NLC India Ltd Guidance Report - SOIC x StockScans Report
as of Nov 2026
- NIRL secured 2 GW RE projects + 3,300 MWh BESS
Delivered - At the Q4 FY26 presentation, NIRL was reported to have secured 2 GW RE projects plus 3,300 MWh BESS across PSPCL, NHPC, GUVNL, SECI, NCRTC, TNGECL and NTPC. By the Q2 FY27 presentation, secured projects had increased to 3.4 GW RE plus 3,580 MWh BESS.
- CCEA approval for ₹7,000 Cr equity investment in NIRL
Delivered - At the Q4 FY26 presentation, NLCIL reported securing CCEA approval for investment of up to ₹7,000 Cr equity in NIRL. The FY25 annual report confirms CCEA approved a special exemption enabling NLCIL to invest ₹7,000 crore in NIRL.
- Critical minerals - Semhardih & Raipura phosphorite blocks
Delivered - At the Q4 FY26 presentation, the company declared itself successful bidder for the Semhardih and Raipura phosphorite and limestone blocks in Chhattisgarh. By the Q2 FY27 presentation, two partially explored blocks had been won each in Chhattisgarh and Telangana, with pre-exploration in the Chhattisgarh blocks completed.
- Mine-I washed silica sand plant 1.0 MTPA - commissioned February 2026
Delivered - At the Q4 FY26 presentation, the Mine-I washed silica sand plant (1.0 MTPA) was reported commissioned in February 2026 with commercial sale commenced. The Q2 FY27 presentation confirms two OB-to-M-Sand plants established at Mine-I (1 MTPA) and Mine-IA (0.4 MTPA), with sale commenced.
- Barsingsar 300 MW Solar - FY26 milestone
Delivered - At the Q4 FY26 presentation, Barsingsar 300 MW Solar was listed as an FY26 milestone. The Q2 FY27 presentation again lists Barsingsar 300 MW Solar as an FY26-to-date milestone, with no specific COD date disclosed.
- BESS 250 MW/500 MWh TNGECL - March 2027
On track - At the Q4 FY26 presentation, the 250 MW/500 MWh BESS with TNGECL was shown with a March 2027 date and NIT floated. The FY25 annual report records NIRL receiving the LoA from TNGECL for the 250 MW/500 MWh BESS project; no commissioning is disclosed and the horizon is not reached.
- 600 MW Kawada - commissioning declaration
Pending - At the Q2 FY27 call, management said the 600 MW Kawada project was completed but commissioning was not declarable due to transmission line non-availability, with 500 MW almost ready and 100 MW expected ready by end of January. The same call records the transmission constraint; the January 2027 horizon for the 100 MW is not reached.
- NALCO JV 4x270 MW thermal project
On track - At the Q2 FY27 call, management said the NALCO JV 4x270 MW (\~1,000-1,100 MW) thermal project would be taken up, with land already with NALCO and coal from Machikatta mines. A JV company has been formed with NALCO to develop a 1,080 MW coal-based plant, and the Q2 FY27 presentation lists COD of December 2031.
- Neyveli TS2 second expansion (2x500 MW) - contract awarded by December end
Pending - At the Q2 FY27 call, management said the Neyveli TS2 second expansion (2x500 MW) contract was expected to be awarded by December end, "in next 1 month's time". As of 21 Nov 2026 no award is disclosed; the tender has been opened and technical evaluation is ongoing.
- Capex plan ₹1.6 lakh crore to 2032
On track - At the Q2 FY27 call, management set out a capex plan of ₹1.6 lakh crore up to 2032, echoed in the Q2 FY27 presentation. The horizon is not reached; FY26 capex was ₹9,131 Cr, and H1 FY27 capex is not disclosed in our record.
- Energy storage portfolio 8,238 MWh by 2032
On track - At the Q2 FY27 call, management guided an energy storage portfolio of 8,238 MWh by 2032, with the Q2 FY27 presentation showing 3,580 MWh contracted/awarded plus 4,658 MWh pipeline. Current contracted storage is 3,580 MWh (TN 500, WB 200, Haryana 530, GUVNL 550, SECI 1,800 MWh); the 2032 horizon is not reached.
- NLCIL @2030 equity outlook - ₹30,155 Cr overall equity
On track - At the Q4 FY26 presentation, the NLCIL @2030 outlook showed ₹30,155 Cr overall equity - ₹19,668 Cr regulated (65%) plus ₹10,487 Cr non-regulated (35%). The Q2 FY27 presentation revised this to ₹51,270 Cr by 2032 (₹33,499 Cr regulated + ₹17,771 Cr non-regulated); current net worth is ₹23,401 Cr and the horizon is not reached.
- Dividend policy - existing policy followed going forward
Delivered - At the Q2 FY27 call, management said the existing dividend policy would be followed going forward. An interim dividend of 15.0% has been declared for FY27, and the dividend trend shows consistent payouts.
- Coal sales mix - \~50% e-auctions
Delivered - At the Q2 FY27 call, management guided that \~50% of total coal sales would go through e-auctions, with the balance 50% to NTPL plus the MOU route. About 0.5 crore tonnes of coal has been sold through e-auction out of \~1.01 crore tonnes potential, with the balance via MOU route plus NTPL - a \~50% e-auction mix.
- FY28 and beyond - 2 GW renewable capacity every year
Pending - At the Q2 FY27 call, management said the company is planning to add 2 GW of renewable capacity every year from FY28 onwards. The horizon is not reached; NIRL has secured 3.4 GW of RE projects plus 3,580 MWh of BESS to date.
- FY27 renewable additions - \~950 MW by end FY27
On track - At the Q2 FY27 call, management said FY27 renewable additions of \~950 MW were expected to declare commercial operation by end of the financial year. H1 FY27 additions were 710 MW (660 MW thermal + 50 MW renewables), and the 600 MW Kawada is completed but not declarable due to transmission line non-availability; the FY27 horizon is not reached.
- NUPL underrecovery - eliminated by FY28
Pending - At the Q2 FY27 call, management said NUPL underrecovery would not be there in the next financial year once Pachwara coal supply starts and Talabira coal is diverted. One NUPL unit has been shut for 7 months for want of coal with only 2 of 3 units running, and Pachwara coal evacuation is expected February-March 2027; the horizon is not reached.
- NTPL underrecovery - targeting zero in FY27
On track - At the Q2 FY27 call, management said NTPL underrecovery was being targeted at zero level this year - already at zero as of now - after being brought down to almost zero last year, and would be maintained. The underrecovery is at zero now, having been brought down to almost zero last year; no full-year FY27 outcome is yet available.
- Solar and Thermal power assets - 5,000 MW pan-India
Delivered - In a September 2020 announcement, the company said it would develop Solar and Thermal power assets to the tune of 5,000 MW on a pan-India basis. Current capacity stands at 8.4 GW - thermal 6.6 GW plus RE 1.8 GW - exceeding the 5,000 MW target.
- NUPPL Unit-2 and Unit-3 - COD during FY 2025-26
Delivered - In a September 2025 announcement, NUPPL Unit-2 (660 MW) was stated to be on track to achieve commercial operation along with Unit-3 during FY 2025-26. Unit-2 achieved COD on 9 December 2025 and Unit-3 on 13 June 2026, both within FY 2025-26.
- TPS-I units retirement - 2x50 MW by end September 2020
Delivered - At the Q1 FY21 result, management guided that the remaining two TPS-I units (2x50 MW) would be retired by end of September 2020. Four TPS-I units (1x100 MW, 3x50 MW) had been retired up to July 2020, and a sale order has since been issued for dismantling the 600 MW decommissioned TPS-I.
- NNTPS Unit-II 500 MW - capitalization in FY21
Delivered - At the Q1 FY21 result, NNTPS Unit-II (500 MW) was scheduled for capitalization in FY21. The unit was under commissioning but delayed due to COVID-19 at Q1 FY21, and the milestones list shows NNTPS Unit II (500 MW) CoD in 2021.
- Talabira coal production - 6.0 MTPA raised to 8.0 MTPA in FY22
Partial - In the FY22 annual report, the company set out steps to achieve 6.0 MTPA against the original 4.0 MTPA target, and further to 8.0 MTPA, during FY22. FY22 coal production touched 0.64 crore tonnes (6.4 MTPA), a 527% increase over the prior year - above the original 4.0 MTPA but short of the raised 8.0 MTPA target.
- Exit FY2030 as balanced 20,130 MW integrated energy platform
On track - At the Q4 FY26 presentation, the company guided to exit FY2030 as a balanced 20,130 MW integrated energy platform - 10,020 MW thermal plus 10,110 MW RE. Current capacity is 8.4 GW (6.6 GW thermal + 1.8 GW RE); the 2030 horizon is not reached.
- Green Hydrogen 4 MW project - 18-month timeline
On track - At the Q4 FY26 presentation, the Green Hydrogen 4 MW project at Neyveli was set on an 18-month timeline at 300 kg H₂/day, reiterated as underway at Q2 FY27. The LoA has been issued, contract signed, OEC appointed, and kick-off and geotechnical investigations completed; no commissioning is disclosed.
- NIRL IPO - planned FY2027
Pending - At the Q4 FY26 presentation, the NIRL IPO was planned in FY2027 to support the renewable build-out toward 10 GW. No IPO filing or completion is disclosed in our record as of 21 Nov 2026; CCEA has approved investment of up to ₹7,000 Cr equity in NIRL.
- Group financial guidance FY2030 - Revenue ₹37,713 Cr, PAT ₹5,294 Cr
On track - At the Q4 FY26 presentation, group financial guidance for FY2030 was Revenue ₹37,713 Cr, PAT ₹5,294 Cr, Assets ₹159,747 Cr and EBITDA margin 50.6%. The Q2 FY27 presentation extended projections to FY2032 - Revenue ₹47,507 Cr, PAT ₹9,669 Cr, EBITDA margin 60.7%; FY26 actuals were Revenue ₹17,490 Cr and PAT ₹3,769 Cr, with H1 FY27 at ₹9,449 Cr and ₹1,764 Cr.
- Thermal capacity 10,020 MW by 2030
On track - At the Q4 FY25 presentation, thermal total was guided at 10,020 MW by 2030, echoed as 10 GW by 2030 in the FY25 annual report. The Q4 FY26 presentation showed thermal 5,960→10,020 MW by 2030, later revised to 6.6→14.9 GW by 2032; installed thermal is 6.6 GW as of Q2 FY27, with Ghatampur 1,980 MW fully commissioned by June 2026.
- Mining capacity 104.35 MTPA by 2030
On track - At the Q4 FY25 presentation, mining total was guided at 104.35 MTPA by 2030, echoed in the FY25 annual report. The Q4 FY26 presentation showed mining 50→104 MTPA by 2030, later revised to 50→122 MTPA by 2032; current capacity is 50.1 MTPA, with Pachwara South 9 MTPA commenced in March 2026.
- No new thermal capacity beyond 2030
On track - In an August 2024 announcement, NLCIL foresaw no new thermal power capacity addition beyond 2030, a vision repeated in the FY24 annual report and the Q4 FY26 presentation. The thermal pipeline carries CODs through FY 2031-32 - Odisha Phase I (U3 Mar 2030), Phase II (Sep 2030), Machhakata TPS (U3 Mar 2032), Ghatampur TPS 660 MW (Mar 2032), NALCO 1,080 MW (Dec 2031) - all pre-2030 commitments in development.
- RE to form 50% of generation mix by 2030
On track - In an August 2024 announcement, NLCIL targeted an RE portfolio mix of 50% of total planned capacity by 2030, reiterated at the Q4 FY26 presentation and refined to \~50% of own generation mix at Q2 FY27. The current split is 79% thermal (6.6 GW) and 21% renewables (1.8 GW); the 2030 horizon is not reached.
- Renewable capacity 10,110 MW by 2030
On track - At the Q4 FY25 presentation, the FY 2030 outlook targeted RE total of 10,110 MW, matching the August 2024 announcement of 10.11 GW by 2030 and the FY25 annual report. The Q4 FY26 presentation staged additions of 4,216 MW by FY27, 5,910 MW by FY28, 7,910 MW by FY29 and 10,110 MW by FY30, later raised to a 16 GW NIRL build-out by 2032; operating renewable capacity is 1.8 GW, with 5,420 MW contracted/awarded and 9,000 MW pipeline.
- New Patrapara (South) coal mine 12 MTPA - COD November 2029
On track - At the Q4 FY25 presentation, the New Pathrapara (South) coal mine was set at 12 MT, ₹4,000 Cr, with COD November 2029. The Q4 FY26 presentation revised this to FY 2031-32, maintained at Q2 FY27; the horizon is not reached and significant progress has been made at New Patrapara South.
- North Dhadu coal mine 3 MTPA - COD September 2028
On track - At the Q4 FY25 presentation, the North Dhadu coal mine was set at 3 MT, ₹1,396 Cr, with COD September 2028. The Q4 FY26 presentation revised this to FY 2028-29 (₹1,354 Cr) and Q2 FY27 to FY 2029-30; the horizon is not reached and significant progress has been made at North Dhadu Western Part.
- Machhakata coal mine 30 MTPA - COD April 2029
On track - At the Q4 FY25 presentation, the Machhakata coal mine was set at 30 MT, ₹6,123 Cr, with COD April 2029. The Q4 FY26 presentation revised opening to FY 2031-32 and Q2 FY27 to FY 2030-31; the horizon is not reached and significant progress has been made at Machhakata.
- Odisha Pithead TPS Phase I 2,400 MW - CODs Mar 2029 to Mar 2030
On track - At the Q4 FY25 presentation, Odisha Pit Head TPS Phase I (2,400 MW, 3×800, ₹27,213 Cr) had LoA issued with CODs of U-1 Mar 29, U-2 Sep 29 and U-3 Mar 30. The Q4 FY26 presentation shifted these to Feb 30, Aug 30 and Feb 31, before Q2 FY27 restored U1 Mar 2029, U2 Sep 2029 and U3 Mar 2030; LoA is issued with no construction completion disclosed.
- Solar 810 MW Rajasthan - Mar 2027
On track - At the Q4 FY25 presentation, the 810 MW Rajasthan solar project (₹4,788 Cr) was dated March 2027. The Q4 FY26 presentation revised this to March 2028; the horizon is not reached and no commissioning is disclosed in our record.
- Solar 600 MW Gujarat - Sep 2026 revised COD
Partial - At the Q4 FY25 presentation, the 600 MW Gujarat solar project (₹3,336 Cr) carried a December 2025 expected COD; the Q4 FY26 presentation revised this to September 2026. That deadline has lapsed with no commissioning disclosure in our record, and the Q2 FY27 presentation still lists 3,221 MW of solar under construction.
- Solar 50 MW Neyveli mined-out land - Sep 2025
Partial - At the Q4 FY25 presentation, the 50 MW solar project on Neyveli mined-out land (₹218 Cr) was dated September 2025. The Q4 FY26 presentation revised this to June 2026, and the Q2 FY27 presentation lists "Neyveli 50 MW Solar in mined-out area" as an FY26-to-date milestone, with no specific COD date disclosed.
- 150 MW Wind-Solar Hybrid - 100 MW Solar and 50 MW Wind by Jan 2026
Pending - At the Q4 FY25 presentation, the 150 MW Wind-Solar Hybrid (₹865 Cr) was dated 100 MW Solar January 2026 and 50 MW Wind January 2026. The Q4 FY26 presentation revised this to 50 MW Wind June 2026 and 100 MW Solar December 2026; no commissioning is disclosed, with the Q2 FY27 presentation listing Hybrid 600 MW under construction.
- Solar 500 MW IREDA - 300 MW by Sep 2025, 200 MW by Jan 2026
Partial - At the Q4 FY25 presentation, the 500 MW IREDA solar project (₹3,031 Cr) was dated 300 MW September 2025 and 200 MW January 2026. 52.83 MW of the 300 MW solar project was commissioned on 20.08.2025 in Rajasthan; no disclosure of the full 300 MW or the 200 MW tranche appears in our record.
- South Pachwara coal block - 9 MTPA, mine commencement July 2025
Partial - At the Q4 FY25 presentation, the South Pachwara coal block (9.00 MT, estimated cost ₹2,243 Cr) was expected to commence mining in July 2025. At the Q2 FY27 call, coal evacuation was expected to start by February-March with production reaching 0.9 crore tonnes in \~2.5-3 years; coal production in fact commenced in March 2026, about 8 months after target.
- Lignite-to-methanol gasification - 1,200 TPD project
Missed - At the Q2 FY23 call, management detailed the lignite-to-methanol gasification project with board-approved cost of ₹4,394 crore and the first EPC package tender floated on 22 October 2022; the FY21 annual report had set the target at 1,200 metric tonnes of methanol per day. The Q4 FY26 presentation shows the revised DFR for 1,200 TPD under review following significant cost increase and adverse IRR projections, with an EoI under approval for a 100 TPD Lignite-to-Ammonium Nitrate alternative; no construction or commissioning is disclosed.
- Ghatampur 1,980 MW - commissioned within one year
Partial - At the Q2 FY23 call, management stated the 1,980 MW Ghatampur project "is going to be commissioned in the next one year of time". The Q4 FY25 presentation showed Unit I COD 12.12.2024 (actual) with Unit II July 25 and Unit III Oct 25, later revised to Unit III June 2026; Unit-1 achieved COD on 12 December 2024, Unit-2 on 9 December 2025 and Unit-3 on 13 June 2026, completing the full 1,980 MW by June 2026.
- FY24 capex - ₹8,244 crore corporate plan
Missed - At the Q2 FY23 call, management guided FY24 capex of ₹8,244 crore "as per our corporate plan", likely to increase thereafter. FY24 actual capex was ₹4,270 crore, 148% of the target per the FY24 annual report - the ₹8,244 crore plan was not achieved.
- Talabira coal production - 1.3 crore tonnes in FY23
Partial - At the Q2 FY23 call, management set the Talabira coal production target at 1.3 crore tonnes for FY23, versus 0.64 crore tonnes in FY22. FY23 coal production at Talabira-II & III OCP reached 1 crore tonnes against a target of 80 lakh tonnes - short of the 1.3 crore tonne target but a record and above the original 80 lakh tonne target.
- FY25 thermal PLF - 69.45%
Partial - In the FY25 annual report, thermal PLF for April 2024-March 2025 was reported at 69.45% against a target of 73.43%. The FY25 thermal PLF of 69.45% is confirmed, below the 73.43% target.
- FY24 PAT - up 48%
Partial - In the FY24 annual report, the company stated FY 2023-24 PAT was up 48%. FY24 PAT was ₹1,867 Cr against ₹1,425 Cr in FY23, an increase of 31%; the 48% growth figure is not confirmed by the reported financials.
- FY23 lignite production - 2.35 crore tonnes
Partial - In the FY23 annual report, FY23 lignite production was reported at 2.35 crore tonnes against a target of 2.64 crore tonnes. The FY23 lignite production of 2.35 crore tonnes is confirmed, below the 2.64 crore tonne target.
- Neyveli 1320 MW lignite power plant tender - award by end FY23
Missed - At the Q2 FY23 call, management said they were working to finalize and award the Neyveli 1320 MW lignite power plant tender "by this year, by the current financial year itself". No FY23 disclosure confirming the award appears in our record; the Q4 FY25 PPT lists TPS II 2nd Expansion (1,000 MW, ₹10,575 Cr) with EPC tender to be floated, the Q4 FY26 PPT shows it under planning/NIT floated (₹11,653 Cr), and the Q2 FY27 PPT lists COD FY 2030-31.