Key Takeaways


Profitability Drag: JVs, Finance Costs & Other Expenses

Management: "Late payment surcharge is not our main source of income. It is incidental if these are more of a deterrent rates of recovering the financial cost. So, the low trend is in one sense indicative of a better collection efficiency."

Operational Strength: Generation, Coal & PLF

Management: "The fixed cost under recovery for 9 months is Rs.548 crore, this is much less than the corresponding previous period, which was Rs.692 crore. However, we are targeting to bring it down to a level of Rs.250 crore by FY end."

Nuclear: The New Growth Leg

Management: "By 2050, we will have around 20000 MW capacity in NTPC from nuclear."

Renewables: Pipeline, Monetisation & Run Rate

Management: "We cannot hazard a guess, as far as the quantum is concerned, we are contemplating offloading between 10% to 20%, depending on the response. So, it would be difficult, and it will not be appropriate also to give an expectation here when the bidding process is on within the board."

Thermal Pipeline & Capex

Management: "...we expect to open the bid in the month of March itself and award it by April."

Guidance & Commitments

CommitmentSpecificsTimeline
Fixed cost under-recoveryBring down to ₹250 croreBy FY23 end
Lara expansion awardBid opening in March, award by AprilApril 2023
Singrauli thermal orderingCapacity ordering targetedDecember 2023
Renewable monetisationOffload 10-20%, process concludedBy March 2023
Renewable run rate5-6 GW per yearStarting in 1-1.5 years
Nuclear capacity2,000 MW from Chutka and Mahi BanswaraBy 2032
Nuclear capacity4,200 MWBy 2035
Nuclear capacity~20,000 MWBy 2050
FGD completionAll units across Category A, B, C deadlinesDec 2024 / 2025 / 2026
FY24 standalone commissioning2,855 MW (Barh, N Karanpura, Telangana, RE)FY24
FY24 group commissioning6,810 MW (incl. BIPCL, NREL, THDC)FY24
FY24 capex₹26,000 crore (standalone)FY24

Key Metrics

MetricQ3 FY23
Total Income (standalone)₹42,149 cr, +35.26% YoY
Total Income (standalone, 9M)₹124,685 cr, +39.60% YoY
Profit After Tax (standalone)₹4,476 cr, +5.42% YoY
Profit After Tax (standalone, 9M)₹11,524 cr, +8.07% YoY
Adjusted PAT₹4,424 cr, adjusted profit up 18% YoY
Group Total Income (9M)₹133,231 cr, +36.97% YoY
Group PAT (9M)₹12,250 cr, +4.16% YoY
Incentive income₹125 cr, highest Q3 in last 3–4 years
Late payment surcharge₹67 cr, 9M total ₹459 cr
Fixed cost under-recovery (9M)₹548 cr, improved from ₹692 cr YoY; targeting ₹250 cr by FY end
Average PLF of coal stations (9M)74.45%, national average 63.27%, spread over 11%
Standalone gross generation (9M)25,500 cr Units, +~12% YoY
Group generation (9M)29,500 cr Units, +~11% YoY
Commercial capacity (Group)70,884 MW as on 31 Dec 2022
RE capacity added in FY23 (till 31 Dec)>1.3 GW
RE projects under construction4,718 MW
Under-construction capacity (Group, all sources)18,253 MW (coal 11,280 MW, hydro 2,255 MW, RE 4,718 MW)
Capacity addition target FY24 (Group)6,810 MW
Capacity addition target FY25 (Group)4,684 MW
Own coal production (9M)1.46 cr MMT, ~51% growth YoY
Coal materialisation against ACQ (9M)98.20%, improved from 97.80% YoY
NVVN trading volumes (9M)2,200 cr Units, +~24% YoY
Average cost of borrowing (9M)6.32%, vs 5.95% in 9M FY22
Group CAPEX (9M)₹26,058 cr, vs ₹25,064 cr YoY
Standalone CAPEX outlay FY23₹22,454 cr, 84% spent in 9M
Regulated equity (standalone)₹75,449 cr as on 31 Dec 2022
Profit from JVs and subsidiaries (9M)₹1,771 cr, vs ₹2,225 cr YoY
Dividend income from subsidiaries and JVs (9M)₹1,046 cr, vs ₹1,142 cr YoY
FGD capacity awarded~62,000 MW, capex ₹29,331 cr awarded
Nuclear capacity target by 20322,000 MW, from Chutka (2x700 MW) and Mahi Banswara (4x700 MW)