Key Takeaways


Vadraj Cement Acquisition

Jayakumar Krishnaswamy: "We were very clear that Nuvoco will start this expansion plan the moment we hit our internal target of Rs. 3,500 to Rs. 4,000 crores of debt level. And in between Vadraj happened, and then we did a cost benefit analysis of the value by Vadraj as well as our own investment. We found the Vadraj being very economically attractive for us, and hence we went for it and then successfully bid for it."

Volume & Demand Recovery

Jayakumar Krishnaswamy: "I just want to assure you that we were always committed to premium products. We pride on our ability to sell premium products in the country. I think that's the DNA of the Company and I do not think we will move away from the basic DNA of the organization, even in this quarter we have not moved."

Pricing & Realization

Jayakumar Krishnaswamy: "The only wet blanket in this quarter was prices kind of went to probably three years low in East as well as North... the December end realization was 6% of the quarter realization. So, we ended the quarter very strong."

Cost Performance


Balance Sheet & Debt


New Products & Premiumization


Guidance & Commitments

CommitmentSpecificsTimeline
Vadraj NCLT approvalNCLT process filed; approval expected6 months (optimistic) to 8-9 months (worst case)
Vadraj paymentRs. 1,800 crores paid subsequent to NCLT approvalAround Q3 of this calendar year
Vadraj production startOne mill operationalized first, then clinker lineQ3 FY27
Total capacity post-Vadraj3.1 crore tonnes per annum cement capacityBy Q3 FY27
Vadraj additional capexRs. 900-1,200 crores to make assets fully operationalOver 18-24 months
Vadraj volume ramp0.1 cr tonnes (FY27), 0.2 cr (FY28), 0.3-0.4 cr (FY29)FY27-FY29
Organic volume growth2.1 cr tonnes next year, then +0.2 cr per year for 3-4 yearsFY26 onward
Net debt targetBelow Rs. 4,000 croresBy end of this calendar year
Jajpur railway sidingOperational; cement movement into South Bengal via rakeQ1 FY26
Sonadih railway sidingTarget 5 rakes per day, eliminating road clinker movementOngoing
Q4 cost savings~Rs. 75 per tonne (up from Rs. 54 at nine months)Q4 FY25

Key Metrics

MetricQ3 FY25
Revenue₹2,409 cr
EBITDA₹258 cr
Volume0.47 crore tonnes, +16% YoY
Cement realization-3.6% QoQ; December exit realization 6% above quarter average
Power and fuel cost per tonne-6% QoQ
Blended fuel cost₹1.45 per million cal, lowest in 13 quarters
Distribution cost per tonne-3% QoQ
Project Bridge 2.0 cost savings₹54 per tonne YTD, upwards of ₹50 per tonne
Premium product share39% of volumes
Trade share71% of volumes, unchanged QoQ
Lead distance327 km, down 3 km QoQ
Road vs rail mix64% road, 36% rail; road was 60% in Q2
Fuel mixCoal 42%, petcoke 48%, AFR 10%; AFR was 8% in Q2
Net debt₹4,350 cr, -₹183 cr YoY and -₹151 cr QoQ
YTD capex₹299 cr; Q4 expected ₹50–60 cr
Vadraj acquisition bid amount₹1,800 cr; additional spend ₹900–1,200 cr over 18–24 months
Vadraj acquisition cost~\$60 per tonne
Post-acquisition capacity target3.1 crore tonnes per annum by Q3 FY27 (East 1.9, North 0.6, West 0.6)
Audited emission rate (FY24)457 kg CO2 per tonne of cementitious material