NHPC Ltd Q4 FY2026 Concall Summary

Source transcript PDF: https://assets.stockscans.in/docs/9uulzv0qkl4sp475304i3uiy.pdf

Key Takeaways


The Tariff Overhang: Parbati-II and Subansiri Lower

Two major new assets are generating and billing revenue, but both are doing so under interim arrangements that leave material upside on the table pending final regulatory orders.

Mahesh Kumar Sharma: "we have the next hearing date of Parbati-II on 25th of this month only. So, there we are expecting that orders will be reserved. Hopefully, on 25th May, this tariff petition hearing will be completed and the order will be reserved. We will be expecting the final orders by the end of this quarter."

Operations: What Drove the Quarter

Saroj Kumar Roy: "going forward, we are very much sure that June onwards, we are going to have operation to get resumed in respect of Teesta-V. So, by end of June onwards, you can see some top-line activity in Teesta-V also."

The Tax Adjustment: Understanding the Reported PAT

Saroj Kumar Roy: "So, net impact of this deferred tax liability adjustment comes to around Rs. 900 Crore. So, if you reduce Rs. 900 Crore from the Reported PAT, you will arrive at Adjusted PAT."

The Next Growth Cycle: Projects Moving to Construction

Management is pivoting from delivering the current wave of completions to seeding the next one, with an ambitious target of bringing five hydro projects and one large PSP to construction stage this fiscal year.

Saroj Kumar Roy: "Cost escalation in hydro projects are very inherent. You cannot rule out. Even though if there is no time overrun, there will be cost overrun."

Commissioning Pipeline and Renewable Build-Out

ProjectTimelineStatus
Subansiri Lower (remaining 4 of 8 units)One-by-one till March'274 units of 250 MW each already commissioned
Rangit-IV HENovember'26Under construction
Teesta-V restartJune'26Restoration in progress
Pakal Dul HEQ4 FY'27On track
Kiru HEQ4 FY'27On track
Kwar HEMarch'28On track
Ratle HENovember'28Under construction
Teesta-VI HESeptember'29Under construction
Dibang MultipurposeFebruary'32Dam package (₹14,446 Cr) awarded April'26; Nalla diversion achieved

Guidance & Commitments

CommitmentSpecificsTimeline
Parbati-II final tariff orderFinal CERC order; differential revenue plus interest recognized in the quarter of receiptBy June 30, 2026 (end of Q1 FY'27)
Subansiri Lower interim tariffInterim tariff order from CERC to set billing rate above current 80% AFC bookingNo date; petition filed
Subansiri Lower final tariffFinal CERC order expected within six months of interim tariff~6 months after interim order
Teesta-V generation restartStation to resume operations and show top-line activityEnd of June 2026
TLDP-III and TLDP-IV silt resolutionPAF to normalize after silt removal efforts concludeWithin three months
Five hydro projects to construction stageUri-I Stage-II, Dulhasti Stage-II (awarded); Etalin, Sawalkot, Kamala (likely this year)FY'27
Indira Sagar-Omkareshwar PSP construction start640 MW PSP to begin construction activitiesFY'27
Subansiri Lower full commissioningAll eight units operationalBy March 2027
Pakal Dul and Kiru commissioningBoth projects to be commissionedQ4 FY'27

Key Metrics

MetricQ4 FY26
Revenue from operations₹2,816 cr, +20% YoY
Profit after tax (reported)₹1,460 cr, +71% YoY
Adjusted PAT~₹560 cr (per an analyst's math), after removing ~₹900 cr one-off DTL reversal
Other income₹305 cr, +45% YoY
Finance costs₹574 cr, vs -₹12 cr in Q4 FY25
Depreciation, amortization and impairment₹642 cr, vs ₹315 cr in Q4 FY25
Tax expense-₹1,823 cr, vs ₹247 cr in Q4 FY25, due to deferred tax adjustment and MAT credit recognition
Generation377 crore units, +20% YoY
Plant availability factor (PAF)62.47%, vs 66.84% in Q4 FY25
Incentives earned₹366 cr, vs ₹350 cr in Q4 FY25
CAPEX (FY26)₹13,689 cr, vs ₹11,596 cr in FY25
Trade receivables₹2,630 cr as of Mar 31, 2026, vs ₹2,573 cr as of Mar 31, 2025
Net amount due (billed)₹704 cr as of Mar 31, 2026, with dues >45 days at ₹242 cr
Parbati-II profit₹104 cr in Q4, vs a full-year loss of ₹150 cr
Subansiri Lower profit₹487 cr in Q4, vs a full-year profit of ₹495 cr