Key Takeaways
- Generation-led earnings surge: Q2 FY27 PAT jumped 52% YoY to ₹1,549 Cr, driven by a 14% H1 generation increase from new unit commissions and the Teesta-V restoration.
- Subansiri Lower begins contributing: With five units now online, the project delivered ₹132 Cr PBT in Q2, boosted by temporarily higher water availability per unit.
- Project pipeline is firming up: Management expressed "100% sure" confidence on timelines for Dibang (Feb’32), Uri-I Stage-II and Dulhasti Stage-II (Nov’29), and Kwar (May’28).
- Receivables spike was temporary: Trade receivables hit ₹4,283 Cr at quarter-end but normalized to ₹1,159 Cr by 3 Nov 2026, with only ₹6 Cr over 45 days.
- What to watch next quarter: The final tariff order for Parbati-II, the interim tariff for Subansiri Lower, and CCEA approval for the 1,800 MW Sawalkot project.
The Subansiri Lower Inflection
- Unit commissioning on track: Unit 5 was commissioned on 23 October 2026, bringing operational capacity to1,250 MW (5 of8 units). Two more units are targeted for FY27, with the final unit expected by June2027.
- Profitability boosted by water availability: With fewer units running, water availability per unit is higher, enabling generation ~300 MUs above proportionate design energy for four units. This effect will normalize as more units come online.
- Tariff order awaited: A petition for an interim tariff has been filed, the hearing is complete, and the order is reserved. Management expects it "very soon."
- Full financial impact deferred: The full-year impact of Subansiri Lower is expected largely in FY28, with the full top line from FY29 onwards. On full commissioning, the project is expected to generate an AFC of ~₹5,500 Cr/year and PAT of ₹1,500-1,600 Cr.
- Cost contained: Anticipated cost remains at ₹30,072 Cr, with ₹26,936 Cr incurred (90%) by September2026. Management does not anticipate any further increase.
Gupta: "Te anticipated cost of the project is Rs.30,072 Crore, and we have already incurred around Rs.26,936 Crore till September’26, which is90% of anticipated cost and we don't anticipate any further increase in the cost."
Parbati-II: The Quarter's Star
- Turnaround from loss to profit: Parbati-II swung from a ₹164 Cr loss in Q2 last year to a ₹215 Cr PBT this quarter, contributing ₹380 Cr in incremental PBT YoY.
- Tariff order imminent: The next hearing is fixed for 11th November, with management hoping it will be the final hearing and the order will be reserved thereafter.
- Financial expectations set: Management stated total AFC/revenue of ~₹2,400 Cr, PAT of ~₹680 Cr from 17% base ROE (with incentives of 4-5% on top), and an EBITDA margin of 60-65%.
- Billing underway: An interim order has been received, and75% billing is being done.
Project Execution & Pipeline Confidence
- "100% sure" on key timelines: Management expressed absolute confidence in meeting scheduled completion dates for Dibang (February2032), Uri-I Stage-II and Dulhasti Stage-II (November2029), and Kwar (May2028).
- Near-term commissions stacking up: FY27 targets include an additional500 MW from Subansiri Lower,624 MW from Kiru (reservoir filling from November2026), and120 MW from Rangit-IV (expected December2026). Pakal Dul is targeting two units by March2027 and full commissioning by June2027.
- New project approvals in motion: CCEa approval is expected "very soon" for Sawalkot (1,800 MW) and within2-3 months for Etalin (3,097 MW). Physical work at both sites is targeted to start during FY27.
- Kamala HEP advancing: CCEa approval was received in April2026 for the ₹26,070 Cr investment. Environment and Forest Clearances are expected this month (November2026), with physical work targeted to start in FY27.
- Transmission evacuation de-risked: A master plan for Arunachal hydro projects is ready, with tariff-based competitive bidding for transmission lines run by PFC/ReC. Management sees no evacuation problem.
Gupta: "I am100% sure that both the projects, Uri-I Stage-II and Dulhasti Stage-II, will be commissioned within the scheduled time."
Receivables: Spike and Normalization
- Quarter-end spike explained: Trade receivables rose to ₹4,283 Cr as of30 Sep2026 from ₹2,630 Cr on31 Mar2026. After adjusting for unbilled debtors and instalment-converted dues, the net amount due was ₹1,893 Cr, with dues over45 days at ₹290 Cr.
- Rapid post-quarter normalization: By3 November2026, receivables had normalized to ₹1,159 Cr, with only ₹6 Cr over45 days. This reflects an average debtor turnover of51 days and timely collections.
- Disciplined recovery framework: The Electricity Late Payment Surcharge Rules2023 have streamlined dues. Management stated no dues are pending beyond75 days, calling the recovery position "very good."
- Subansiri Lower excluded from reported receivables: All revenue from Subansiri Lower is booked to unbilled debtors (contract assets) and is not included in the ~₹4,300 Cr reported receivables figure.
Sharma: "Beyond75 days, we don't have a single penny pending."
Renewable Energy: Cautious Growth
- Construction portfolio progressing slowly:1,190 MW of RE is under construction, to be100% completed next year, with delays attributed to connectivity availability.
- PPa tie-up strategy is selective: Management expects to sign an additional ~5,000–7,070 MW of PPAs, totalling ~15,000 MW. However, ~5,000 MW may not be tied up due to states' reluctance to commit to25-year PPAs amid changing energy requirement patterns.
- No build-without-PPA policy: Management was explicit that it will not construct projects without PPAs to avoid an "unnecessary dent on finances." The company is discussing internally and with stakeholders what type and configuration of RE power can be sold long-term.
- NHPC Green Energy structure: No hive-off is planned until projects are commissioned. After commissioning, options will be evaluated. Discussions are ongoing with various states for JVs for floating solar, solar, solar plus BESS, and wind projects.
Gupta: "Te don't want to construct the projects and then we are not having any PPA. Tat we do not want to do. Tat will be unnecessary dent on my finances."
Financial Health & Capex
- Capex run-rate achievable: The FY27 target of ₹14,300 Cr is on track, with ₹6,500 Cr achieved so far and better utilization expected in H2. From next year onward, average consolidated capex is expected at ~₹14,000–₹15,000 Cr.
- Internally funded equity: Internal accruals are sufficient for the equity requirement, with no fresh equity needed. FY28 operating cash is projected at ~₹10,000 Cr against a dividend of ~₹1,800 Cr and debt repayment of ~₹2,800–₹3,000 Cr, leaving ~₹4,000 Cr+ for capex.
- 10-year plan sized: Total capex of ₹1,11,000 Cr is planned, with a ₹40,000 Cr equity requirement. The average ~₹4,000 Cr/year equity from NHPC is covered by internal resources.
- Debt under control: Management reassured that at the consolidated level, Debt/Equity and Debt/EBITDA ratios are "very much in control."
- EBITDA trajectory: Post-commissioning of Subansiri Lower (full year), Pakal Dul, and other projects, EBITDA is expected to reach ~₹10,000 Cr.
Guidance & Commitments
| Commitment | Specifics | Timeline |
|---|---|---|
| Subansiri Lower unit commissioning | 2 more units commissioned | During FY27 |
| Subansiri Lower final unit | Remaining1 unit commissioned | By June2027 |
| Dibang Multipurpose Project | Completion | February2032 |
| Uri-I Stage-II | Commissioning | November2029 |
| Dulhasti Stage-II | Commissioning | November2029 |
| Kwar HEP | Commissioning | May2028 |
| Pakal Dul HEP | Full commissioning of all units | By June2027 |
| Kiru HEP | All units commissioned | By March2027 |
| Rangit-IV HEP | Commissioning | By December2026 |
| Kamala HEP | Physical work at site starts | During FY27 |
| Etalin HEP | Physical work at site starts | During FY27 |
| Sawalkot HEP | Two major packages awarded | By end of FY27, if CCEa approval by Dec2026 |
| Indira Sagar - Omkareshwar PSP | Physical work commences | During FY27 |
| RE under construction (1,190 MW) | 100% completed | Next year (FY28) |
| FY27 capex | ₹14,300 Cr | FY27 |
| Average consol capex (from FY28 onward) | ~₹14,000–₹15,000 Cr/year | FY28 onward |
Key Metrics
| Metric | Q2 FY27 |
|---|---|
| Revenue from Operations | ₹4,482 cr, up 33% YoY (₹1,117 cr) |
| PAT (reported) | ₹1,549 cr, up 52% YoY (₹528 cr) |
| PAT (adjusted, per an analyst's math) | ~₹1,700 cr, adding back ₹231 cr Teesta-IV provision |
| Other Income | ₹187 cr, down 29% YoY (₹78 cr) |
| Generation | 13,935 MUs, up 17% YoY (2,065 MUs) |
| Plant Availability Factor | 92.24%, up ~14 ppt YoY from 78.58% |
| Total Incentives | ₹59 cr, down from ₹253 cr in Q2 FY26 |
| Generation Expenses | ₹277 cr, down ₹25 cr YoY |
| Employee Benefit Expenses | ₹392 cr, up ₹66 cr YoY |
| Finance Cost | ₹556 cr, up ₹278 cr YoY |
| Depreciation & Amortization | ₹610 cr, up ₹169 cr YoY |
| Other Expenses | ₹938 cr, up ₹228 cr YoY; includes ₹231 cr provision for Teesta-IV |
| Tax Expenses | ₹536 cr, similar to Q2 FY26 |
| H1 FY27 CAPEX | ₹5,232 cr (consolidated), vs ₹5,683 cr in H1 FY26 |
| Trade Receivables (30 Sep 2026) | ₹4,283 cr, vs ₹2,630 cr on 31 Mar 2026; dues >45 days: ₹290 cr |