Key Takeaways
- Revenue and profit up double digits, but under-recovery overshadows: H1 FY27 Group revenue grew 18% YoY to ₹9,449 crores and PAT grew 13% to ₹1,764 crores, yet management confirmed FY27 group under-recovery will exceed last year’s ~₹800 crores because NUPL’s burden has been added.
- Coal price windfall is real but called “irrational”: E-auction coal prices swung from ₹850–900 to ₹2,800 per tonne, driven by eastern India production shortfalls after an extended monsoon; management expects elevated prices to persist for some period before tapering.
- The under-recovery story hinges on one mine and one railway line: Pachwara coal evacuation is expected to start by February–March, and once that coal reaches Ghatampur and NUPL, plus Talavira coal is routed to NUPL, under-recovery is promised to “substantially come down” from FY28.
- A ₹1.6 lakh crore CapEx plan was approved, anchored by green energy: The board cleared Corporate Plan 2032, targeting 14.9 GW thermal, 16.2 GW renewable, and 122 MTPA mining capacity, with ₹78,000 crores earmarked for green energy alone.
- What to watch next quarter: Whether Pachwara railway evacuation actually begins by March, whether Ghatampur’s third unit starts running, and whether the e-auction coal price retreats or stays elevated.
Under-Recovery: The Quarter’s Defining Drag
- Ghatampur is the largest hole: Under-recovery reached ~₹490 crores up to September because coal was unavailable for the first 6–7 months; only 2 of 3 units ran despite COD being declared for all three, dragging overall plant availability down.
- NUPL added a fresh layer: One unit was shut for the entire 7 months with no coal, and only 2 units operated; this is the main reason FY27 group under-recovery will exceed FY26’s ~₹800 crores.
- TS2 expansion still a worry: Under-recovery was drastically reduced from ₹500–600 crores last year, but the second unit’s modification has not yet been completed; material is being collected from BHEL and the modification is targeted to start in February–March, taking 4 months once begun.
- NTPL held at zero: Under-recovery was brought to almost zero last year and has been maintained at zero as of now.
- NNTPS improving but not clean: Q2 plant availability factor was close to 60% vs72% last year; both units are now running and management expects availability close to80% going forward, with some under-recovery from H1 adjustable in H2.
- The fix is logistics, not geology: Pachwara mines have not started full-fledged operations because the railway evacuation facility is not ready; coal evacuation is expected to begin by February–March, with production and evacuation improving next year onward to reach0.9 crore tonnes in2–3 years.
- Ghatampur coal supply timeline: From Q4 FY27, supply will improve; management is trying to bring1 rack per day from Pachwara in February–March and1–2 racks from Talavira via RCR mode.
- Full-fledged Ghatampur operation is at least2–3 quarters away; from next year onward under-recovery there is expected to be nominal.
Prasanna Kumar Acharya: “Definitely this year under recovery will be more than the last year. ... But next year, on next year onwards, financial year onwards, it will substantially come down.”
The E-Auction Coal Price Swing
- Prices tripled in six months: E-auction coal moved from ₹850–900 per tonne in Q1 to ₹1,500–1,600, then to ₹2,800 recently, driven by lower coal production in eastern India after an extended monsoon.
- Management calls the behavior “irrational”: The CMD described the fluctuation as “a little bit irrational kind of thing” and expects the elevated price to remain for some period then taper down to normal.
- Volume strategy is roughly half-and-half: Close to50% of total coal is to be sold through e-auctions, with the balance50% going to NTPL and via MOU route to PSEs.
- An analyst’s question on the exact split went only partly answered: Management stated0.5 crore tonnes were done through e-auction but did not confirm the2.1 crore tonne base figure the analyst cited or provide the remaining split.
Prasanna Kumar Acharya: “So its behavior is a little bit irrational kind of thing, I can say, that fluctuating in the last6 months.”
Corporate Plan2032: The ₹1.6 Lakh Crore Bet
- Board approved the plan this quarter: Corporate Plan2032 covers thermal, mining, renewables, and diversification projects, with a total CapEx outlay of ₹1.6 lakh crores.
- Capacity targets are steep: Mining from50 MTPA to122 MTPA, thermal from6.6 GW to14.9 GW, and renewable from1.8 GW to16.2 GW, all within6 years.
- Green energy gets the largest allocation: ₹78,000 crores for green energy, ₹66,000 crores for thermal, ₹11,000 crores for mining, and ₹6,500 crores for diversification.
- Regulated equity by2032 is expected to be ₹33,500 crores, or65% of total equity of ₹51,270 crores.
- Thermal expansion is framed as a peak-power response: The CMD pointed to September peak power demand exceeding summer peaks as forcing all conventional generators to rethink thermal capacity.
Prasanna Kumar Acharya: “Thermal- we are trying to expand our thermal base to meet this country’s peak power demand. Particularly, you have seen that in September also, the peak power demand was more than the summer peaks of this year.”
Thermal Project Pipeline: Where the New Megawatts Will Come From
- Ghatampur Phase4 (Unit4): 660 MW additional unit planned on land already available; in discussions with UP state for PPA signing; power expected to be cheapest among Ghatampur units because brownfield.
- Talabira expansion: Contract awarded to BHEL for3×800 MW with one more unit planned; environment clearance process ongoing; tender expected to be floated this financial year; brownfield so work can start immediately after tender finalization.
- Neyveli TS2 second expansion: 2×500 MW; tender already opened, technical evaluation ongoing; award expected by December end.
- Bijnag (Rajasthan): 2×125 MW; evaluation ongoing; tender expected this financial year; mine already exists.
- NALCO JV project: 4×270 MW (~1,000–1,100 MW); land available with NALCO; coal to be supplied from Machikatta coal mines ~10 km away.
- Madya Pradesh peated plant: 4×800 MW planned; discussions with distribution companies ongoing; Ministry of Power reviewing development modality.
- Timelines: Larger thermal projects take5–6 years; smaller capacity projects like NALCO and Bijnag take ~4 years.
Renewables: The2 GW-Per-Year Ambition
- H1 performance was strong: Group renewable generation grew31.89% YoY to148.6 crore units.
- FY27 additions target ~950 MW: 600 MW Kawada (500 MW almost ready,100 MW expected by end-January, but commissioning declaration delayed by transmission line non-availability) plus350 MW wind plus maybe100 MWh battery storage, all expected COD by FY27 end.
- FY28 target is2 GW: Management stated a plan to add2 GW capacity next year but gave no specific project breakdown.
- Subsidiary NIRL secured a large pipeline: 3.64 GW of RE projects and3,580 MWh BESS projects won pan-India.
- Wind projects in motion: 50 MW being developed by Inox in Gujarat;200 MW being developed by Kosal in Gujarat, with100 MW expected this FY.
Operational Frictions: Land, Logistics, and an Incomplete Answer
- Neyveli mines are normal but land is tight: Production is normal and meeting thermal plant requirements, but a ~5-year gap in land acquisition (2013–2018) caused by Tamil Nadu’s delay in aligning its Land Acquisition Act with the central Act reduced advanced land availability from4–5 years to only2–2.5 years.
- A temple inside the mine area is close to being settled for shifting outside, one of2–3 small measures management is pursuing to maximize production for the next2–3 years.
- Ghatampur financials were requested but not clearly delivered: An analyst asked for H1 revenue, EBITDA, and PAT; management gave contradictory figures (“EBITDA is500” then “833 crores,533 crores revenue”) and never provided PAT.
Prasanna Kumar Acharya: “Not only in Aveli, wherever you go for the land acquisitions, issues wil be there, chalenges wil be there. So with that, we have to live with that situation.”
Guidance & Commitments
| Commitment | Specifics | Timelne |
|---|---|---|
| Pachwara coal evacuation start | Railway evacuation facility ready; coal evacuation begins | February–March (end of FY27) |
| TS2 expansion second unit modification start | Material being collected from BHEL; activity takes4 months once started | Start February–March FY27 |
| TS2 expansion tender award | Technical evaluation ongoing | By December end (next1 month) |
| Talabira expansion tender float | Environment clearance process ongoing; tender document being prepared | This financial year |
| Bijnag tender float | Evaluation ongoing | This financial year |
| Ghatampur full-fledged operation | All3 units running on adequate coal supply | At least2–3 quarters away |
| Group under-recovery reduction | Pachwara coal supply starts, Talavira coal used for NUPL, TS2 modification completes | From FY28 onward, “substantially come down” |
| NNTPS plant availability | Both units now running | Close to80% going forward |
| Renewable capacity addition rate | Targeting2 GW every year | FY28 onward |
| FY27 renewable COD | 600 MW Kawada +350 MW wind + maybe100 MWh BESS | By end FY27 |
| Dividend maintenance | Per existing dividend policy | Ongoing |
Key Metrics
| Metric | Q2/H1 FY27 |
|---|---|
| Group revenue from operations (H1) | ₹9,449 cr, all-time highest ever, +18.05% YoY vs ₹8,004 cr |
| Group PAT (H1) | ₹1,764 cr, +12.81% YoY vs ₹1,564 cr (Note: PAT is ₹1,764 cr; EBITDA is ~₹3,300 cr with PAT around ₹1,800 cr per slide) |
| Group EBITDA (H1) | ~₹3,300 cr, EBITDA margin 35% |
| Group EPS (H1) | ₹13.45, +27% YoY |
| Standalone revenue from operations (H1) | ₹5,563 cr, +9.92% YoY vs ₹5,061 cr |
| Standalone total comprehensive income growth (H1) | +92.75% YoY |
| Group net worth | ₹23,401 cr as on 30 Sep 2026, +17.21% YoY vs ₹19,996 cr |
| Standalone net worth | ₹20,859 cr as on 30 Sep 2026 vs ₹18,099 cr YoY |
| Interim dividend declared | 15% |
| Market capitalization | ₹36,300 cr as on 30 Sep 2026 |
| Standalone coal production (H1) | 78.55 lakh tonne, +4.92% YoY vs 74.87 lakh tonne |
| Standalone coal sales (H1) | 1.01 crore tonne, +14.55% YoY vs 88.37 lakh tonne |
| Group gross thermal power generation (H1) | 1,462.2 crore units, +19.37% YoY vs 1,224.9 crore units |
| Group renewable power generation (H1) | 148.6 crore units, +31.89% YoY vs 112.7 crore units |
| CUF | 18.97% |
| NIRL H1 revenue | ₹462 cr |
| NIRL H1 PAT | ₹150 cr, PBT ₹201 cr |
| Ghatampur H1 under-recovery | ~₹490 cr up to September |
| NNTPS PAF (Q2) | ~60%, vs 72% last year |
| Last e-auction coal price | ~₹2,800 per tonne, vs ~₹1,500–1,600 in previous period and ~₹850–900 in Q1 |
| E-auction coal sales done (H1) | 0.5 crore tonne, targeting ~50% of total sales via e-auction |
| Total workforce | 9,201 as on 30 Oct 2026, including 722 female employees |
| ESG rating | 61.2 by CareEdge, 60 by ICRA |
| FY27 renewable capacity addition target | 950 MW expected commercial operation by year-end (600 MW Kawada + 350 MW wind/inertia) |
| Total CapEx plan up to 2032 | ₹1.6 lakh cr (thermal ₹66,000 cr, green energy ₹78,000 cr, mining ₹11,000 cr, diversification ₹6,500 cr) |
| FY26 total under-recovery | ~₹800 cr (per an analyst's math) |