NHPC Ltd Q4 FY2025 Concall Summary

Source transcript PDF: https://assets.stockscans.in/docs/sy3ocww7e31ebfkfh71xv2rm.pdf

Key Takeaways


The Teesta Shock: Damage, Restoration & Financial Hit

R.K. Chaudhary: "The Indus Water Treaty is not abolished. It is kept under suspension. So in this scenario, yes, you are right that now there is a lot of emphasis and we are going to start the Uri-I Stage-II (240 MW) and we have already floated the tenders for civil works."

Revenue Bridge: Tariff Windfalls Mask Volume Weakness


The Commissioning Wave: Parbati-II Arrives, Subansiri Looms

R.P. Goyal: "Actually, three units have been capitalized from 1st April '25 and the fourth unit will be capitalized from 15th April '25. So, full year generation and full year revenue will be there and we are in the process of filing tariff petition in the CERC. So, based on filing of tariff petition, we will recognize 90% of the revenue on provisional basis till the order comes from CERC."

The Development Pipeline: New Approvals & Tender Activity


Receivables & Balance Sheet: The Denominator Problem


Solar & Diversification: Early Steps, Modest Scale


Guidance & Commitments

CommitmentSpecificsTimeline
Teesta-V restorationComplete restoration and return to serviceJanuary 2026
Subansiri Lower commissioningFirst 3 units online; remaining 5 units onlineJune 2025; May 2026
Parbati-II revenue recognitionFile tariff petition with CERC; recognize 90% provisional revenueFY26 (full year)
Rangit-IV (JPCL) commissioningProject commissionedDecember 2025
Pakaldul & Kiru commissioningBoth projects commissionedSeptember 2026
Dibang balance packages awardTwo remaining contract packages awarded"Shortly"
Bikaner Solar (300 MW) full commissioningAll capacity onlineAugust 2025
Khavda Solar Stage-3 (200 MW) commissioningProject commissionedMarch 2026
Kamala Hydro (1,720 MW) clearancesAll clearances received; move for investment approval, PIB, CCEADuring this year
Subansiri Upper (1,605 MW) investment approvalMove for Government investment approvalBy year-end
Uri-I Stage-II HM & EM tendersTenders floatedThis month
Dulhasti Stage-II civil works tenderTender floatedThis month-end
Indra Sagar Omkareshwar PSP DPR clearanceDPR cleared by CWC and CEANext 2-3 months

Key Metrics

MetricQ4 FY25
Revenue from Operations₹2,059 cr, +25% YoY from ₹1,649 cr
FY25 Revenue from Operations₹8,994 cr, +7% YoY from ₹8,396 cr
PAT₹894 cr, +29% YoY from ₹693 cr
FY25 PAT₹3,084 cr, -17% YoY from ₹3,722 cr
Adjusted PBT decline (Q4)~₹100 cr one-off from reversal of interest on arbitration
FY25 Adjusted PBT decline~₹200 cr: ₹100 cr pay anomaly, ₹26 cr interest on arbitration, ₹100 cr lower energy charges
Generation217 cr units, -6% YoY from 230.4 cr units
FY25 Generation1,986.2 cr units, -9% YoY from 2,177.3 cr units
Plant Availability Factor58.59%, +4 ppt YoY from 54.65%
FY25 Plant Availability Factor73.94%, -4 ppt YoY from 77.60%
Finance CostNegative ₹30 cr, vs ₹349 cr in Q4 FY24; includes ₹110 cr reversal of interest on arbitration capitalized
FY25 CAPEX incurred₹11,596 cr on consolidated basis, against target of ₹11,762 cr
Total incentives earned₹293 cr, vs ₹339 cr in Q4 FY24; Secondary Energy ₹81 cr, PAF-based ₹207 cr, Deviation Charges ₹5 cr
FY25 Total incentives earned₹385 cr, vs ₹459 cr in FY24; Secondary Energy ₹123 cr, PAF-based ₹227 cr, Deviation Charges ₹35 cr
Trade Receivables (31 Mar'25)₹4,412 cr, vs ₹3,978 cr as on 31 Mar'24; unbilled ₹3,677 cr, billed ₹735 cr
Overdue >45 days (31 Mar'25)₹220 cr; net billed receivables ₹616 cr after excluding ₹119 cr converted to installments
Parbati-II regulated equity addition~₹4,000 cr (30% of ~₹13,000 cr capital cost), taking total regulated equity to ~₹18,000 cr this FY
Subansiri Lower incremental revenue~₹4,500 cr annually when fully commissioned; 3 units expected by Jun'25, all 8 by May'26
Teesta basin PBT impactLoss of ~₹400 cr at PBT level from Teesta-V, TLDP-III, TLDP-IV combined, vs normal ~₹500 cr PBT