Key Takeaways
- A year scarred by Teesta, rescued by tariffs: PAT fell ~17% YoY to ₹3,084 Cr as the Teesta-V flash flood wiped out ~₹400 Cr at the PBT level, but a ₹742 Cr prior-period tariff bump and Parbati-II commissioning cushioned the blow.
- Parbati-II is now the new earnings anchor: All four units (800 MW) are online and capitalized from April 2025, promising a full year of generation and 90% provisional tariff recognition, making it NHPC's largest operating station.
- The commissioning pipeline is dense and near-dated: Subansiri Lower's first three units are due by June 2025, with the remaining five by May 2026; Rangit-IV, Pakaldul, and Kiru are all slated within the next 18 months.
- Receivables quality is better than the headline suggests: Gross trade receivables stand at ₹4,412 Cr, but net billed receivables are only ₹616 Cr, with overdue at just ₹220 Cr, while the bulk is tied up in unbilled AFC and regulatory interest.
- What to watch next quarter: The pace of Subansiri Lower unit commissioning against the June 2025 deadline, the CERC tariff order for Parbati-II, and any movement on investment approval for the 1,856 MW Sawalkot project.
The Teesta Shock: Damage, Restoration & Financial Hit
- Teesta-V remains fully shut: The October 2023 flash flood in the Teesta Basin caused a complete shutdown of the 510 MW Teesta-V Power Station, which had generated 196.6 crore units in the prior year, and a subsequent August 2024 landslide damaged the Tail Race Tunnel outlet and part of the GIS Building, further delaying restoration.
- Restoration timeline pushed to January 2026: Restoration works are progressing well but the station will have been offline for over two years by the time it returns, with the January 2026 target now the firm commitment.
- The P&L damage is concentrated but deep: Normal PBT from the three affected Teesta basin projects (Teesta-V, TLDP-III, TLDP-IV) is ~₹500 Cr annually, but in FY25 they posted a combined loss of ₹92 Cr, implying a ~₹400 Cr swing at the PBT level that accounts for the bulk of the PAT decline.
- Generation and PAF fell in lockstep: Full-year generation dropped ~9% (191.1 crore units) and the Plant Availability Factor slipped to 73.94% from 77.60%, driven by the Teesta-V shutdown, lower water availability, and outages at TLDP-III and Uri-I.
R.K. Chaudhary: "The Indus Water Treaty is not abolished. It is kept under suspension. So in this scenario, yes, you are right that now there is a lot of emphasis and we are going to start the Uri-I Stage-II (240 MW) and we have already floated the tenders for civil works."
Revenue Bridge: Tariff Windfalls Mask Volume Weakness
- Prior-period sales did the heavy lifting: FY25 revenue rose ~7% to ₹8,994 Cr, but the increase was driven by ₹742 Cr in prior-year sales from pay anomaly orders and Annual Fixed Charges revisions, plus ₹540 Cr in unbilled revenue mainly from interest on arbitration cases, while energy charges actually fell ₹262 Cr on lower generation.
- Q4 got a one-off water cess boost: Q4 revenue jumped ~25% YoY (₹410 Cr) largely because the previous Q4 had booked a ₹337 Cr reversal of water cess for Himachal Pradesh and Sikkim following a High Court ruling, creating a favourable base effect alongside an ₹83 Cr increase in capacity charges.
- Other income and finance costs contain offsetting noise: Q4 Other Income fell ₹191 Cr (~32%) on lower dividend income and exchange rate variation gains, while Finance Cost swung to negative ₹30 Cr due to a ₹183 Cr decrease in interest on arbitration cases and a ₹110 Cr reversal that was capitalized, muting the net P&L impact.
- The adjusted PBT story is flatter: Management calculates that Q4 PBT declined only ₹100 Cr, entirely from a one-off ₹110 Cr interest-on-arbitration reversal, while the full-year ₹200 Cr PBT decline breaks down into ₹100 Cr from pay anomaly provisions, ₹26 Cr net interest on arbitration, and ₹100 Cr from lower energy charges.
The Commissioning Wave: Parbati-II Arrives, Subansiri Looms
- Parbati-II is now the flagship: All four units (800 MW) achieved commercial operation, with three units capitalized from 1 April 2025 and the fourth from 15 April 2025, displacing other stations as NHPC's largest operational hydro asset and guaranteeing a full year of generation and revenue in FY26.
- Revenue recognition will be provisional at 90%: NHPC is filing a tariff petition with CERC and will recognize 90% of revenue on a provisional basis until the final order, a standard regulatory approach that front-loads cash flow visibility.
- Subansiri Lower is on the cusp: Dry commissioning of units 1 and 2 is complete, pre-commissioning of unit 3 is underway, and the NDSA team has visited to review the reservoir filling plan, with three units expected by June 2025 and the remaining five by May 2026.
- Dibang is moving from paper to execution: Five of seven contract packages are awarded, the crucial Nalla diversion is achieved, and the two remaining packages are under evaluation with award expected shortly, keeping the February 2032 completion target in sight.
- Smaller projects fill the near-term pipeline: Rangit-IV (JPCL, December 2025), Pakaldul (September 2026), and Kiru (September 2026) are all slated to commission within the next 18 months, while the LTHPL merger is complete and the JPCL merger is progressing through the First Motion Application stage.
R.P. Goyal: "Actually, three units have been capitalized from 1st April '25 and the fourth unit will be capitalized from 15th April '25. So, full year generation and full year revenue will be there and we are in the process of filing tariff petition in the CERC. So, based on filing of tariff petition, we will recognize 90% of the revenue on provisional basis till the order comes from CERC."
The Development Pipeline: New Approvals & Tender Activity
- Uri-I Stage-II and Dulhasti Stage-II are moving to tender: Civil works tenders for Uri-I Stage-II (240 MW) are already floated, with hydro-mechanical and electromechanical tenders due this month, while Dulhasti Stage-II (260 MW) received CEA concurrence today and its civil works tender will be floated by month-end.
- Sawalkot is waiting on one government signature: Bid documents for two packages are prepared and approvals are progressing fast, but the 1,856 MW project cannot proceed to tender until investment approval arrives from the Government of India.
- Kamala and Subansiri Upper are the next big clearance targets: The 1,720 MW Kamala project has cleared pre-DPR chapters with CEA and CWC, with cost chapters likely cleared soon and all clearances expected this year, while the 1,605 MW Subansiri Upper is on track for investment approval by year-end.
- Pumped storage exploration is broad but early-stage: NHPC is exploring PSPs across nine states, with DPRs under preparation for six projects totalling ~7,500 MW and PFRs submitted or prepared for another seven, though no specific commissioning timelines are attached.
- Nepal projects advance on paper: Final DPRs for West Seti (800 MW) and SR-6 (460 MW) were submitted to Nepal's Investment Board in October 2024 and March 2025 respectively, and strategic discussions on joint ventures and PPAs have begun, with a model encompassing both domestic supply and cross-border export.
Receivables & Balance Sheet: The Denominator Problem
- Headline receivables are inflated by regulatory accruals: Gross trade receivables of ₹4,412 Cr include ₹3,677 Cr in unbilled debtors, of which ₹1,366 Cr is unbilled AFC, ₹580 Cr is interest on arbitration and court cases, and ₹485 Cr is the impact of effective tax rate on RoE, items that are regulatory in nature rather than billing disputes.
- Net billed receivables are a manageable ₹616 Cr: After stripping out unbilled debtors and installment-converted dues, the net billed receivable is ₹616 Cr, with overdue amounts at just ₹220 Cr, and as of 19 May 2025, dues older than 45 days stood at only ₹73 Cr.
- Realization dipped but the quality holds: ₹8,349 Cr was received from beneficiaries in FY25 versus ₹9,606 Cr in FY24, a decline consistent with lower generation, while the overdue book remains small relative to the revenue base.
- CAPEX ran close to target: Consolidated CAPEX of ₹11,596 Cr was incurred against a target of ₹11,762 Cr, a 98.6% achievement rate that signals execution discipline even as Teesta restoration consumed resources.
Solar & Diversification: Early Steps, Modest Scale
- Solar commissioning is trickling in: 107 MW out of a 300 MW CPSU scheme project in Bikaner, Rajasthan was commissioned on 12 April 2025, with full commissioning expected by August 2025, while two 200 MW Khavda, Gujarat projects are at the EPC contract stage with tariffs of ₹2.66/unit and commissioning targets of March 2026.
- The solar pipeline is small relative to hydro: At 700 MW of awarded or commissioned solar capacity against a hydro portfolio measured in thousands of megawatts, solar remains a diversification story rather than a near-term earnings driver.
- Land and EPC contracts are in place: A land sub-lease has been executed for a 600 MW solar project in Gujarat, and EPC contracts for the two Khavda stages were awarded in August and December 2024, with site surveys and geo-tech investigations completed for Stage-1.
Guidance & Commitments
| Commitment | Specifics | Timeline |
|---|---|---|
| Teesta-V restoration | Complete restoration and return to service | January 2026 |
| Subansiri Lower commissioning | First 3 units online; remaining 5 units online | June 2025; May 2026 |
| Parbati-II revenue recognition | File tariff petition with CERC; recognize 90% provisional revenue | FY26 (full year) |
| Rangit-IV (JPCL) commissioning | Project commissioned | December 2025 |
| Pakaldul & Kiru commissioning | Both projects commissioned | September 2026 |
| Dibang balance packages award | Two remaining contract packages awarded | "Shortly" |
| Bikaner Solar (300 MW) full commissioning | All capacity online | August 2025 |
| Khavda Solar Stage-3 (200 MW) commissioning | Project commissioned | March 2026 |
| Kamala Hydro (1,720 MW) clearances | All clearances received; move for investment approval, PIB, CCEA | During this year |
| Subansiri Upper (1,605 MW) investment approval | Move for Government investment approval | By year-end |
| Uri-I Stage-II HM & EM tenders | Tenders floated | This month |
| Dulhasti Stage-II civil works tender | Tender floated | This month-end |
| Indra Sagar Omkareshwar PSP DPR clearance | DPR cleared by CWC and CEA | Next 2-3 months |
Key Metrics
| Metric | Q4 FY25 |
|---|---|
| Revenue from Operations | ₹2,059 cr, +25% YoY from ₹1,649 cr |
| FY25 Revenue from Operations | ₹8,994 cr, +7% YoY from ₹8,396 cr |
| PAT | ₹894 cr, +29% YoY from ₹693 cr |
| FY25 PAT | ₹3,084 cr, -17% YoY from ₹3,722 cr |
| Adjusted PBT decline (Q4) | ~₹100 cr one-off from reversal of interest on arbitration |
| FY25 Adjusted PBT decline | ~₹200 cr: ₹100 cr pay anomaly, ₹26 cr interest on arbitration, ₹100 cr lower energy charges |
| Generation | 217 cr units, -6% YoY from 230.4 cr units |
| FY25 Generation | 1,986.2 cr units, -9% YoY from 2,177.3 cr units |
| Plant Availability Factor | 58.59%, +4 ppt YoY from 54.65% |
| FY25 Plant Availability Factor | 73.94%, -4 ppt YoY from 77.60% |
| Finance Cost | Negative ₹30 cr, vs ₹349 cr in Q4 FY24; includes ₹110 cr reversal of interest on arbitration capitalized |
| FY25 CAPEX incurred | ₹11,596 cr on consolidated basis, against target of ₹11,762 cr |
| Total incentives earned | ₹293 cr, vs ₹339 cr in Q4 FY24; Secondary Energy ₹81 cr, PAF-based ₹207 cr, Deviation Charges ₹5 cr |
| FY25 Total incentives earned | ₹385 cr, vs ₹459 cr in FY24; Secondary Energy ₹123 cr, PAF-based ₹227 cr, Deviation Charges ₹35 cr |
| Trade Receivables (31 Mar'25) | ₹4,412 cr, vs ₹3,978 cr as on 31 Mar'24; unbilled ₹3,677 cr, billed ₹735 cr |
| Overdue >45 days (31 Mar'25) | ₹220 cr; net billed receivables ₹616 cr after excluding ₹119 cr converted to installments |
| Parbati-II regulated equity addition | ~₹4,000 cr (30% of ~₹13,000 cr capital cost), taking total regulated equity to ~₹18,000 cr this FY |
| Subansiri Lower incremental revenue | ~₹4,500 cr annually when fully commissioned; 3 units expected by Jun'25, all 8 by May'26 |
| Teesta basin PBT impact | Loss of ~₹400 cr at PBT level from Teesta-V, TLDP-III, TLDP-IV combined, vs normal ~₹500 cr PBT |