NLC India Ltd Q2 FY2023 Concall Summary

Source transcript PDF: https://www.stockscans.in/document/cwbowp29x17b90og76r3myte.pdf

Key Takeaways


Operational Performance & Constraints

Rakesh Kumar: “The surcharge, which was although adding to the income, but it was not very happy moment for us, and it was adding risk to our business we are able to mitigate that risk and we are able to consolidate our position on real business through other sources...”

Power Project Pipeline & Tie-Ups

Rakesh Kumar: "We are working on that target only that we want to finalize the award by this year, by the current financial year itself."

Coal & Lignite: Supply, Demand & New Blocks

Rakesh Kumar: “In the short and medium term coal future is bright and we want to avail this opportunity to its maximum.”

Coal & Lignite Gasification Strategy

Rakesh Kumar: "Government of India has set a target of hundred million ton of gasification by 2030, we see a huge opportunity. Therefore lignite gasification throws a very big opportunity to NLC."

Financial Health: Receivables, Under-Recovery & Dividends

Rakesh Kumar: “The legal battle is long, but the power industry is definitely one sector where these disputes are inevitable. ... we are hopeful that in the time to come, the power sector will also witness clean slate. ... however, that will take some more time.”

Guidance & Commitments

CommitmentSpecificsTimeline
Neyveli 1,320 MW tender awardFinalize award for the 1,320 MW thermal projectBy end of current financial year (FY23)
Ghatampur commissioning1,980 MW project to start giving revenue and profitWithin the next one year
Talabira power tie-upBalance 400 MW with GRIDCO willing to purchase; management sees little doubt on proceedingUndated, but PPA pipeline in advanced discussion
Coal gasification first EPC packageFirst EPC tender already floated on 22 October 2022; second package being expeditedTender in market; award timeline not specified
CapEx target FY24₹8,244 croreFY24 [9-10]
CapEx beyond FY24“Likely to increase thereafter”FY25 and beyond, no specific figure [9-10]
South Pachwara railway sidingSPV formed; feasibility report submitted to Eastern Railway; bankability meeting next weekProject will “take a bit time”
Indigenous lignite gasification with BHELPilot project initially, then expansion with indigenous technologyPilot timeline not specified; expansion “later on, once it is proven”

Key Metrics

MetricQ2 FY23
Standalone revenue from operations (H1)₹5,847.21 cr, +20.47% YoY
Consolidated revenue from operations (H1)₹7,352.19 cr, +19.93% YoY
Standalone profit for the period (H1)₹873.29 cr, +53.9% YoY
Consolidated PAT (H1)₹985.86 cr, +77.76% YoY
Consolidated PBT before exceptional items and tax (H1)₹1,469.93 cr, +5.31% YoY
Mining segment profit (H1)₹819.36 cr, vs ₹377.24 cr in H1 FY22
Mining segment revenue (Q2)₹1,838.26 cr, vs ₹2,155.47 cr in Q1 FY23 and ₹1,624 cr in Q2 FY22
Coal EBIT (H1)₹252.18 cr
Thermal under-recovery (H1)₹189.72 cr, improved from ₹243.30 cr in H1 FY22
NNTPS under-recovery (H1)₹1.65 cr, vs ₹76.74 cr in H1 FY22
Coal production (H1)49.75 LT, vs 18.76 LT in H1 FY22
Lignite production (H1)124.42 LT, +6.87% YoY
Average lignite transfer price₹1,950 per ton, unchanged from Q1; to remain until CERC approves 2019-24 tariff petition
Coal e-auction price (October)₹2,690 to ₹2,740 per ton, for a recent auction of 2.5 lakh tonnes
Barsingsar lignite e-auction price (October)₹4,830 to ₹4,930 per ton
Standalone power generation (H1)13,104.90 MU, +0.47% YoY
Consolidated power export (H1)14,312.99 MU, +3.07% YoY
NLC average PLF (up to September)74.66%, vs all-India average of 64.49%
NNTPP PAF (H1)92.27%
TPS1 expansion PAF (H1)86.29%
TPS1 expansion PLF (H1)68.46%
Total regulated equity (as on 30 Sep 2022)₹6,593.19 cr, mine: ₹2,830.78 cr, thermal: ₹3,762.41 cr; excludes NTPL
NTPL regulated equity₹1,490 cr, total equity ₹2,200 cr
Renewable energy investment (completed)₹6,594 cr total investment, equity deployment ₹1,675 cr for 1,421 MW
FY23 CapEx target₹2,920 cr, breakup: mining ₹190 cr, power ₹860 cr, Pachwara JV ₹110 cr, NTPL FGD ₹250 cr, NUPPL Ghatampur ₹1,510 cr
FY24 CapEx target₹8,244 cr, as per corporate plan, likely to increase thereafter
Revaluation of trade receivables (H1)₹88 cr charge provided, out of ₹425 cr total revaluation
Tamil Nadu dues under installment scheme~₹735 cr, amount keeps changing
Talabira coal production target (FY23)1.3 crore tonnes, H1 achieved ~0.5 crore tonnes
Coal gasification project cost (lignite to methanol)₹4,394 cr, board approved