Key Takeaways
- PAT jumps 20% on lower coal costs: Stand-alone PAT rose 19.66% YoY even as revenue dipped 0.66%, driven by a 5.46% fall in coal prices and improved coal materialization to 97%.
- Nuclear structure takes shape: A JV with NPCIL (ASHVINI) will build PHWR projects, while a new wholly owned subsidiary will pursue SMRs, FBRs and PWRs, with the Mahi Banswara project targeting first concrete by March 2026.
- Renewable pipeline scales fast: NGEL signed JVs for 35 GW of RE with Rajasthan and Maharashtra, targets 3 GW addition this year rising to 8 GW by FY27, and its IPO process is proceeding as planned.
- Thermal ordering cycle accelerates: 8.8 GW of thermal awards are expected by December, with the balance 4.8 GW next year, adding to 11.16 GW already under construction toward a 13.6 GW target by FY27.
- What to watch next quarter: The NGEL IPO valuation and timing, progress on the 8.8 GW thermal award target, and any update on the Chutka nuclear project transfer.
Profitability Drivers
- Coal cost tailwind: Average coal price fell INR 207 per ton (5.46%), more than offsetting the 0.66% revenue decline and lifting stand-alone PAT 19.66% and group PAT 13% in H1.
- Coal materialization improved: Materialization rose to 97% from 95.8% in H1 FY24, while imported coal consumption dropped sharply from 3.73 MMT to 0.2 crore metric tons, reducing exposure to seaborne prices.
- Dividend income boost: Dividend from subsidiaries and JVs rose from INR 541 crores to INR 762 crores, with subsidiary profits up 21.91% and JV share up 3.88%.
- Under-recovery headwind: Under-recovery and disincentive increased to INR 495 crore from INR 381 crore, driven by higher planned outages (6.12% vs 5.19%) and the composition of capacity charges across plants.
- Regulatory deferral mechanics: Unfavourable ERV expenses of ~INR 1,997 crores moved through the regulatory deferral account, booked in relevant cost heads while the pass-through is captured below PBT, making it profit-neutral under the cost-plus mechanism.
Management: "the cost is booked on the relevant account head of either interest or the finance cost, other expenses, and we are capturing the pass-through because it's a cost-plus mechanism, The Pass-through happens through below the PBT."
Nuclear Build-Out
- Dual-entity structure: ASHVINI, the JV with NPCIL, will execute Pressurized Heavy Water Reactor projects, while a newly formed wholly owned NTPC subsidiary will implement Small Modular Reactors, Fast Breeder Reactors and Pressurized Water Reactors.
- Mahi Banswara first: The Government approved transfer of the Mahi Banswara nuclear power project (4 x 700 MW) to ASHVINI, with first pour of concrete targeted for March 2026, first unit criticality by FY31-32, and all four units by FY32.
- Chutka stalled on land: The Chutka project has not been transferred to the JV due to land issues, and NPCIL is currently working on resolution; management offered no definitive timeline.
- Nuclear excluded from NGEL: Nuclear energy will sit outside NTPC Green Energy Limited, which will focus on solar, wind, storage and green molecules.
Renewable Energy & NGEL
- IPO on track: NGEL filed its DRHP on 18 September 2024 and the process is proceeding as planned, with a Q3 timeline; no valuation has been decided yet.
- State JVs secure land and scale: NGEL signed a JV with Rajasthan RVUNL for 25 GW RE and 1 MMT per annum green hydrogen/derivatives, and with Maharashtra MAHAPREIT for 10 GW RE parks/projects, with the state partner bringing land in each case.
- Capacity ramp: RE addition targets are 3 GW in FY25, 5 GW in FY26, and 8 GW in FY27, taking operational capacity to 19.4 GW by FY27, toward a 60 GW target by FY32.
- PSP allocation: Pumped storage will sit within NGEL for renewable RTC and firm dispatchable solutions, with stand-alone PSPs also implemented by THDC and NEEPCO subsidiaries; ~8 GW of PSP is expected at NGEL.
- Funding edge: NGEL will have access to multilateral loans from institutions with an exclusive focus on green energy and ESG, enabling cheaper funding than the parent.
- Selective bidding strategy: The company participates in pure-play solar and wind but evaluates structured bids like RTC and FDRE based on risk profile and return expectations, while building land banks and scaling individual locations to avoid transmission constraints.
Management: "going ahead further, they will -- NGEL will also have an edge that they will have access to a lot of multilateral loans from financial multilaterals who are with a clear exclusive focus on green energy, renewable energy and ESG."
Thermal Business
- Award cycle accelerating: 8.8 GW of thermal capacity awards are expected by December, with the balance 4.8 GW ordered in the next financial year, adding to 11.16 GW already under construction toward a 13.6 GW target by FY27.
- Recent approvals: Investment approval accorded for Sipat Stage-III (1x800 MW) and Darlipali Stage-II (1x800 MW), with EPC contracts already placed for both.
- PLF outperformance despite decline: NTPC coal stations achieved 76.31% PLF vs the national average of 70.63%, with Lara (91.63%) and Singrauli (88.83%) ranked 5th and 13th nationally; management noted thermal PLF will structurally decline as renewables grow and thermal plays a subservient daytime role.
- Capex per MW rising: Thermal capex has moved beyond INR 12 cr/MW due to the addition of Air Cooled Condensers for water conservation (~INR 0.7 cr/MW) and a reduction in EPC bidders to only one, causing slight cost increases; costs are lower when three units are built together.
- Coal production at record: Highest-ever coal production of 1.92 crore metric tons in H1 FY25, up 19.74%, with a target to grow group production from 4 crore metric tons in FY25 to 6.7 crore metric tons by FY29.
- FGD fully hedged: FGD commissioning is planned for the entire operational and under-construction capacity over the next three years, covering 49 GW; management stated that any policy change on FGD would be a change in law, and the cost-plus mechanism provides a complete hedge.
Management: "this FGD is coming out of a statutory stipulation depending on the environmental imperatives. These are policy decision at the highest level. And however, at the company level, this becomes a change in law. Even if it is introduced, altered, withdrawn, as far as the company is concerned, it operates on a cost-plus principles, and we are completely hedged against this kind of a situation."
Operational Highlights
- Biomass co-firing surge: 2.62 lakh metric tons of biomass received in H1 FY25, a sharp increase from 0.31 lakh metric tons in H1 FY24.
- Ash utilization: Nine stations achieved 100% ash utilization, with 2.45 crore metric tons supplied to road projects vs 2.15 crore metric tons in H1 FY24.
- Cross-border power sales: NVVN signed a PPA with Nepal Electricity Authority for 230 MW, and a trilateral agreement between NVVN, NEA and BPDP for supply of 40 MW from Nepal to Bangladesh.
- Tehri PSP nearing completion: All four units of the 1,000 MW Tehri PSP are expected to commission by December.
- PPA consent pending: Balance PPA consent for Telangana (~75%) and Gadarwara (~68%) is expected within two months.
Guidance & Commitments
| Commitment | Specifics | Timeline |
|---|---|---|
| Thermal capacity awards | 8.8 GW awarded | By December 2024 |
| Thermal capacity awards | Balance 4.8 GW ordered | Next financial year (FY26) |
| Thermal capacity under construction | 13.6 GW awarded, adding to 11.16 GW already under construction | By FY27 |
| Renewable capacity addition | 3 GW FY25, 5 GW FY26, 8 GW FY27; 19.4 GW operational | By FY27 |
| Renewable energy target | 60 GW (solar, wind, storage, green molecules) | By FY32 |
| Coal production | Group production rising from 4 crore MT to 6.7 crore MT | FY25 to FY29 |
| FGD commissioning | Entire operational and under-construction capacity covered | Over next 3 years |
| Mahi Banswara nuclear | First pour of concrete | March 2026 |
| Mahi Banswara nuclear | First unit criticality, all 4 units operational | FY31-32 / FY32 |
| Tehri PSP | All four 1,000 MW units commissioned | By December 2024 |
| Telangana and Gadarwara PPA consent | Balance consent (~75% and ~68%) secured | Within 2 months |
| NGEL IPO | Process proceeding as planned | Q3 FY25 timeline |
| Stand-alone capital outlay | INR 22,700 crores | FY25 |
| Consolidated group capital outlay | INR 27,982 crores | FY25 |
| PSP at NGEL | ~8 GW expected | No date (pipeline) |
Key Metrics
| Metric | Q2 FY25 |
|---|---|
| Total income (stand-alone) | ₹41,245 cr, vs ₹41,518 cr in Q2 FY24, decline of 0.66% |
| PAT (stand-alone, reported) | ₹4,649 cr, vs ₹3,885 cr in Q2 FY24, increase of 19.66% |
| PAT (stand-alone, adjusted) | ₹4,202 cr |
| PAT (consolidated, reported) | ₹5,380 cr |
| PAT (consolidated, adjusted) | ₹4,867 cr |
| Total income (group, H1 FY25) | ₹94,179 cr, vs ₹88,775 cr in H1 FY24, increase of 6.09% |
| PAT (group, H1 FY25) | ₹10,886 cr, vs ₹9,634 cr in H1 FY24, increase of 13% |
| Stand-alone regulated equity | ₹89,430 cr as on 30 Sep 2024, growth of 7.67% YoY |
| Consolidated regulated equity | ₹105,049 cr as on 30 Sep 2024, growth of 5.5% YoY |
| Interim dividend declared | ₹2.50 per share for FY 2024-25 |
| Average interest rate on borrowings (H1 FY25) | 6.63%, vs 6.67% in H1 FY24 |
| Group capex (H1 FY25) | ₹17,474 cr, vs ₹13,204 cr in H1 FY24 |
| Stand-alone capex (H1 FY25) | ₹14,040 cr, vs ₹7,959 cr in H1 FY24 |
| Stand-alone capital outlay target (FY25) | ₹22,700 cr |
| Consolidated capital outlay target (FY25) | ₹27,982 cr |
| Group gross generation (H1 FY25) | 22,000 crore units, growth of 3.77% YoY |
| Stand-alone gross generation (H1 FY25) | 18,600 crore units, growth of 3.91% YoY |
| Coal station PLF (H1 FY25) | 76.31%, vs national average of 70.63% |
| Coal materialization against ACQ (H1 FY25) | 97%, vs 95.8% in H1 FY24 |
| Coal supply (H1 FY25) | 11.94 crore metric tons, including 0.2 crore metric ton imported |
| Own coal production (H1 FY25) | 1.92 crore metric tons, growth of 19.74% YoY |
| Cumulative coal mine development expenditure | ₹11,585 cr till 30 Sep 2024 |
| Under recovery / disincentive | ₹495 cr, vs ₹381 cr in Q2 FY24 |
| Planned outages | 6.12%, vs 5.19% in Q2 FY24 |
| Unfavourable ERV expenses (regulatory deferral) | ₹1,997 cr |
| Commissioned RE capacity (group) | 4,013 MW |
| RE capacity addition target (FY25) | 3 GW |
| RE capacity addition target (FY26) | 5 GW |
| RE capacity addition target (FY27) | 8 GW, taking operational capacity to 19.4 GW |
| Thermal capacity under construction | 11.16 GW |
| Fresh thermal capacity planned for award by FY27 | 13.6 GW, of which 8.8 GW bidded out and expected awarded by Dec 2024 |
| Thermal commissioning target (FY25) | 2.7 GW |
| Thermal commissioning target (FY26) | 1.46 GW |
| FGD commissioned | 14,600 MW, work under progress for 49 GW cumulative |
| Ash supplied to road projects (H1 FY25) | 2.45 crore metric tons, vs 2.15 crore metric tons in H1 FY24 |
| Biomass received (H1 FY25) | 2.62 lakh metric tons, vs 0.31 lakh metric tons in H1 FY24 |
| NGEL operational RE capacity | ~4.3 GW |
| NGEL contracted and awarded pipeline | ~12 GW, further ~11.5 GW at different stages |
| PSP pipeline at NGEL | ~8 GW, comprising 2.8 GW awarded (Tamil Nadu, Maharashtra) and 4.2 GW in pipeline |
| Mahi Banswara nuclear project first pour of concrete | March 2026, all 4 units (4x700 MW) by FY32 |
| Capacity addition in Q2 FY25 | 485 MW, all renewable (90 MW NTPC, 395 MW group companies) |