NHPC Ltd Q2 FY2024 Concall Summary

Source transcript PDF: https://assets.stockscans.in/docs/vcoibr7xnnccejkphq4x55av.pdf

Key Takeaways


Operational Performance: A Dry Quarter

RP Goyal: "We are not much aggressive on renewable energy front. We are basically a hydro company. But keeping at least 12% ROE, we will be taking solar or wind projects. Otherwise, we will not take up solar or wind project."

Teesta Flood: Damage, Insurance, and Restoration

RP Goyal: "There is no loss to our already constructed part of the project. Only loss is in shape of filling up debris in our reservoir, our tunnel and washing out of our one of the stores. So there is no much loss. We estimate the loss at around Rs. 250 Crore and it is fully insured through our Contractors All Risk Policy."

The Commissioning Pipeline: A Project-by-Project Map


Pumped Storage & Renewables: A Cautious Build-Out


Financial Position: Funding, Costs, and the MAT Credit

RP Goyal: "We are raising loans at the cheapest rate. Recently we have raised Rs. 2,000 Crore loan at the rate of 7.54% per year, and that is variable. And we are keeping clause regarding prepayment at any time without any repayment charges. So, we are able to raise the loan at the cheapest rate in the market."

Guidance & Commitments

CommitmentSpecificsTimeline
Subansiri Lower first unitsTwo units (500 MW) commissionedQ4 FY24
Subansiri Lower full capacityRemaining six units onlineBy May 2025
Parbati-II completion800 MW project completedSeptember 2024
FY25 total commissioning~2,500 MW (Parbati-II, Rangit-IV, Subansiri partial)FY25
FY26 total commissioning~2,600 MW (Subansiri balance, Kiru)FY26
FY27 total commissioning~2,900 MW (Pakal Dul, Kwar, Ratle, Teesta-VI)FY27
Teesta-V restoration510 MW station back onlineAround one year
Dibang Multipurpose Project2,880 MW commissionedFebruary 2032
Rangit-IV merger completionJal Power Corporation merger closedAugust 2024
Teesta-VI (Lanco) commissioning500 MW project onlineAugust 2026
Ratle HE Project850 MW commissionedMay 2026
Pakal Dul1,000 MW commissionedSeptember 2026
Kiru HE Project624 MW commissionedMarch 2026
Kwar HE Project540 MW commissionedNovember 2026
FY24 consolidated capexRs. 10,857 Crore targetFY24

Key Metrics

MetricQ2 FY24
Revenue from Operations₹2,485 cr, down 12% YoY (₹351 cr) due to lower generation
PAT₹1,447 cr, up 1% YoY (₹14 cr); includes ₹442 cr positive impact from MAT credit recognition
Other Income₹129 cr, up 12% YoY (₹14 cr) driven by higher dividend income
Generation901 crore units, down 11% YoY (112.8 crore units) due to lower water availability and Parbati-III outage
Plant Availability Factor (PAF)89.78%, down ~10 ppt YoY from 99.87%
Total Incentives₹16 cr, vs ₹228 cr YoY; PAF incentive nil due to change in recognition methodology
Employee Cost₹321 cr, up ₹30 cr YoY on account of increments and promotions
Finance Cost₹115 cr, up ₹8 cr YoY due to higher interest on short-term loans
Depreciation & Amortization₹277 cr, down ₹7 cr YoY due to completion of 12-year life of Sewa-II Power Station
Generation Expenses₹397 cr, up ₹30 cr YoY mainly due to applicability of Water Cess in Uttarakhand, Sikkim, and Himachal Pradesh
MAT Credit Recognized (net impact on PAT)₹442 cr positive impact (₹519 cr recognized, ₹77 cr utilized)
CAPEX Incurred (Half Year FY24)₹4,095 cr on consolidated basis, against full-year target of ₹10,857 cr
Trade Receivables (as of 30 Sep'23)₹5,970 cr, including ₹2,685 cr unbilled debtors; net receivables as of 5 Nov'23 at ₹1,124 cr
Realisation from Beneficiaries (Half Year FY24)₹5,065 cr, vs ₹3,800 cr in corresponding previous period
Subansiri Lower Project Commissioning500 MW (2 units) expected by end of Mar'24; remaining 1,500 MW by May'25