|
| Revenue from Operations | ₹2,485 cr, down 12% YoY (₹351 cr) due to lower generation |
| PAT | ₹1,447 cr, up 1% YoY (₹14 cr); includes ₹442 cr positive impact from MAT credit recognition |
| Other Income | ₹129 cr, up 12% YoY (₹14 cr) driven by higher dividend income |
| Generation | 901 crore units, down 11% YoY (112.8 crore units) due to lower water availability and Parbati-III outage |
| Plant Availability Factor (PAF) | 89.78%, down ~10 ppt YoY from 99.87% |
| Total Incentives | ₹16 cr, vs ₹228 cr YoY; PAF incentive nil due to change in recognition methodology |
| Employee Cost | ₹321 cr, up ₹30 cr YoY on account of increments and promotions |
| Finance Cost | ₹115 cr, up ₹8 cr YoY due to higher interest on short-term loans |
| Depreciation & Amortization | ₹277 cr, down ₹7 cr YoY due to completion of 12-year life of Sewa-II Power Station |
| Generation Expenses | ₹397 cr, up ₹30 cr YoY mainly due to applicability of Water Cess in Uttarakhand, Sikkim, and Himachal Pradesh |
| MAT Credit Recognized (net impact on PAT) | ₹442 cr positive impact (₹519 cr recognized, ₹77 cr utilized) |
| CAPEX Incurred (Half Year FY24) | ₹4,095 cr on consolidated basis, against full-year target of ₹10,857 cr |
| Trade Receivables (as of 30 Sep'23) | ₹5,970 cr, including ₹2,685 cr unbilled debtors; net receivables as of 5 Nov'23 at ₹1,124 cr |
| Realisation from Beneficiaries (Half Year FY24) | ₹5,065 cr, vs ₹3,800 cr in corresponding previous period |
| Subansiri Lower Project Commissioning | 500 MW (2 units) expected by end of Mar'24; remaining 1,500 MW by May'25 |