Key Takeaways
- PAT growth lagged revenue surge: Total Income jumped 35% YoY on higher generation, but standalone PAT rose only 5% YoY to ₹4,476 crore as finance costs and other expenses ate into the top-line gain.
- JV/subsidiary profits fell sharply: Group PAT grew just 4% YoY for 9M, dragged by a ₹354 crore drop in JV profit (to ₹481 crore) as the Late Payment Surcharge rules converted outstanding dues into instalments, shrinking a lucrative income stream.
- Coal and generation story is strong: Own coal production rose 51% YoY, materialisation against ACQ hit 98.2%, and PLF stayed 11 points above the national average, putting the thermal fleet in a solid operational position.
- The nuclear ambition is now concrete: Management laid out a path to 20,000 MW by 2050, starting with the ASHVINI JV for PHWRs and active work on SMRs and PWRs via government-to-government deals, with a stated tariff of ₹7.36/kWh at 80% PLF.
- What to watch next quarter: Whether the renewable monetisation closes by March as promised, the Lara expansion award lands by April, and fixed cost under-recovery hits the ₹250 crore target by year-end.
Profitability Drag: JVs, Finance Costs & Other Expenses
- JV profit collapse: Profit from JVs fell to ₹481 crore from ₹834 crore, with THDC alone down ₹126 crore. The common driver was the LPS scheme, which forced outstanding dues into instalments and slashed late payment surcharge income, a previously reliable contributor.
- Subsidiary profit also down: Subsidiary profit fell 7% to ₹1,290 crore, with the same LPS dynamic at work. HURL added a ~₹76 crore variation hit because gas consumption ran above norms.
- Finance cost spike: Finance costs rose ₹524 crore QoQ, with exchange rate variation accounting for ₹421 crore of that. The average cost of borrowing also ticked up to 6.32% from 5.95% a year ago.
- Other expenses jumped: Other expenses rose ₹2,674 crore, driven by exchange rate variation (₹1,783 crore), ash utilisation and marketing (₹483 crore), and higher R&M (₹239 crore) from more outage and overhaul activity in the quarter.
- Late payment surcharge trending down: Q3 brought in just ₹67 crore, and the 9M figure of ₹459 crore reflects a structural decline. Management framed this positively: the low trend signals better collection efficiency, and the surcharge was always a deterrent, not a core income line.
Management: "Late payment surcharge is not our main source of income. It is incidental if these are more of a deterrent rates of recovering the financial cost. So, the low trend is in one sense indicative of a better collection efficiency."
Operational Strength: Generation, Coal & PLF
- Generation growth: NTPC Group generated 29,500 crore units in 9M FY23, up ~11% YoY, with standalone gross generation up ~12%, reflecting both higher demand and improved coal supply.
- PLF dominance: Average PLF of NTPC coal stations was 74.45%, maintaining a spread of more than 11 percentage points over the national average of 63.27%. Five NTPC stations ranked among the top 10 nationally.
- Coal supply improved materially: Coal supply rose to 166 MMT (including 11.59 MMT imported) from 148 MMT, and materialisation against ACQ improved to 98.20%. Management sees no shortage this year, with ~15 days of stock on hand and imported coal in the pipeline.
- Own coal production surged: NTPC's own coal production grew ~51% YoY to 1.46 crore MMT, and the first coal rake from Talaipalli Mine was dispatched to Lara station in November 2022.
- Backing down reduced: Backing down fell from 7,628 crore units to 7,238 crore units, helped by improved scheduling from beneficiaries.
- Fixed cost under-recovery improving: The 9M figure fell to ₹548 crore from ₹692 crore, and the ash transportation accounting change (now booking under revenue after the final CERC order) improves PBT and cash flow by enabling billing to DISCOMs.
Management: "The fixed cost under recovery for 9 months is Rs.548 crore, this is much less than the corresponding previous period, which was Rs.692 crore. However, we are targeting to bring it down to a level of Rs.250 crore by FY end."
Nuclear: The New Growth Leg
- ASHVINI JV structure: NTPC will execute nuclear capacity addition through Pressurised Heavy Water Reactors via ASHVINI, a JV with NPCIL. Asset transfer modalities for Chutka (2x700 MW, Madhya Pradesh) and Mahi Banswara (4x700 MW, Rajasthan) are in progress.
- Beyond PHWRs: NTPC is also contemplating Small Modular Reactors and Pressurised Water Reactors through government-to-government agreements, and is pursuing fuel tie-ups with Uranium Corporation of India Ltd.
- Capacity roadmap: Management targets 2,000 MW by 2032 from Chutka and Mahi Banswara, 4,200 MW by 2035, and ~20,000 MW by 2050.
- Tariff economics: Nuclear will operate on a single-part tariff as a must-run plant, ranking high in the merit order. At 80% PLF, the tariff would come down from ₹7.36/kWh.
- Liability not a blocker: Management is working with the government on the liability clause and stated NPCIL is already comfortable. The problem sits with EPC contractors wanting a shield, not with NTPC as developer, and management does not see it as an issue for this fleet.
Management: "By 2050, we will have around 20000 MW capacity in NTPC from nuclear."
Renewables: Pipeline, Monetisation & Run Rate
- FY23 additions: NTPC added more than 1.3 GW of renewable capacity in FY23 through 31 December, and the Group commissioned 3,154 MW of RE projects under EPC mode.
- Pipeline under construction: 4,718 MW of RE projects are under construction, with plans for another 24 GW of Ultra Mega Renewable Energy Power Parks at various stages.
- Feasibility pipeline: ~36 GW of RE is under feasibility and planning, split between ~26 GW via solar parks and ~10 GW under CPSU schemes.
- 60 GW by 2032 breakdown: 40 GW from tariff-based competitive bidding (35 GW plus 5 GW CPSU), 15 GW non-PPA (5 GW flexibilisation, 5 GW merchant, 5 GW C&I/BESS), and 5 GW from green hydrogen.
- Run rate ambition: Management expects to hit a 5 to 6 GW per year renewable run rate starting in 1 to 1.5 years, once module supply issues are sorted.
- Monetisation on track: The renewable monetisation process is to be concluded by March, with management contemplating offloading 10% to 20% depending on response. Management declined to hazard a guess on the quantum, citing the live bidding process.
- Land tied up: Land has been secured in Gujarat and partly in Madhya Pradesh, with more being tied up in Karnataka and Rajasthan.
Management: "We cannot hazard a guess, as far as the quantum is concerned, we are contemplating offloading between 10% to 20%, depending on the response. So, it would be difficult, and it will not be appropriate also to give an expectation here when the bidding process is on within the board."
Thermal Pipeline & Capex
- Lara expansion: The bid for the 1.6 GW Lara expansion is expected to open in March 2023 and be awarded by April 2023.
- Singrauli ordering: Thermal capacity ordering for Singrauli is targeted by December 2023.
- Thermal pipeline FY24-FY25: Around 6,100 MW of thermal capacity addition is planned across FY24 and FY25, excluding Talcher thermal.
- Coal-based feasibility: ~6 GW from coal-based plants is under feasibility and planning.
- Capex trajectory: Standalone capex is ₹22,454 crore for FY23, rising to ₹26,000 crore for FY24, then ₹22,484 crore for FY25 and ₹24,957 crore for FY26, averaging ~₹25,000 crore per annum.
- FY24 commissioning (standalone): Barh Unit #3 (660 MW), North Karanpura Unit #2 (660 MW), Telangana Unit #2 (800 MW), and RE (735 MW), totalling 2,855 MW. Group commissioning adds BIPCL (660 MW), NREL (~2,300 MW), and THDC (1,000 MW), for a group total of 6,810 MW.
- FGD on track: 7 units (2,330 MW) commissioned so far; 129 units (60,940 MW) under construction; Category A deadline December 2024, Category B 2025, Category C 2026. Management expects to meet all deadlines.
- Gas peaking under discussion: The government is asking GAIL to supply gas at a reasonable rate for peaking operations, with gas plants able to go from start to full load in 25 minutes and run for 2-3 hours during peak load. No definitive numbers yet.
Management: "...we expect to open the bid in the month of March itself and award it by April."
Guidance & Commitments
| Commitment | Specifics | Timeline |
|---|---|---|
| Fixed cost under-recovery | Bring down to ₹250 crore | By FY23 end |
| Lara expansion award | Bid opening in March, award by April | April 2023 |
| Singrauli thermal ordering | Capacity ordering targeted | December 2023 |
| Renewable monetisation | Offload 10-20%, process concluded | By March 2023 |
| Renewable run rate | 5-6 GW per year | Starting in 1-1.5 years |
| Nuclear capacity | 2,000 MW from Chutka and Mahi Banswara | By 2032 |
| Nuclear capacity | 4,200 MW | By 2035 |
| Nuclear capacity | ~20,000 MW | By 2050 |
| FGD completion | All units across Category A, B, C deadlines | Dec 2024 / 2025 / 2026 |
| FY24 standalone commissioning | 2,855 MW (Barh, N Karanpura, Telangana, RE) | FY24 |
| FY24 group commissioning | 6,810 MW (incl. BIPCL, NREL, THDC) | FY24 |
| FY24 capex | ₹26,000 crore (standalone) | FY24 |
Key Metrics
| Metric | Q3 FY23 |
|---|---|
| Total Income (standalone) | ₹42,149 cr, +35.26% YoY |
| Total Income (standalone, 9M) | ₹124,685 cr, +39.60% YoY |
| Profit After Tax (standalone) | ₹4,476 cr, +5.42% YoY |
| Profit After Tax (standalone, 9M) | ₹11,524 cr, +8.07% YoY |
| Adjusted PAT | ₹4,424 cr, adjusted profit up 18% YoY |
| Group Total Income (9M) | ₹133,231 cr, +36.97% YoY |
| Group PAT (9M) | ₹12,250 cr, +4.16% YoY |
| Incentive income | ₹125 cr, highest Q3 in last 3–4 years |
| Late payment surcharge | ₹67 cr, 9M total ₹459 cr |
| Fixed cost under-recovery (9M) | ₹548 cr, improved from ₹692 cr YoY; targeting ₹250 cr by FY end |
| Average PLF of coal stations (9M) | 74.45%, national average 63.27%, spread over 11% |
| Standalone gross generation (9M) | 25,500 cr Units, +~12% YoY |
| Group generation (9M) | 29,500 cr Units, +~11% YoY |
| Commercial capacity (Group) | 70,884 MW as on 31 Dec 2022 |
| RE capacity added in FY23 (till 31 Dec) | >1.3 GW |
| RE projects under construction | 4,718 MW |
| Under-construction capacity (Group, all sources) | 18,253 MW (coal 11,280 MW, hydro 2,255 MW, RE 4,718 MW) |
| Capacity addition target FY24 (Group) | 6,810 MW |
| Capacity addition target FY25 (Group) | 4,684 MW |
| Own coal production (9M) | 1.46 cr MMT, ~51% growth YoY |
| Coal materialisation against ACQ (9M) | 98.20%, improved from 97.80% YoY |
| NVVN trading volumes (9M) | 2,200 cr Units, +~24% YoY |
| Average cost of borrowing (9M) | 6.32%, vs 5.95% in 9M FY22 |
| Group CAPEX (9M) | ₹26,058 cr, vs ₹25,064 cr YoY |
| Standalone CAPEX outlay FY23 | ₹22,454 cr, 84% spent in 9M |
| Regulated equity (standalone) | ₹75,449 cr as on 31 Dec 2022 |
| Profit from JVs and subsidiaries (9M) | ₹1,771 cr, vs ₹2,225 cr YoY |
| Dividend income from subsidiaries and JVs (9M) | ₹1,046 cr, vs ₹1,142 cr YoY |
| FGD capacity awarded | ~62,000 MW, capex ₹29,331 cr awarded |
| Nuclear capacity target by 2032 | 2,000 MW, from Chutka (2x700 MW) and Mahi Banswara (4x700 MW) |