Key Takeaways
- Profit optically down, operationally steady: PAT fell 23% YoY to ₹1,929 Crore, but the entire dip traces to a one-time MAT Credit recognized last year that did not repeat; Operating Profit was comparable YoY.
- Teesta-V is the single largest drag: The 510 MW station has been shut since October 2023 after a flash flood, then suffered a second incident in August 2024; it will not restart until December 2025, and Business Interruption insurance cover expired in September 2024.
- The commissioning pipeline is dense and near-dated: Parbati-II (Feb’25), Subansiri Lower first 3 units (Mar’25), Rangit-IV (Dec’25), and Pakal Dul (Sep’26) are all approaching COD, setting up a Regulated Equity trajectory that management says will more than double from ₹13,000 Crore to ₹28,500 Crore over four years.[16-17]
- Balance sheet capacity is deliberately underused: Debt-Equity stands at just 0.84x, and management is explicit that internal accruals plus undrawn debt headroom can fund the equity needs of the next wave of projects without strain.
- What to watch next quarter: Whether Parbati-II actually commissions in February 2025 after already slipping from December 2024, and whether the ₹160 Crore balance Teesta-V insurance claim receives insurer consent.
The Teesta-V Overhang
- Two disasters, one station: The October 2023 glacial lake outburst flood in the Teesta basin shut Teesta-V completely; restoration was underway when a landslide in August 2024 damaged the Tail Race Tunnel outlet structure and GIS Building, pushing the restart timeline out to December 2025.
- Insurance cover has now lapsed: Business Interruption loss was fully insured for one year, which ended in September 2024. After that date, no further BI loss is recoverable from the insurer, leaving an annual AFC of ~₹450 Crore exposed, with management estimating net under-recoveries at only ₹40–50 Crore after insurance.
- The accounting is asymmetric: Insurance claim recoveries flow through Other Income (₹155 Crore booked in H1), while the corresponding losses sit in Other Expenses, inflating both lines without touching operating profit.[22-23]
- Cost structure is almost entirely fixed: ~90% of Teesta-V’s costs are O&M staff, interest, finance charges and depreciation; there is negligible variable cost relief from the shutdown.
Management: "As per our latest estimate, this plant will commence generation by December’25. Reason being, this plant suffered a second incident in August’24."
Commissioning Pipeline & Regulated Equity Build
- The near-term catalysts are stacked: Parbati-II (800 MW, 98% physical progress) is targeting February 2025 commissioning after slipping from December 2024; Subansiri Lower (2,000 MW, 94% progress) expects three units by March 2025 and the remaining five in a phased manner through May 2026; Rangit-IV (120 MW, 80% progress) is due December 2025.
- The medium-term pipeline extends the runway: Pakal Dul (1,000 MW) and Kiru (624 MW) are both slated for September 2026; Teesta-VI (500 MW), Kwar (540 MW) and Ratle (850 MW) target December 2027; Dibang Multipurpose Project is scheduled for February 2032.
- Regulated Equity is the earnings flywheel: Management laid out a year-by-year trajectory: ₹16,500 Crore by end-FY25 (post Parbati-II), ₹17,000 Crore in FY26 (post Rangit-IV), ₹25,365 Crore by FY27 (post full Subansiri and Pakal Dul), and ₹28,590 Crore by FY28 (post Teesta-VI, Kwar, Ratle). That is more than a doubling from the current ~₹13,000 Crore base. [16-17]
- PAF Incentive recognition has changed: Incentive will now be recognized only after capacity charges of a particular power station are fully recovered, pushing the bulk of recognition to Q4; the current quarter and half-year carry nil PAF Incentive.
R.P. Goyal: "So, meaning thereby, in next four years, our Regulated Equity is going to be more than double. So, current level of Rs. 13,000 Crore is going to be Rs. 28,500 Crore."
Financials: The PAT Story Is a Tax Story
- Operating profit held up: Management stated explicitly that Operating Profit is comparable with last year; the 23% YoY PAT decline to ₹1,929 Crore is driven entirely by MAT Credit timing: ₹529 Crore was recognized in H1 last year versus nil in the current period, plus a ₹221 Crore MAT Credit utilization this half-year.[12-13]
- Revenue was flattish with a mix shift: H1 Revenue from Operations dipped ~2% YoY, but Q2 standalone was up 3% YoY, helped by ₹170 Crore of prior-year sales and ₹169 Crore of unbilled revenue toward insurance and security expenses, partially offset by a ₹190 Crore decline in Energy Charges.
- Other Income surged on insurance and one-offs: H1 Other Income rose 81% YoY, driven by ₹155 Crore of Business Interruption insurance realization for Teesta-V, a ₹99 Crore reversal of provision for Bursar Project expenditure, and ₹54 Crore of higher Dividend Income.
- Generation Expenses fell on a regulatory reprieve: H1 Generation Expenses dropped ₹320 Crore, mainly because no Water Cess liability was created for Himachal Pradesh stations (the relevant Act was deemed unconstitutional by the High Court) and for Sikkim stations (management views the obligation beyond amounts already paid as contingent).
- Finance Cost rose on litigation interest: H1 Finance Cost increased ₹281 Crore, almost entirely from a ₹338 Crore rise in Interest on Arbitration/Court Cases, partly offset by lower weighted-average interest rates and loan repayments. Under CERC Regulations 2024-29, such interest is recoverable from beneficiaries after a CERC order, and petitions have been filed.
- Trade Receivables improved sharply: Net Trade Receivables stood at ₹870 Crore as of 5 November 2024, with over-45-day debtors of only ₹118 Crore.
Capital Position & Funding Capacity
- The balance sheet is deliberately under-levered: Debt-Equity stands at 0.84x, and management argues that after commissioning of ongoing projects, internal accruals will be sufficient to infuse equity into upcoming projects; for debt, there is ample headroom because the company is "very under leveraged."
- Dulhasti ROE securitization executed: The company realized ₹2,348 Crore for an 8-year tenor, demonstrating access to structured financing.
- Dividend maintained: Total dividend for FY24 was 19% (₹1.90 per share), comprising a 14% interim and a 5% final paid in September 2024. [13-14]
Renewables & Pumped Storage: Early but Intentional
- Solar capacity is being built, not just talked about: The 88 MW NHDC Floating Solar project was fully commissioned and achieved COD on 29 October 2024; a 200 MW Solar project at Khavda (EPC awarded August 2024) targets August 2025 commissioning; a 50 MW Floating Solar project in Kerala (EPC awarded July 2024) targets February 2026.
- The Rajasthan MoU signals scale ambition: A ₹50,000 Crore investment plan was signed with the Rajasthan government on 30 September 2024, covering Pumped Storage Projects, Renewables (Solar, Floating Solar, Wind) and BESS.
- Pumped Storage exploration is widespread: PFRs have been submitted for projects in Andhra Pradesh, Odisha, Jharkhand, Madhya Pradesh, Chhattisgarh, Gujarat, Tripura, Punjab and Maharashtra; a DPR for Savitri PSP is under preparation.
- PPA risk sits with DISCOMs, not NHPC: For projects implemented in REIA Mode, NHPC carries no CAPEX risk; if the tariff is viable, PPAs will be signed, and if the tariff is high, DISCOMs may refuse, but that refusal does not create a liability for NHPC. A 1,200 MW FDRE PPA with Uttar Pradesh DISCOM is pending and management is hopeful of signing shortly.
Project Execution: Progress & Slippage
- Parbati-II slipped but is now very close: The project was originally slated for December 2024 commissioning; management now targets February 2025, with reservoir filling to start that month and all four units commissioned in a single stroke. The 31.5 km Headrace Tunnel has achieved daylighting, and 98% physical progress is complete.
- Subansiri Lower hit a milestone: The rotor of Unit 3 (673 tons) was successfully lowered on 17 October 2024; overall physical progress is 94%. Three units are targeted by March 2025, with the remaining five phased through May 2026.
- Dibang is moving through contract awards: Five of seven contract packages have been awarded; permanent access is established; diversion tunnel and underground structures are progressing. The Dam Contract tender is in process and management hopes to award it in 2–3 months, leaving only the Hydromechanical package thereafter.
- Dugar and Sawalkot are in early tendering: The Dugar Civil Works tender has been floated with the last date extended by ~3 weeks at bidders’ request; Sawalkot is floating tenders for Infrastructure and Diversion Tunnel Works and Consultancy for Dam Design.
- Nepal projects are advancing through DPR stages: The Final DPR for West Seti HE Project was submitted to the Investment Board of Nepal in October 2024, and an MoU for grid connectivity was signed in May 2024; the Inception Report for West Seti River-6 (460 MW) has been accepted and its DPR is under preparation; the Review Report of the DPR for Phukot Karnali (624 MW) was submitted in March 2024.
R.P. Goyal: "As per our plan, it was to be commissioned in December’24. But hydro has some challenges. That’s why we are shifting our goal posts to February’25..."
Guidance & Commitments
| Commitment | Specifics | Timeline |
|---|---|---|
| Teesta-V generation restart | Plant to commence generation after two incidents (Oct’23 flood, Aug’24 landslide) | December 2025 |
| Parbati-II commissioning | All 4 units in a single stroke; reservoir filling starts Feb’25 | February 2025 |
| Subansiri Lower first units | 3 units commissioned; remaining 5 phased thereafter | 3 units by March 2025; full project by May 2026 |
| Rangit-IV completion | 80% physical progress achieved | December 2025 |
| Pakal Dul completion | Under construction | September 2026 |
| Kiru completion | Under construction | September 2026 |
| Teesta-VI commissioning | Under construction | December 2027 |
| Kwar commissioning | Under construction | December 2027 |
| Ratle commissioning | Under construction | December 2027 |
| Dibang Multipurpose Project completion | 5 of 7 contract packages awarded; Dam Contract award targeted in 2–3 months | February 2032 |
| 200 MW Solar at Khavda | EPC awarded August 2024 | August 2025 |
| 50 MW Floating Solar Kerala | EPC awarded July 2024; Lease Deed executed September 2024 | February 2026 |
| Regulated Equity trajectory | ₹13,000 Cr → ₹16,500 Cr (FY25) → ₹17,000 Cr (FY26) → ₹25,365 Cr (FY27) → ₹28,590 Cr (FY28) | FY25–FY28 [16-17] |
| Teesta-V insurance balance recognition | ₹160 Crore to be booked, subject to insurer consent | Next two quarters |
| FDRE PPA with UP DISCOM | 1,200 MW pending | "Short period" (no date) |
Key Metrics
| Metric | Q2 FY25 |
|---|---|
| Revenue from Operations | ₹2,551 cr, +3% YoY |
| Profit After Tax | ₹905 cr, -37% YoY |
| Other Income | ₹370 cr, +187% YoY, driven by Teesta-V insurance claim of ₹138 cr and higher dividend income |
| Generation | 803.4 cr units, -11% YoY |
| Plant Availability Factor | 84.87%, vs 89.78% in Q2 FY24 |
| Finance Cost | ₹298 cr, +137% YoY, mainly due to ₹203 cr increase in interest on arbitration/court cases |
| Employee Cost | ₹318 cr, flat YoY |
| Other Expenses | ₹489 cr, +42% YoY, driven by ₹64 cr increase in insurance expenses and ₹18 cr increase in R&M expenses |
| Generation Expenses | ₹313 cr, -21% YoY, mainly due to non-creation of water cess liability in Himachal Pradesh and Sikkim |
| Depreciation and Amortization | ₹271 cr, flat YoY |
| Tax Expenses | ₹360 cr, vs -₹273 cr in Q2 FY24; MAT credit of ₹141 cr utilized vs ₹519 cr recognized in prior year |
| Incentive (Secondary Energy + Deviation Charges) | ₹16 cr, flat YoY |
| PAF Incentive | Nil, due to change in recognition methodology |
| CAPEX incurred (Half Year FY25) | ₹4,812 cr, against full-year target of ₹11,762 cr on consolidated basis |
| Trade Receivables (as of 30 Sep'24) | ₹4,266 cr, including ₹2,812 cr unbilled debtors; net billed receivables ₹1,245 cr |
| Net Trade Receivables (as of 5 Nov'24) | ₹870 cr, with >45 days debtors of ₹118 cr |
| Teesta-V annual AFC under-recovery | ~₹40-50 cr (annual AFC ₹450 cr, insurance recovery ₹410 cr); insurance cover expired Sep'24 |
| Regulated Equity (projected) | ₹16,500 cr by end of FY25, ₹28,590 cr by FY28 |
| Dulhasti ROE securitization | ₹2,348 cr realized for 8 years |
| REIA capacity tendered | ~9,000 MW; PPA signed/consent received for ~7,000 MW |