Key Takeaways
- Tax-adjusted PAT masks a strong operational quarter: Reported PAT fell sharply due to a one-time ~₹900 Cr deferred tax adjustment from the shift to the 25% tax regime. Excluding this, the underlying business saw revenue rise 20% YoY in Q4 on higher generation from newly commissioned assets.
- The commissioning engine is finally delivering: Parbati-II, part of Subansiri Lower, and Karnisar Solar came online, driving a 16% jump in annual generation. This marks a shift from construction-heavy capex to revenue-generating operations.
- Tariff orders are the single biggest swing factor: Parbati-II is billing at an interim 75% of filed tariff, and Subansiri Lower is booking revenue at 80% of expected AFC. Final CERC orders, expected within months, will unlock material catch-up revenue and remove a key overhang.
- A wave of new construction starts is imminent: With Uri-I Stage-II and Dulhasti Stage-II already awarded, management plans to bring three more hydro projects and one large PSP to construction stage this fiscal year, setting up the next growth cycle.
- What to watch next quarter: The final CERC tariff order for Parbati-II (expected by June 30), the restart of generation at the idle Teesta-V station, and concrete progress on awarding the next batch of construction-stage projects.
The Tariff Overhang: Parbati-II and Subansiri Lower
Two major new assets are generating and billing revenue, but both are doing so under interim arrangements that leave material upside on the table pending final regulatory orders.
- Parbati-II billing at 75%: An interim CERC tariff notification allows billing at 75% of the filed tariff. The final hearing is scheduled for 25th May, with orders expected to be reserved then and a final order anticipated by the end of Q1 FY'27.
- Catch-up revenue on final order: If the final order arrives within the quarter, the differential revenue plus interest from the COD will be recognized in that same quarter, creating a one-time lumpy boost.
- Subansiri Lower booking at 80% of AFC: With no interim tariff notification yet, management is conservatively booking revenue at 80% of the expected Annual Fixed Cost based on the capital cost of the three commissioned units (~₹20,000 Cr). This has created an under-recovery of ~₹150 Cr.
- Subansiri tariff timeline: An interim tariff petition has been filed. Management expects an interim tariff order first, followed by a provisional order roughly six months later. As additional units are commissioned, supplementary tariff petitions will be filed.
- Design energy not yet challenged: Parbati-II generated 164.2 crore units vs design energy of 312.5 crore units, partly due to a cloudburst. Management declined to argue for lower design energy, stating regulations require at least three years of data before a challenge can be made.
Mahesh Kumar Sharma: "we have the next hearing date of Parbati-II on 25th of this month only. So, there we are expecting that orders will be reserved. Hopefully, on 25th May, this tariff petition hearing will be completed and the order will be reserved. We will be expecting the final orders by the end of this quarter."
Operations: What Drove the Quarter
- Generation surge: Annual generation rose ~16% YoY, driven by the commissioning of Parbati-II, the subsequent increase in Parbati-III generation, part commissioning of Subansiri Lower, and higher output from Uri-I and NHDC stations.
- PAF dip is temporary: Reported Plant Availability Factor fell ~4% to 75%, dragged down by Teesta-V (which generated zero revenue all year). Excluding Teesta-V, standalone PAF was a healthy 80%, in line with normative levels. The remaining drag came from planned shutdowns at Dulhasti, Chamera-III, and TLDP-IV for MIV repair and gate restoration.
- Parbati-II swung to profit in Q4: Despite a full-year loss of ₹150 Cr, the station reported a ₹104 Cr profit in Q4. This was because the year-end accounting booked the full shortfall of energy (~₹200 Cr) under revenue, per regulations that allow billing for shortfalls beyond the generator's control.
- Teesta-V remains a zero-revenue drag: The station incurred only expenditure in FY'26, with total AFC of ~₹500 Cr (~₹400 Cr ex-tax). Restoration work is underway, with generation expected to resume by end of June.
- Silt issues at TLDP-III and TLDP-IV: Heavy silt accumulation from October 2023 flash floods continues to depress PAF at these stations. Management expects resolution within three months.
Saroj Kumar Roy: "going forward, we are very much sure that June onwards, we are going to have operation to get resumed in respect of Teesta-V. So, by end of June onwards, you can see some top-line activity in Teesta-V also."
The Tax Adjustment: Understanding the Reported PAT
- What happened: The company opted for the lower 25% tax regime under Section 115BAA. Since MAT Credit facilities will be discontinued from FY'27 onwards, a deferred tax liability previously created at a higher rate was restricted to 25%. The net impact on PAT was a negative adjustment of ~₹900 Cr.
- How to read the numbers: Management explicitly guided that adjusted PAT, excluding this one-time deferred tax hit, is the correct measure of operational performance. The adjustment also turned the tax expense line negative for both the quarter and the full year.
- Other income movements: FY'26 other income fell 13% due to the absence of a ₹466 Cr business interruption insurance claim related to Teesta-V that had boosted the prior year. This was partially offset by a ₹321 Cr increase in other insurance claims, mainly for Teesta-V (₹254 Cr) and Parbati-II (₹121 Cr). Q4 other income rose 45% on higher insurance claims and dividend income.
Saroj Kumar Roy: "So, net impact of this deferred tax liability adjustment comes to around Rs. 900 Crore. So, if you reduce Rs. 900 Crore from the Reported PAT, you will arrive at Adjusted PAT."
The Next Growth Cycle: Projects Moving to Construction
Management is pivoting from delivering the current wave of completions to seeding the next one, with an ambitious target of bringing five hydro projects and one large PSP to construction stage this fiscal year.
- Already awarded: Uri-I Stage-II and Dulhasti Stage-II received board investment approval in February 2026, with an implementation agreement signed with J&K State Power Development Corporation in March 2026. Civil contracts were awarded in the same month. Both target November 2029 completion.
- Targeted for FY'27 construction start: Etalin (3,097 MW), Sawalkot (1,856 MW), and Kamala (2,886 MW) are likely to be brought to construction stage this financial year. Kamala received CCEA investment approval of ₹26,070 Cr in April 2026, with a subsidiary being formed and clearances in process.
- PSP entry: The Indira Sagar-Omkareshwar Pumped Storage Project (640 MW) is also targeted to start construction in FY'27. Management declined to provide realization, tariff, or CAPEX details, calling it too early.
- Subansiri Upper deferred: Explicitly pushed to next fiscal year, not this one.
- Cost overrun is the norm, not the exception: Management was candid that cost escalation is inherent in multi-year hydro construction, even without time overruns, due to price variation. CERC allows cost overruns beyond management control, providing a regulatory safety valve.
Saroj Kumar Roy: "Cost escalation in hydro projects are very inherent. You cannot rule out. Even though if there is no time overrun, there will be cost overrun."
Commissioning Pipeline and Renewable Build-Out
| Project | Timeline | Status |
|---|---|---|
| Subansiri Lower (remaining 4 of 8 units) | One-by-one till March'27 | 4 units of 250 MW each already commissioned |
| Rangit-IV HE | November'26 | Under construction |
| Teesta-V restart | June'26 | Restoration in progress |
| Pakal Dul HE | Q4 FY'27 | On track |
| Kiru HE | Q4 FY'27 | On track |
| Kwar HE | March'28 | On track |
| Ratle HE | November'28 | Under construction |
| Teesta-VI HE | September'29 | Under construction |
| Dibang Multipurpose | February'32 | Dam package (₹14,446 Cr) awarded April'26; Nalla diversion achieved |
- Solar progress: 300 MW in Bikaner commissioned under CPSU Scheme Tranche-II. Near-term additions include 100 MW in Andhra Pradesh (June'26), 200 MW Khavda Stage-I (June'26), 600 MW in Gujarat (December'26), 200 MW Khavda Stage-III (December'26), 40 MW in Ganjam, Odisha (October'26), and 50 MW Floating Solar in Kerala (March'27).
- PSP exploration: 18 GW of PSPs are at the DPR/PFR stage across seven states. Beyond Indira Sagar-Omkareshwar, no other PSP has a firm construction start timeline.
- REIA tendering pause: Management acknowledged no recent tendering activity. Of ~23 GW already awarded, ~13 GW is likely to see PPA/PSA signing, with ~7 GW already signed. More clarity is expected in the coming months.
Guidance & Commitments
| Commitment | Specifics | Timeline |
|---|---|---|
| Parbati-II final tariff order | Final CERC order; differential revenue plus interest recognized in the quarter of receipt | By June 30, 2026 (end of Q1 FY'27) |
| Subansiri Lower interim tariff | Interim tariff order from CERC to set billing rate above current 80% AFC booking | No date; petition filed |
| Subansiri Lower final tariff | Final CERC order expected within six months of interim tariff | ~6 months after interim order |
| Teesta-V generation restart | Station to resume operations and show top-line activity | End of June 2026 |
| TLDP-III and TLDP-IV silt resolution | PAF to normalize after silt removal efforts conclude | Within three months |
| Five hydro projects to construction stage | Uri-I Stage-II, Dulhasti Stage-II (awarded); Etalin, Sawalkot, Kamala (likely this year) | FY'27 |
| Indira Sagar-Omkareshwar PSP construction start | 640 MW PSP to begin construction activities | FY'27 |
| Subansiri Lower full commissioning | All eight units operational | By March 2027 |
| Pakal Dul and Kiru commissioning | Both projects to be commissioned | Q4 FY'27 |
Key Metrics
| Metric | Q4 FY26 |
|---|---|
| Revenue from operations | ₹2,816 cr, +20% YoY |
| Profit after tax (reported) | ₹1,460 cr, +71% YoY |
| Adjusted PAT | ~₹560 cr (per an analyst's math), after removing ~₹900 cr one-off DTL reversal |
| Other income | ₹305 cr, +45% YoY |
| Finance costs | ₹574 cr, vs -₹12 cr in Q4 FY25 |
| Depreciation, amortization and impairment | ₹642 cr, vs ₹315 cr in Q4 FY25 |
| Tax expense | -₹1,823 cr, vs ₹247 cr in Q4 FY25, due to deferred tax adjustment and MAT credit recognition |
| Generation | 377 crore units, +20% YoY |
| Plant availability factor (PAF) | 62.47%, vs 66.84% in Q4 FY25 |
| Incentives earned | ₹366 cr, vs ₹350 cr in Q4 FY25 |
| CAPEX (FY26) | ₹13,689 cr, vs ₹11,596 cr in FY25 |
| Trade receivables | ₹2,630 cr as of Mar 31, 2026, vs ₹2,573 cr as of Mar 31, 2025 |
| Net amount due (billed) | ₹704 cr as of Mar 31, 2026, with dues >45 days at ₹242 cr |
| Parbati-II profit | ₹104 cr in Q4, vs a full-year loss of ₹150 cr |
| Subansiri Lower profit | ₹487 cr in Q4, vs a full-year profit of ₹495 cr |