NTPC Ltd Q3 FY2024 Concall Summary

Source transcript PDF: https://assets.stockscans.in/docs/wvv90z32lbkf6pmbtp40dyx6.pdf

Key Takeaways


Financial Performance


Under-Recovery & Regulatory Outlook

Management: "Under recovery in the third quarter was close to INR256 crores. And overall, it is around INR740 crores, which we should see the reversal during the fourth quarter."

Thermal Capacity: The Big Build-Out


Renewable Energy: Ambition Meets Execution Friction

Management: "First things first, no, we are not happy with the pace of execution, but these are things which are not in our control and now hopefully, we are back on track."

Fuel Security & Coal Mining


Pumped Storage & Green Hydrogen

Management: "Generally, the time taken is two years for DPR and construction period is between five to six years. Totalling, around seven, eight."

Guidance & Commitments

CommitmentSpecificsTimeline
Under-recovery reversalINR740 crore 9M under-recovery to reverse; full-year FY24 to end at INR400-450 croreQ4 FY24
Conventional capacity addition3,580 MW target for FY24By March 2024
Thermal tendering5,600 MW to be tendered (Singrauli 3, Sipat 3, Darlipalli)Q1/Q2 next fiscal year
Thermal tenderingFurther 6,400 MW to be tenderedUp to Q2 FY26
Thermal tenderingRemaining 4,800 MW to be tenderedFY27
Renewable commissioning1 GW to be commissionedBy March 2024
Renewable commissioningClose to another 3 GW to be commissionedNext fiscal year
Renewable commissioningBalance of 7.8 GW under-construction portfolioOver subsequent 24 months
Coal mining production3.4 crore tons for FY24FY24
Coal mining productionAnnual run-rate of 5 crore tonnesWithin 3 years
FGD commissioningFGD for entire operational and under-construction capacityOver next 3 years
Biomass pellet plant22 TPD plant at BhatindaQ4 FY24
Capex (standalone)~INR22,700 croreFY25
Capex (standalone)~INR26,300 croreFY26

Key Metrics

MetricQ3 FY24
Total Income (Standalone)₹40,288 cr, as against ₹42,149 cr in Q3 FY23
PAT (Standalone)₹4,572 cr, increase of 2.14% YoY
Adjusted PAT (Standalone)₹4,468 cr, as against ₹4,424 cr in Q3 FY23
Group PAT (9M FY24)₹14,842 cr, increase of 21.16% YoY
Subsidiaries Profit₹1,516 cr, increase of 17.45% YoY
Regulated Equity (Standalone)₹82,094 cr as on 31 Dec 2023
Average Rate of Interest (9M FY24)6.66%, as compared to 6.32% in 9M FY23
Group CAPEX (9M FY24)₹21,552 cr, as compared to ₹26,058 cr in 9M FY23
Standalone CAPEX Guidance (FY25)~₹22,700 cr
Under Recovery (Disincentive)₹256 cr in Q3, around ₹740 cr in 9M FY24; expected to end FY24 at around ₹400-450 cr
Commercial Capacity (Group)73,874 MW as on 31 Dec 2023
Coal Station PLF (9M FY24)76.40%, as against National Average of 68.51%
Coal Supply62.37 MMT, including 2.15 MMT of imported coal; materialization against ACQ at 95%
Group Coal Production (9M FY24)2.54 crore MMT, growth of over 74% YoY; full-year target of 3.4 crore tonnes intact
Renewable Energy Commissioned3,364 MW; 7,808 MW under construction, 22,747 MW tangible pipeline
Thermal Capacity Addition Pipeline16.8 GW to be awarded in near future, in addition to 10 GW under construction