Key Takeaways
- A quarter distorted by a one-off, not a demand problem: Q3 revenue fell 3% YoY only because the prior-year quarter included a ~Rs. 500 Crore one-off from pay anomaly and interest on arbitration; strip that out and revenue grew.
- The build-out is accelerating: Two units of Subansiri Lower (2,000 MW) commissioned, 300 MW Karnisar Solar fully online, and management plans to start construction on 5–6 new hydro projects totaling ~10,000 MW this year.
- Tariff confidence is high but the clock is ticking: Parbati-II and Subansiri Lower are booking revenue at only 80% of estimated tariff pending CERC orders; management is "very much sure" of full cost recovery, but final orders are 5–6 months away for Parbati-II and longer for Subansiri.
- RE PPA market has shifted underfoot: Discoms now want solar-with-battery or round-the-clock supply, not standalone solar, creating a mismatch NHPC is working to resolve; management hopes to sign 2,000–3,000 MW of PPAs in the next 2–3 months.
- What to watch next quarter: Whether the Subansiri interim tariff order lands within the promised ~2 months, the pace of PPA signings in a changed RE market, and whether the dam contract for Dibang closes this month as guided.
Generation & Operational Performance
- Nine-month generation up 15%: Driven mainly by commissioning of Parbati-II (800 MW), which also increased water availability and generation at downstream Parbati-III, plus improvements at some other power stations.
- Plant Availability Factor dipped 3%: The decline came from monsoon shutdowns at Dulhasti, Salal, Chamera-I and Chamera-III that were beyond management's control; recovery is expected over the full financial year.
- Secondary energy doubled in Q3: Subsidiary NHDC had already achieved its design energy, so all incremental generation was accounted as secondary energy, boosting the quarter.
- Under-recoveries are nil: Normative recoveries are proceeding smoothly with no outstanding issues.
Financial Performance: The One-Off Distortion
- Q3 revenue fell 3% YoY, but the headline hides growth: The prior-year quarter included ~Rs. 500 Crore from pay anomaly and interest on arbitration that did not repeat. Excluding that one-off, Q3 revenue was higher than the corresponding period.
- Nine-month revenue rose 10%: The same Parbati-II commissioning that lifted generation also lifted the top line over the nine-month period.
- Other income fell sharply: Down 25% for nine months and 18% for Q3, mainly because the prior year included Rs. 352 Crore of business interruption loss realizations from Teesta-V that did not recur; partially offset by fresh insurance claim income of Rs. 251 Crore (Teesta-V Rs. 132 Crore, Parbati-II Rs. 121 Crore).
- Employee costs provided a tailwind: Nine-month employee costs fell Rs. 306 Crore, largely because the prior year carried Rs. 363 Crore of pay anomaly remuneration that was absent this period, partly offset by increments and DA.
- Finance costs fell despite new borrowings: Nine-month finance costs dropped Rs. 352 Crore as a Rs. 894 Crore decrease in interest on arbitration and court cases more than offset Rs. 518 Crore of higher interest on bonds and term loans tied to Parbati-II, Subansiri Lower and Karnisar Solar, which are now charged to P&L post-commissioning.
- Depreciation and other expenses rose with the asset base: Depreciation increased Rs. 456 Crore on newly commissioned stations; other expenses rose Rs. 1,447 Crore, driven by Rs. 781 Crore of general network access charges, Rs. 323 Crore of higher insurance, and Rs. 71 Crore of higher R&M.
Saroj Kumar Roy: "Yes, as DF sir has already shared with you while sharing the variance in the line item that during Q3 of the corresponding period, we had a one-off revenue to the extent of Rs. 500 Crore, on account of pay anomalies and interest on arbitration. So, if you exclude Rs. 500 Crore from the previous year, then you will find that our Revenue is higher than the corresponding period."
Project Execution: The Commissioning Pipeline
- Subansiri Lower (2,000 MW) is the near-term driver: Two units already commissioned; the third unit is expected within the week of the call, the fourth by end-March 2026, and all remaining four units by December 2026.
- Three JV projects are racing toward year-end deadlines: Pakal Dul, Kiru, and Rangit-IV (120 MW, 95% complete, only HRT work left) are all targeted for commissioning by October–December 2026; management is confident on all three.
- Ratle is on track for November 2028: Dam pit excavation is complete and concreting has begun, a major milestone witnessed by the Power Minister; management is "fully confident" of meeting the deadline.
- Dibang (2,880 MW) is at an inflection point: The dam tender price bid opened on the day of the call with four bidders; the contract is to be awarded within the month. Underground cavern excavation is at a very advanced stage and six diversion tunnels are nearly complete. The 2032 target stands.
- Teesta-VI taken over from NCLT: Physical progress has reached 71%; management is proceeding "very methodological and careful" given geological risks, with a targeted commissioning of 2029.
- Solar build-out continues: 300 MW Karnisar fully commissioned (NHPC's largest solar project); 100 MW in Andhra Pradesh expected by June 2026, 600 MW in Gujarat by December 2026, and 200 MW at Khavda Stage-III by March 2026 — over 1,000 MW of solar to be added this calendar year.
Bhupender Gupta: "This is a very good project for us, because the levelized tariff of this project is Rs. 4.46 per unit and we intend to complete it as early as possible."
The Tariff Overhang: 80% Recognition and CERC Timelines
- Parbati-II is booking only 80% of estimated revenue: Rs. 900 Crore has been recognized over nine months against 100% of expenses taken, meaning true profitability is understated. Final CERC tariff notification is expected in 5–6 months.
- Subansiri Lower follows the same conservative policy: 80% revenue recognition until tariff is set. The tariff petition will be filed in the first week of March 2026; interim tariff is expected within ~2 months of filing; final tariff will come only after the last unit is commissioned.
- Management is adamant that costs will be fully allowed: All delays were beyond management's control, and CERC regulations explicitly permit cost overruns beyond control to be included in capital cost for tariff determination. Management sees "very less chances of any sort of disallowance" and will take up the petition "very strongly."
- The Subansiri tariff math: At Rs. 7.50/unit over 25 years, management argues this is not a high tariff for peaking, clean power, and internal and stakeholder discussions have not surfaced any reason to expect CERC deductions.
- Transmission charges are a working-capital item: Rs. 781 Crore is recoverable from Power Grid up to December 2025 for Subansiri; this amount will decrease as units are added (four by March), with some recovery from ATC next financial year but not to the same extent.
Saroj Kumar Roy: "All these delays were beyond the control of the management and CERC is very much clear in their regulation that any cost overrun beyond the control of the management shall be part of the capital cost for tariff determination. So, we are very much sure that whatever tariff and whatever cost we are going with to CERC, they will consider definitely."
The Next Wave: New Project Starts
- A 10,000 MW construction start target this year: Five to six projects are planned to begin construction during FY27: Uri-I Stage-II (240 MW), Dulhasti Stage-II (260 MW), Sawalkot (1,856 MW), Subansiri Upper (1,605 MW), Etalin (3,097 MW), and Kamala/Middle Subansiri (1,720 MW). Starts will be staggered across Q1, Q2, and Q3 of FY27.
- Etalin has been reassigned to NHPC: The Ministry of Power moved the 3,097 MW project from SJVN to NHPC; NHPC will reimburse SJVN for expenditure incurred, mainly land procurement. Environment and forest clearances are in place, ~90% of land is acquired, and construction is expected to start from July/August 2026.
- Kamala (Middle Subansiri) is the most advanced: PIB clearance obtained, property survey done, district administration award expected anytime, all clearances including land expected by end-March, contract award in April/May, and construction start from May/June.
- Upper Subansiri follows 4–5 months behind: Property surveys are ongoing and forest clearance is at an advanced stage; the gap between Middle and Upper Subansiri starts is expected to be around 4–5 months.
- Geology looks more favorable than Lower Subansiri: Terrain and geological conditions at Upper Subansiri, Middle Subansiri and Etalin are "much better" than Lower Subansiri; Dibang geology is also very good based on investigation. Management does not foresee many surprises, though it cautions "we can never avoid any surprise."
RE Market Shift and Pumped Storage
- The standalone solar PPA market has dried up: Discoms are now refusing to sign PPAs for standalone solar because connectivity is available only in 2029–30; they want solar with battery, solar-wind-battery hybrids, or round-the-clock/assured peak supply. This has created a mismatch between adequacy plans, demand, and available power.
- NHPC is working the policy channels: The issue has been raised in meetings with MNRE and the Ministry of Power chaired by the Power Minister and MNRE Minister; some aspects are resolvable and management expects a positive outcome, with hopes of signing 2,000–3,000 MW of PPAs in the next 2–3 months.
- Pumped storage is the strategic answer: NHPC is exploring PSPs across eight states (Andhra Pradesh, Odisha, Madhya Pradesh, Chhattisgarh, Gujarat, Punjab, Rajasthan, Maharashtra) with DPRs under process. Management plans to start construction on at least two projects totaling ~2,000 MW or more this calendar year, and is "100% sure" projects will be attractive at a generation cost of ~Rs. 4.50/unit and total cost of ~Rs. 7.00/unit, with confident offtake from beneficiaries who hold solar in their portfolios.
- Omkareshwar PSP (640 MW) looks attractive based on preliminary feasibility analysis; only viable PSP projects are being pursued.
Bhupender Gupta: "Discoms are now planning that they will not sign the PPA for like standalone solar. And they want that solar with the battery or some other alternative like solar plus wind plus battery, because they want now 24-hour round the clock (RTC) supply or they want assured peak."
Guidance & Commitments
| Commitment | Specifics | Timeline |
|---|---|---|
| Subansiri Lower full commissioning | All 8 units (2,000 MW) online | By December 2026 |
| Subansiri Lower tariff petition filing | Petition to CERC | First week of March 2026 |
| Subansiri Lower interim tariff | Interim tariff order from CERC | Within ~2 months of petition filing |
| Parbati-II final tariff | CERC final tariff notification | Within 5–6 months |
| Pakal Dul, Kiru, Rangit-IV commissioning | All units online | By December 2026 (Pakal Dul, Kiru); October/November 2026 (Rangit-IV) |
| Ratle HE Project completion | Full commissioning | By November 2028 |
| Dibang dam contract award | Award to winning bidder | Within March 2026 |
| Dibang Multipurpose Project completion | Full commissioning | Target 2032 |
| Teesta-VI completion | Full commissioning | Target 2029 |
| Solar capacity addition | 100 MW Andhra, 600 MW Gujarat, 200 MW Khavda Stage-III | June 2026, December 2026, March 2026 respectively |
| New hydro project construction starts | 5–6 projects, ~10,000 MW (Uri-I St-II, Dulhasti St-II, Sawalkot, Subansiri Upper, Etalin, Kamala) | Staggered across Q1–Q3 FY27 |
| Etalin construction start | Start of construction | July/August 2026 |
| Kamala (Middle Subansiri) construction start | Start of construction | May/June 2026 |
| Pumped storage construction starts | At least 2 projects, ~2,000 MW or more | During calendar year 2026 |
| CAPEX | Rs. 13,300 Crore (FY26), Rs. 15,000 Crore (FY27), Rs. 12,000–13,000 Crore annual average thereafter | FY26, FY27, medium term |
| RE PPA signings | 2,000–3,000 MW | Next 2–3 months |
Key Metrics
| Metric | Q3 FY26 |
|---|---|
| Revenue from Operations | ₹2,221 cr, -3% YoY (previous Q3 had ~₹500 cr one-off from pay anomaly and arbitration interest) |
| Revenue from Operations (9M) | ₹8,800 cr, +10% YoY |
| PAT (9M) | ₹2,306 cr, +7% YoY |
| Adjusted PAT (Q3) | Reported PAT + ₹116 cr (loss from Parbati-II added back, per management) |
| Other Income | ₹272 cr, -18% YoY; lower business interruption loss realization offset by insurance claim income |
| Employee Cost | ₹346 cr, -50% YoY; decrease in pay anomaly provision |
| Finance Cost | ₹310 cr, -52% YoY; decrease in interest on arbitration/court cases offset by interest on new project debt |
| Depreciation & Amortization | ₹457 cr, +54% YoY; commissioning of Parbati-II, Subansiri Lower, Karnisar Solar |
| Other Expenses | ₹1,537 cr, +219% YoY; increase in GNA charges (₹781 cr), insurance, and R&M |
| Tax Expenses | ₹573 cr, +451% YoY; deferred tax adjustments and MAT credit recognition |
| Total Incentives | ₹282 cr, +77% YoY; secondary energy ₹230 cr, PAF incentive ₹39 cr, deviation charges ₹13 cr |
| Generation (9M) | 25,849 MUs, +15% YoY; driven by Parbati-II commissioning and better water availability |
| Plant Availability Factor (9M) | 79.27%, -3 ppt YoY; monsoon shutdowns at Dulhasti, Salal, Chamera-I and III |
| CAPEX (9M, consolidated) | ₹8,844 cr, +19% YoY; FY26 plan ₹13,300 cr, FY27 plan ₹15,000 cr |
| Capacity Added (FY26, till Dec) | 1,350 MW; expected additional 2,100 MW by Mar'26, FY27 hydro addition target 2,744 MW |
| Subansiri Lower Project | 2 of 8 units commissioned; third unit within the week, fourth by Mar'26; levelized tariff ~₹7.50/unit on ₹28,000 cr capex |
| Parbati-II Revenue Recognition | ₹900 cr accounted (80% of estimated); ₹225 cr deferred until final CERC tariff order |
| Transmission Charges (Subansiri) | ₹781 cr booked up to Dec'25, recoverable; to decrease as more units commissioned |
| Solar Capacity Under Construction | 1,190 MW; 300 MW Karnisar commissioned, 100 MW AP by Jun'26, 600 MW Gujarat by Dec'26 |
| REIA PPA Status | 6,000 MW signed out of ~20,000 MW bid out; 2,000–3,000 MW expected in next 2–3 months |