NTPC Ltd Q2 FY2025 Concall Summary

Source transcript PDF: https://assets.stockscans.in/docs/tkw04s65a4fxzlbr41e1z3mq.pdf

Key Takeaways


Profitability Drivers

Management: "the cost is booked on the relevant account head of either interest or the finance cost, other expenses, and we are capturing the pass-through because it's a cost-plus mechanism, The Pass-through happens through below the PBT."

Nuclear Build-Out


Renewable Energy & NGEL

Management: "going ahead further, they will -- NGEL will also have an edge that they will have access to a lot of multilateral loans from financial multilaterals who are with a clear exclusive focus on green energy, renewable energy and ESG."

Thermal Business

Management: "this FGD is coming out of a statutory stipulation depending on the environmental imperatives. These are policy decision at the highest level. And however, at the company level, this becomes a change in law. Even if it is introduced, altered, withdrawn, as far as the company is concerned, it operates on a cost-plus principles, and we are completely hedged against this kind of a situation."

Operational Highlights


Guidance & Commitments

CommitmentSpecificsTimeline
Thermal capacity awards8.8 GW awardedBy December 2024
Thermal capacity awardsBalance 4.8 GW orderedNext financial year (FY26)
Thermal capacity under construction13.6 GW awarded, adding to 11.16 GW already under constructionBy FY27
Renewable capacity addition3 GW FY25, 5 GW FY26, 8 GW FY27; 19.4 GW operationalBy FY27
Renewable energy target60 GW (solar, wind, storage, green molecules)By FY32
Coal productionGroup production rising from 4 crore MT to 6.7 crore MTFY25 to FY29
FGD commissioningEntire operational and under-construction capacity coveredOver next 3 years
Mahi Banswara nuclearFirst pour of concreteMarch 2026
Mahi Banswara nuclearFirst unit criticality, all 4 units operationalFY31-32 / FY32
Tehri PSPAll four 1,000 MW units commissionedBy December 2024
Telangana and Gadarwara PPA consentBalance consent (~75% and ~68%) securedWithin 2 months
NGEL IPOProcess proceeding as plannedQ3 FY25 timeline
Stand-alone capital outlayINR 22,700 croresFY25
Consolidated group capital outlayINR 27,982 croresFY25
PSP at NGEL~8 GW expectedNo date (pipeline)

Key Metrics

MetricQ2 FY25
Total income (stand-alone)₹41,245 cr, vs ₹41,518 cr in Q2 FY24, decline of 0.66%
PAT (stand-alone, reported)₹4,649 cr, vs ₹3,885 cr in Q2 FY24, increase of 19.66%
PAT (stand-alone, adjusted)₹4,202 cr
PAT (consolidated, reported)₹5,380 cr
PAT (consolidated, adjusted)₹4,867 cr
Total income (group, H1 FY25)₹94,179 cr, vs ₹88,775 cr in H1 FY24, increase of 6.09%
PAT (group, H1 FY25)₹10,886 cr, vs ₹9,634 cr in H1 FY24, increase of 13%
Stand-alone regulated equity₹89,430 cr as on 30 Sep 2024, growth of 7.67% YoY
Consolidated regulated equity₹105,049 cr as on 30 Sep 2024, growth of 5.5% YoY
Interim dividend declared₹2.50 per share for FY 2024-25
Average interest rate on borrowings (H1 FY25)6.63%, vs 6.67% in H1 FY24
Group capex (H1 FY25)₹17,474 cr, vs ₹13,204 cr in H1 FY24
Stand-alone capex (H1 FY25)₹14,040 cr, vs ₹7,959 cr in H1 FY24
Stand-alone capital outlay target (FY25)₹22,700 cr
Consolidated capital outlay target (FY25)₹27,982 cr
Group gross generation (H1 FY25)22,000 crore units, growth of 3.77% YoY
Stand-alone gross generation (H1 FY25)18,600 crore units, growth of 3.91% YoY
Coal station PLF (H1 FY25)76.31%, vs national average of 70.63%
Coal materialization against ACQ (H1 FY25)97%, vs 95.8% in H1 FY24
Coal supply (H1 FY25)11.94 crore metric tons, including 0.2 crore metric ton imported
Own coal production (H1 FY25)1.92 crore metric tons, growth of 19.74% YoY
Cumulative coal mine development expenditure₹11,585 cr till 30 Sep 2024
Under recovery / disincentive₹495 cr, vs ₹381 cr in Q2 FY24
Planned outages6.12%, vs 5.19% in Q2 FY24
Unfavourable ERV expenses (regulatory deferral)₹1,997 cr
Commissioned RE capacity (group)4,013 MW
RE capacity addition target (FY25)3 GW
RE capacity addition target (FY26)5 GW
RE capacity addition target (FY27)8 GW, taking operational capacity to 19.4 GW
Thermal capacity under construction11.16 GW
Fresh thermal capacity planned for award by FY2713.6 GW, of which 8.8 GW bidded out and expected awarded by Dec 2024
Thermal commissioning target (FY25)2.7 GW
Thermal commissioning target (FY26)1.46 GW
FGD commissioned14,600 MW, work under progress for 49 GW cumulative
Ash supplied to road projects (H1 FY25)2.45 crore metric tons, vs 2.15 crore metric tons in H1 FY24
Biomass received (H1 FY25)2.62 lakh metric tons, vs 0.31 lakh metric tons in H1 FY24
NGEL operational RE capacity~4.3 GW
NGEL contracted and awarded pipeline~12 GW, further ~11.5 GW at different stages
PSP pipeline at NGEL~8 GW, comprising 2.8 GW awarded (Tamil Nadu, Maharashtra) and 4.2 GW in pipeline
Mahi Banswara nuclear project first pour of concreteMarch 2026, all 4 units (4x700 MW) by FY32
Capacity addition in Q2 FY25485 MW, all renewable (90 MW NTPC, 395 MW group companies)