NTPC Ltd Q2 FY2026 Concall Summary

Source transcript PDF: https://assets.stockscans.in/docs/nuha2sc1txz5qs450k2huy2g.pdf

Key Takeaways


Demand & Generation: A Weather-Driven Quarter

Management: "There was a clear dichotomy over which was working to them, which was detrimental to us. But based on the policy advocacy and follow-up, now this Suo-Moto order has ameliorated that situation for us."

Capacity Addition: Record Pace, Bigger Ambition

Management: "We have a clear visibility on the CODs over the next three years."

Financial Health: Lower Costs, Cleaner Balance Sheet

Management: "I would just like to inform the members that the promoters are taking this very, very seriously and all attempts are being made to get the receivables from the various urban local bodies and we are looking at various options including our stake sale in IntelliSmart."

Renewables & Storage: Scaling the Next Engine

Management: "The co-located BESS are primarily being done with an intent to use the solar capacity during the peak hours in the evening. So, that is expected to give us a significant boost in our revenue. But the exact numbers would come up only once we are able to firm up the tie-ups."

Thermal & Nuclear: The Base Load Foundation

Management: "No, we don't intend participating in any tariff-based competition."

ESG & Operational Excellence


Guidance & Commitments

CommitmentSpecificsTimeline
Fixed cost under-recoveriesReduce to ~₹250 croreBy year-end FY26
Tehri PSP commissioningRemaining two 250 MW unitsCurrent fiscal
Coal mine transfer to NMLAll remaining mines transferredCurrent fiscal
Meja II project startState UP approval, work beginsApproval within 2 months; work from Jan 1
Mahi Banswara nuclear awardBalance nuclear island and TG package awardedThis financial year
BESS project awardAwards for battery storage projectsCurrent financial year
Lara Stage 3 (1.6 GW) awardNew thermal orderingThis financial year
FY26 capacity addition (COD)6 GW totalCurrent fiscal
FY27 capacity addition (COD)8 GW totalNext fiscal
FY28 capacity addition (COD)8 GW totalFY28
NGEL FY26 RE capacity addition5,365 MWCurrent fiscal
NGEL FY27 RE capacity addition8 GWNext fiscal
NGEL FY26 capex~₹30,000 croreCurrent fiscal
NGEL FY27 capex~₹45,000-46,000 croreNext fiscal
Q3 RE commissioning~2 GWQ3 FY26
Q4 RE commissioning~1.7 GWQ4 FY26
Ayana RE-RTC projectsCommissionedAlmost by end of this year
BESS project completionWithin 3 years from award3 years from award date

Key Metrics

MetricQ2 FY26
Standalone total income₹40,689 cr, vs ₹41,245 cr in Q2 FY25
Standalone PAT₹4,653 cr, vs ₹4,649 cr in Q2 FY25
Standalone adjusted PAT₹4,518 cr, up 8% vs ₹4,202 cr in Q2 FY25
Consolidated adjusted PAT₹5,069 cr, up 3% vs ₹4,943 cr in Q2 FY25
Group total income (H1 FY26)₹93,083 cr, vs ₹94,179 cr in H1 FY25
Group PAT (H1 FY26)₹11,334 cr, up 4% vs ₹10,886 cr in H1 FY25
NGEL consolidated revenue₹612 cr, up 21% vs ₹504 cr in Q2 FY25
NGEL operating EBITDA₹530 cr, up 26% vs ₹420 cr in Q2 FY25
NGEL operating EBITDA margin86%, vs 83% in Q2 FY25
Average cost of borrowing (H1 FY26)6.11%, vs 6.63% in H1 FY25
Group CAPEX (H1 FY26)₹23,115 cr, vs ₹17,474 cr in H1 FY25
Standalone CAPEX (H1 FY26)₹14,149 cr, vs ₹14,040 cr in H1 FY25
NGEL consolidated capex (H1 FY26)₹6,607 cr, vs ₹4,884 cr in H1 FY25
Consolidated regulated equity₹1,16,022 cr as on 30 Sep 2025, up 10% vs ₹1,05,049 cr as on 30 Sep 2024
Standalone regulated equity₹94,454 cr as on 30 Sep 2025, up 6% vs ₹89,430 cr as on 30 Sep 2024
NTPC Group installed capacity84,849 MW as on date, up from 83,893 MW at H1 end
Group total generation (H1 FY26)214 BUs, ~600 crore units lower vs H1 FY25
Coal stations PLF70.52%, vs rest of India average of 64.32%
Coal stock at stations13.4 MMT, up 2.1 MMT YoY, sufficient for 15 days at 85% PLF
Captive mines dispatch growth (H1 FY26)2.61% YoY
Fixed costs under recoveries₹625 cr till Sep 2025, expected ~₹250 cr by year-end
Operational gains from coal stations (H1 FY26)₹238 cr
Operational gains from hydro stations (H1 FY26)₹49 cr
Receivables from DISCOMs28 days, improved from 33 days YoY
FY26 capacity addition target9,844 MW (2,019 MW standalone, 7,825 MW JVs and subsidiaries)
Capacity added till H1 FY264,403 MW, highest in any half year since inception
Additional capacity added in October 2025956 MW, taking total fresh addition to 5,359 MW as on date
NGEL Group installed capacity7,564 MW as on date
Current capacity under construction33 GW (17 GW coal, 2 GW hydro, 14 GW renewable)
Revised capacity target149 GW by 2032, 244 GW by 2037
Estimated capex requirement₹7 lakh crore by 2032
First interim dividend₹2.75 per equity share for FY 2025-26
MSCI ESG rating4.1, improved from 3.4
Sustainalytics ESG risk rating31, improved from 35.7
FGD cumulative capacity commissioned20,270 MW, work in progress for balance 39,390 MW
Biomass co-firing (H1 FY26)Over 5 lakh metric tons, nearly double YoY
NTPC Vidyut Vyapar Nigam power trading growth11.45%, from 22.3 BUs to 24.8 BUs
NGEL green ammonia contract0.7 lakh tonnes secured in green chemical tender
Mahi Banswara nuclear project4 x 700 MW, estimated cost ~₹50,000 cr, completion by 2032-33
BESS at existing thermal projects5,000 MWh, fully regulated, with VGF of ₹18 lakh per MWh
BESS tendered2.3 GW already tendered, 2.9 GW expected in December
Land pool for solar projects22.8 GW total, with 16.5 GW in advanced stage
EESL lossesExpected to continue till FY26