NTPC Ltd Q2 FY2024 Concall Summary

Source transcript PDF: https://assets.stockscans.in/docs/p1zi37b2ztb3hp0bpir2j3u6.pdf

Key Takeaways


The JV Profit Surge: A One-Off or Structural Shift?

Management: "It would only be fair to assume it would be around 15-20% but depends on several factors."

Coal: Record Captive Output Meets Tight Inventory


Thermal: A 25 GW Build-Out Is Taking Shape

Management: "As an optimist project manager I am saying it is there, the scope is always there, and we will try everything to do it. But in Indian context, I will tell you, there are some basic problems that we face."

Renewables: Scaling Fast, Listing Later

Management: "We will be working on that and by year and a half or two years there should be a substantial capacity on ground, but when we reach a certain critical mass, we will time it."

Pumped Storage: A 14 GW Ambition with a Long Fuse

Management: "Storage is the cost which is in my control. So that will be of the order of ₹3.50 to ₹4.00 depending on the type of project and location."

Financial Health: Capex Rising, Borrowing Costs Creeping Up

Management: "Yes, we keep on going upwards only and that is a growing company."

Guidance & Commitments

CommitmentSpecificsTimeline
Thermal capacity award11.2 GW to be tendered (50% standalone, 50% JVs)Progressively over next 12 months
Thermal order placementSingrauli 1,600 MW, Sipat 800 MW, Darlipalli 800 MW, Meja 2,400 MWDec 2023, Feb 2024, Jun 2024, Sep 2024 respectively
Thermal capacity commissioning1,480 MW this year, 5,240 MW next FY, ~1,764 MW in FY26FY24, FY25, FY26
Renewable bid completionAll 50 GW bids to be completedBy end-March
Renewable capacity target15 GW commissionedBy FY26
Renewable capacity target60 GW commissionedBy end-FY32
Pumped storage (THDC)First unit of 1,000 MW projectJanuary or latest February
Pumped storage (THDC)Entire 1,000 MW commissionedBy FY25
Fixed cost under recoveryNarrow to ~₹200 croreBy FY24 year-end
Consolidated vs standalone PAT gap15-20% rangeFY25 and going forward
FY24 capex₹28,373 crore (group)FY24
FY25 capexRemaining almost in same range as FY24FY25
Green entity listingStake sale or IPO after reaching critical mass1.5 to 2 years
FGD systemsCommission for entire operational and under-construction capacityOver next 3 years

Key Metrics

MetricQ2 FY24
Total Income (standalone)₹41,517.87 cr, vs ₹41,810.96 cr in Q2 FY23
PAT (standalone)₹3,885.01 cr, +16.62% YoY vs ₹3,331.20 cr in Q2 FY23
Adjusted PAT (standalone)₹3,497 cr, vs ₹3,601 cr in Q2 FY23 and ₹3,794 cr in Q1 FY24
Group PAT (H1 FY24)₹9,633.53 cr, +30.26% YoY vs ₹7,395.44 cr in H1 FY23
Regulated equity (standalone)₹81,498 cr as on 30 Sep 2023
Regulated equity (group)₹98,050 cr as on 30 Sep 2023
Average cost of borrowing (H1 FY24)6.67%, vs 6.22% in H1 FY23
Group CAPEX (H1 FY24)₹13,203.60 cr, vs ₹16,664.19 cr in H1 FY23; FY24 target ₹28,373 cr
Fixed cost under recovery₹381 cr in Q2; full-year estimate near ₹200 cr
Commercial capacity (standalone)57,838 MW as on 30 Sep 2023
Commercial capacity (group)73,824 MW as on 30 Sep 2023
Group generation (H1 FY24)21,200 crore Units, +4% YoY vs 20,400 crore Units in H1 FY23
PLF of coal stations (H1 FY24)76.62%, vs National Average of 68.75%
Coal production from captive mines (H1 FY24)1.61 crore MT, +83% YoY vs 8.76 MMT in H1 FY23
Renewable capacity commissioned3,314 MW; 7,258 MW under construction; visible pipeline of more than 20 GW
Renewable capacity target15 GW by FY26, long-term target 60 GW by end of FY32
Thermal capacity addition planned for award11.2 GW by next fiscal, in addition to 10 GW already under construction
Pumped storage capacity identified~14,000 MW across multiple states, at various stages of development