Key Takeaways
- Strong operations, muted profit: Group generation rose ~15% YoY in H1, but PAT grew only 3.65% YoY, weighed down by a one-time finance charge on LPS receivables discounting (~₹392 crore), a merger-related tax charge (~₹190 crore), and a sharp drop in JV profits.
- JV profits collapsed: NTPC's share of JV profits fell from ₹526 crore to ₹121 crore YoY, driven by a ~5-month boiler shutdown at Meja Urja and stabilization losses at Hindustan Urvarak; management expects a ₹400–450 crore half-yearly profit recovery once both stabilize.
- Renewable monetization is imminent: NTPC plans to sell a 10–20% stake in its consolidated green entity (NGEL) by the close of Q3 FY23 or before year-end, a concrete near-term catalyst that will bring in investor capital for its 60 GW aspirational portfolio.
- Coal pipeline is expanding, cautiously: The government has indicated a requirement for 7,000+ MW of new coal capacity, and NTPC has already decided on 4.8 GW with more under evaluation, while blending of imported coal is expected to fall significantly as domestic supply improves.
- What to watch next quarter: The NGEL stake sale valuation and quantum, the pace of Meja and HURL profit recovery, and whether the projected year-end fixed cost under-recovery narrows to ~₹250 crore from the current ₹718 crore.
Profitability Drags
- JV profit decline: NTPC's share of JV profits fell to ₹120.57 crore in H1 FY23 from ₹526.45 crore YoY, with Meja Urja's ~5-month boiler shutdown and Hindustan Urvarak's initial stabilization losses as the primary drivers.
- HURL losses: The Gorakhpur plant, the first of three 12.6 LMT units commissioned in May 2022, achieved only 37% capacity through September due to stabilization problems and ammonia tank leakages, contributing to a ~₹715 crore loss.
- One-time charges: A one-time finance charge of ~₹392 crore on LPS receivables discounting and a merger-related tax charge of ~₹190 crore depressed PAT, while lower other income from better DISCOM payment trends also weighed.
- Fixed cost under-recovery: H1 under-recovery of ₹718 crore is transient and driven by extended overhaul durations on some units; management projects year-end under-recovery of only ~₹250 crore, concentrated in four stations with major equipment issues.
- Borrowing cost rising: Average cost of borrowing increased to 6.22% in H1 FY23 from 5.96% in H1 FY22, reflecting the rising interest rate environment.
Management: "For the Meja plant, we had an issue with the boiler. So, we had to shut down for around five months and repair it. So now the boiler is back in service. We will be able to recover substantial amount of this from the remaining days."
Renewable Monetization & NGEL
- NGEL stake sale: NTPC plans to offload 10% to 20% of its consolidated green entity, into which the entire renewable portfolio (including NTPC REL) is being transferred; the transaction is expected to conclude by the close of Q3 FY23 or before the end of the financial year, scheduled by December with possible slippage into January.
- Valuation details withheld: Management declined to disclose the portfolio size being considered for valuation (operational 2,800 MW plus 4,000 MW under development vs. the 60 GW aspirational target), stating that is for potential investors to decide and not appropriate to discuss publicly.
- Rationale for dilution: The 10–20% stake sale is intended to bring in investor capital for future project development, with the 60 GW aspirational portfolio by 2032 providing the growth story; future projects will be developed with investor money, not NTPC's alone.
- Government mandate: Management confirmed it has a mandate from the Government of India to pursue monetization.
- Khavda Solar Park: The entire 4.75 GW capacity has been allocated to NTPC REL for own development with no bidding; work has started on about 1,255 MW with balance-of-system packages awarded, and more capacity awards are expected this year with the balance next year.
Management: "We propose to offload anything between 10% to 20%, and we are in the process. But we expect that by the close of Q3 or in any case, before the end of the financial year, we'll be able to conclude this transaction."
Operational Performance
- Generation growth: NTPC Group generation increased ~15% YoY in H1 FY23 and standalone generation increased ~16% YoY, driven by higher coal supply and improved operations.
- PLF leadership: Coal station PLF of 77.27% in H1 FY23 maintained a spread of over 12% above the national average of 64.46%, with four stations ranking among the top 10 nationally.
- Coal supply improvement: Materialisation against ACQ rose to 99.93% from 96.04%, total coal supply increased to 112 MMT from 92.86 MMT, and imported coal rose sharply to 10 MMT from 0.88 MMT as the government mandated blending to meet demand.
- Own coal production: Highest-ever coal production of 0.88 crore MT in H1 FY23, growth over 58% YoY, with the Chatti Bariatu mine starting production from 29 September 2022.
- Grid and fuel constraints easing: Lost generation due to grid restrictions reduced to 4,000 crore Units from 5,200 crore, and fuel supply losses reduced to 200 crore Units from 319 crore.
- Coal blending declining: Blending was ~7.9% in the period but stood at only 3% as of the call date; with domestic coal availability improving in Q3, management expects blending to come down significantly in the remaining half year.
- Average tariff increase: The ₹0.91/unit YoY jump in average tariff (₹3.86 to ₹4.77) is entirely attributable to imported coal pass-through.
Capacity Pipeline
- H1 FY23 additions: 1,952 MW of commercial capacity added, including 672 MW of renewable capacity.
- FY23 target: Targeting around 5,000 MW of capacity addition in the current year.
- FY24 target: Targeting around 7,000 MW combined, including Telangana and North Karanpura coal units, one THDC Khurja unit, THDC Tehri pumped storage (1,000 MW), NREL Solar (2,295 MW), and NTPC directly solar (~1,000 MW).
- Three-year pipeline: Targeting around 18 GW over FY23, FY24, and FY25 taken together.
- New coal projects: 4.8 GW already decided; further projects under evaluation include Meja (2x660 MW) and Telangana (3x800 MW), contingent on coal availability, environmental clearance, and grid requirements.
- Coal project awards: Lara expansion (2x800 MW) NIT targeted by March 2023; Sipat within Q2 FY24; Singrauli and Sipat both in FY25; Darlipalli in FY24 if forest clearances are obtained, otherwise FY25.
- Talcher Thermal: EPC order for 2x660 MW awarded to BHEL last month for ~₹8,200 crore including GST; first unit commissioning in August 2026, second unit within six months, full project completion in FY27.
- Jhabua Power acquisition: Acquired 50% stake in JPL (600 MW operational capacity in MP) through the NCLT route, NTPC's first acquisition of a power asset via the insolvency process; most of the power is tied up.
Management: "We are a bit cautious, but we are steadily moving."
Receivables & LPS Scheme
- LPS scheme impact: ₹6,108 crore of receivables were placed into the scheme with maturities of 36–48 months; the present value differential of ₹333 crore was accounted as a one-time charge, which will progressively unwind as money is received over time.
- No further receivables: The scheme was open for a limited period, and no further receivables are anticipated to go under it.
- Receivable days improving: With the LPS scheme implemented and no overdue discounts allowed, management expects receivable days to be less than 45 days going forward.
- LPS other income declining: Q2 LPS was ₹229 crore, and other income is gradually declining because of better payment trends from DISCOMs.
Capex & Balance Sheet
- Capex trajectory: FY23 capex target is ~₹27,500 crore (group level); FY24 capex is projected at ~₹25,000–26,000 crore (standalone plus group); FY25 and beyond will be maintained above ₹20,000 crore per year, with new coal projects adding ~₹12,000 crore per year from FY25 to FY29.
- Bond issuances: Issued ₹3,500 crore in bonds during H1 FY23 across two tranches: ₹1,500 crore at 5.78% for 2 years and ₹2,000 crore at 7.44% for 10 years.
- Term loans: Signed term loan agreements totalling ₹5,000 crore with HDFC Bank, UCO Bank, and Bank of Baroda.
- FGD capex: All FGD projects are in different stages of completion, with significant capex investment ongoing.
- Solar EPC contracts: All balance-of-system packages are fixed-price, and no renegotiations are possible because bid tariffs are also not open for negotiation.
- Module price relief: Management has heard that the government is considering a 12-month time extension without conditions for projects facing high module prices.
Management: "No, they cannot happen because in all these projects, the tariffs which we have bid at, those are also not open for negotiation."
Guidance & Commitments
| Commitment | Specifics | Timeline |
|---|---|---|
| NGEL stake sale | Offload 10–20% stake in consolidated green entity | Close of Q3 FY23 or before FY23 end (December, possibly into January) |
| FY23 capacity addition | Around 5,000 MW | FY23 |
| FY24 capacity addition | Around 7,000 MW combined | FY24 |
| Three-year capacity addition | Around 18 GW | FY23–FY25 |
| Fixed cost under-recovery | Narrow to ~₹250 crore from ₹718 crore in H1 | FY23 year-end |
| JV/Subsidiary profit recovery | Half-yearly profit contribution to rise by ₹400–450 crore from current ~₹980 crore | Once HURL and Meja stabilize |
| Receivable days | Less than 45 days | Going forward |
| Coal blending | Proportion to come down significantly | Remaining half of FY23 |
| Lara expansion award | NIT award for 2x800 MW | By March 2023 |
| Talcher first unit | Commissioning | August 2026 (48 months from award) |
| Talcher full project | Completion | FY27 |
| Capex | ~₹25,000–26,000 crore (standalone + group) | FY24 |
| Capex | Maintained above ₹20,000 crore/year; new coal projects adding ~₹12,000 crore/year | FY25 and beyond |
Key Metrics
| Metric | Q2 FY23 |
|---|---|
| Total Income | ₹41,810.96 cr, +37.96% YoY |
| PAT | ₹3,331.20 cr, vs ₹3,156.74 cr in Q2 FY22 |
| Group PAT (H1 FY23) | ₹7,395.44 cr, +3.65% YoY |
| Regulated equity (standalone) | ₹74,865.53 cr as on 30 Sep 2022 |
| Average cost of borrowing (H1 FY23) | 6.22%, vs 5.96% in H1 FY22 |
| Group CAPEX (H1 FY23) | ₹16,664.19 cr, vs ₹15,137.67 cr in H1 FY22 |
| FY23 group CAPEX target | ~₹27,500 cr |
| FY24 group CAPEX expectation | ~₹25,000–26,000 cr |
| Commercial capacity (standalone) | 57,639 MW as on 30 Sep 2022 |
| Commercial capacity (Group) | 70,254 MW as on 30 Sep 2022 |
| Coal station PLF (H1 FY23) | 77.27%, vs national average of 64.46% |
| Coal materialisation against ACQ (H1 FY23) | 99.93%, vs 96.04% in H1 FY22 |
| Own coal production (H1 FY23) | 0.88 crore MT, +58% YoY |
| Fixed cost under-recovery (H1 FY23) | ₹718 cr, expected to reduce to ~₹250 cr by year-end |
| Late payment surcharge (Q2 FY23) | ₹229 cr |
| One-time finance charge on LPS receivables | ₹333 cr, on receivables of ₹6,108 cr |
| RE projects under construction | 5,348 MW including NTPC REL ongoing projects |
| Capacity addition target (FY23+FY24+FY25) | ~18 GW combined |
| NVVN units transacted (H1 FY23) | 1,525 crore Units, +27% YoY |
| Share of profit in JVs (H1 FY23) | ₹120.57 cr, vs ₹526.45 cr in H1 FY22 |
| HURL losses (H1 FY23) | ~₹715 cr, Gorakhpur unit at 37% capacity utilisation |
| Average tariff (H1 FY23) | ₹4.77/unit, vs ₹3.86/unit in H1 FY22 |
| Coal blending proportion (H1 FY23) | ~7.9%, down to 3% as of call date |
| Receivable days expectation | Less than 45 days going forward |
| RE monetisation: identified capacity | 2,861 MW, book value over ₹10,000 cr; stake dilution up to 20% in NGEL |