NHPC Ltd Q3 FY2026 Concall Summary

Source transcript PDF: https://assets.stockscans.in/docs/k72ox7rx62d90i2sa6k0xqnm.pdf

Key Takeaways


Generation & Operational Performance


Financial Performance: The One-Off Distortion

Saroj Kumar Roy: "Yes, as DF sir has already shared with you while sharing the variance in the line item that during Q3 of the corresponding period, we had a one-off revenue to the extent of Rs. 500 Crore, on account of pay anomalies and interest on arbitration. So, if you exclude Rs. 500 Crore from the previous year, then you will find that our Revenue is higher than the corresponding period."

Project Execution: The Commissioning Pipeline

Bhupender Gupta: "This is a very good project for us, because the levelized tariff of this project is Rs. 4.46 per unit and we intend to complete it as early as possible."

The Tariff Overhang: 80% Recognition and CERC Timelines

Saroj Kumar Roy: "All these delays were beyond the control of the management and CERC is very much clear in their regulation that any cost overrun beyond the control of the management shall be part of the capital cost for tariff determination. So, we are very much sure that whatever tariff and whatever cost we are going with to CERC, they will consider definitely."

The Next Wave: New Project Starts


RE Market Shift and Pumped Storage

Bhupender Gupta: "Discoms are now planning that they will not sign the PPA for like standalone solar. And they want that solar with the battery or some other alternative like solar plus wind plus battery, because they want now 24-hour round the clock (RTC) supply or they want assured peak."

Guidance & Commitments

CommitmentSpecificsTimeline
Subansiri Lower full commissioningAll 8 units (2,000 MW) onlineBy December 2026
Subansiri Lower tariff petition filingPetition to CERCFirst week of March 2026
Subansiri Lower interim tariffInterim tariff order from CERCWithin ~2 months of petition filing
Parbati-II final tariffCERC final tariff notificationWithin 5–6 months
Pakal Dul, Kiru, Rangit-IV commissioningAll units onlineBy December 2026 (Pakal Dul, Kiru); October/November 2026 (Rangit-IV)
Ratle HE Project completionFull commissioningBy November 2028
Dibang dam contract awardAward to winning bidderWithin March 2026
Dibang Multipurpose Project completionFull commissioningTarget 2032
Teesta-VI completionFull commissioningTarget 2029
Solar capacity addition100 MW Andhra, 600 MW Gujarat, 200 MW Khavda Stage-IIIJune 2026, December 2026, March 2026 respectively
New hydro project construction starts5–6 projects, ~10,000 MW (Uri-I St-II, Dulhasti St-II, Sawalkot, Subansiri Upper, Etalin, Kamala)Staggered across Q1–Q3 FY27
Etalin construction startStart of constructionJuly/August 2026
Kamala (Middle Subansiri) construction startStart of constructionMay/June 2026
Pumped storage construction startsAt least 2 projects, ~2,000 MW or moreDuring calendar year 2026
CAPEXRs. 13,300 Crore (FY26), Rs. 15,000 Crore (FY27), Rs. 12,000–13,000 Crore annual average thereafterFY26, FY27, medium term
RE PPA signings2,000–3,000 MWNext 2–3 months

Key Metrics

MetricQ3 FY26
Revenue from Operations₹2,221 cr, -3% YoY (previous Q3 had ~₹500 cr one-off from pay anomaly and arbitration interest)
Revenue from Operations (9M)₹8,800 cr, +10% YoY
PAT (9M)₹2,306 cr, +7% YoY
Adjusted PAT (Q3)Reported PAT + ₹116 cr (loss from Parbati-II added back, per management)
Other Income₹272 cr, -18% YoY; lower business interruption loss realization offset by insurance claim income
Employee Cost₹346 cr, -50% YoY; decrease in pay anomaly provision
Finance Cost₹310 cr, -52% YoY; decrease in interest on arbitration/court cases offset by interest on new project debt
Depreciation & Amortization₹457 cr, +54% YoY; commissioning of Parbati-II, Subansiri Lower, Karnisar Solar
Other Expenses₹1,537 cr, +219% YoY; increase in GNA charges (₹781 cr), insurance, and R&M
Tax Expenses₹573 cr, +451% YoY; deferred tax adjustments and MAT credit recognition
Total Incentives₹282 cr, +77% YoY; secondary energy ₹230 cr, PAF incentive ₹39 cr, deviation charges ₹13 cr
Generation (9M)25,849 MUs, +15% YoY; driven by Parbati-II commissioning and better water availability
Plant Availability Factor (9M)79.27%, -3 ppt YoY; monsoon shutdowns at Dulhasti, Salal, Chamera-I and III
CAPEX (9M, consolidated)₹8,844 cr, +19% YoY; FY26 plan ₹13,300 cr, FY27 plan ₹15,000 cr
Capacity Added (FY26, till Dec)1,350 MW; expected additional 2,100 MW by Mar'26, FY27 hydro addition target 2,744 MW
Subansiri Lower Project2 of 8 units commissioned; third unit within the week, fourth by Mar'26; levelized tariff ~₹7.50/unit on ₹28,000 cr capex
Parbati-II Revenue Recognition₹900 cr accounted (80% of estimated); ₹225 cr deferred until final CERC tariff order
Transmission Charges (Subansiri)₹781 cr booked up to Dec'25, recoverable; to decrease as more units commissioned
Solar Capacity Under Construction1,190 MW; 300 MW Karnisar commissioned, 100 MW AP by Jun'26, 600 MW Gujarat by Dec'26
REIA PPA Status6,000 MW signed out of ~20,000 MW bid out; 2,000–3,000 MW expected in next 2–3 months