NHPC Ltd Q2 FY2025 Concall Summary

Source transcript PDF: https://assets.stockscans.in/docs/44a7necnwaurhciyqfdlggyo.pdf

Key Takeaways


The Teesta-V Overhang

Management: "As per our latest estimate, this plant will commence generation by December’25. Reason being, this plant suffered a second incident in August’24."

Commissioning Pipeline & Regulated Equity Build

R.P. Goyal: "So, meaning thereby, in next four years, our Regulated Equity is going to be more than double. So, current level of Rs. 13,000 Crore is going to be Rs. 28,500 Crore."

Financials: The PAT Story Is a Tax Story


Capital Position & Funding Capacity


Renewables & Pumped Storage: Early but Intentional


Project Execution: Progress & Slippage

R.P. Goyal: "As per our plan, it was to be commissioned in December’24. But hydro has some challenges. That’s why we are shifting our goal posts to February’25..."

Guidance & Commitments

CommitmentSpecificsTimeline
Teesta-V generation restartPlant to commence generation after two incidents (Oct’23 flood, Aug’24 landslide)December 2025
Parbati-II commissioningAll 4 units in a single stroke; reservoir filling starts Feb’25February 2025
Subansiri Lower first units3 units commissioned; remaining 5 phased thereafter3 units by March 2025; full project by May 2026
Rangit-IV completion80% physical progress achievedDecember 2025
Pakal Dul completionUnder constructionSeptember 2026
Kiru completionUnder constructionSeptember 2026
Teesta-VI commissioningUnder constructionDecember 2027
Kwar commissioningUnder constructionDecember 2027
Ratle commissioningUnder constructionDecember 2027
Dibang Multipurpose Project completion5 of 7 contract packages awarded; Dam Contract award targeted in 2–3 monthsFebruary 2032
200 MW Solar at KhavdaEPC awarded August 2024August 2025
50 MW Floating Solar KeralaEPC awarded July 2024; Lease Deed executed September 2024February 2026
Regulated Equity trajectory₹13,000 Cr → ₹16,500 Cr (FY25) → ₹17,000 Cr (FY26) → ₹25,365 Cr (FY27) → ₹28,590 Cr (FY28)FY25–FY28 [16-17]
Teesta-V insurance balance recognition₹160 Crore to be booked, subject to insurer consentNext two quarters
FDRE PPA with UP DISCOM1,200 MW pending"Short period" (no date)

Key Metrics

MetricQ2 FY25
Revenue from Operations₹2,551 cr, +3% YoY
Profit After Tax₹905 cr, -37% YoY
Other Income₹370 cr, +187% YoY, driven by Teesta-V insurance claim of ₹138 cr and higher dividend income
Generation803.4 cr units, -11% YoY
Plant Availability Factor84.87%, vs 89.78% in Q2 FY24
Finance Cost₹298 cr, +137% YoY, mainly due to ₹203 cr increase in interest on arbitration/court cases
Employee Cost₹318 cr, flat YoY
Other Expenses₹489 cr, +42% YoY, driven by ₹64 cr increase in insurance expenses and ₹18 cr increase in R&M expenses
Generation Expenses₹313 cr, -21% YoY, mainly due to non-creation of water cess liability in Himachal Pradesh and Sikkim
Depreciation and Amortization₹271 cr, flat YoY
Tax Expenses₹360 cr, vs -₹273 cr in Q2 FY24; MAT credit of ₹141 cr utilized vs ₹519 cr recognized in prior year
Incentive (Secondary Energy + Deviation Charges)₹16 cr, flat YoY
PAF IncentiveNil, due to change in recognition methodology
CAPEX incurred (Half Year FY25)₹4,812 cr, against full-year target of ₹11,762 cr on consolidated basis
Trade Receivables (as of 30 Sep'24)₹4,266 cr, including ₹2,812 cr unbilled debtors; net billed receivables ₹1,245 cr
Net Trade Receivables (as of 5 Nov'24)₹870 cr, with >45 days debtors of ₹118 cr
Teesta-V annual AFC under-recovery~₹40-50 cr (annual AFC ₹450 cr, insurance recovery ₹410 cr); insurance cover expired Sep'24
Regulated Equity (projected)₹16,500 cr by end of FY25, ₹28,590 cr by FY28
Dulhasti ROE securitization₹2,348 cr realized for 8 years
REIA capacity tendered~9,000 MW; PPA signed/consent received for ~7,000 MW