Cost Environment

Jayakumar Krishnaswamy: "If petcoke prices were to go to \$215, the cost will go to INR 3 per million KCal. It will be a phenomenal increase, but we are in a pretty comfortable position."

Pricing & Realization


Expansion Projects & Capacity

Jayakumar Krishnaswamy: "We took a conscious call to slightly delay the East expansion from Q3, Q4 FY27 to Q1, Q2 FY28. So, it’s just timing and a sequencing issue, however very much it is there."

Vadraj (Gujarat) Economics


Balance Sheet & Capex

Jayakumar Krishnaswamy: "Our stated position has been that we are comfortable anywhere between INR 3,500 crores to INR 4,000 crores, and our commitment is to find a way to get the net debt about two times EBITDA."

Demand & Regional Dynamics

Jayakumar Krishnaswamy: "My inference is if you have a back-to-back year where things go wrong either in monsoon or in drought, then the demand gets impacted to 5% kind of a number. That's what the historical data says. But I'm assuming that doesn't happen next year."

Guidance & Commitments

CommitmentSpecificsTimeline
Q3 fuel costINR 1.8/kcal, translating to INR 70–80/ton energy cost increase vs Q2Q3 FY27
Q3 net cost inflationINR 100–120/ton QoQ increaseQ3 FY27
Q3 realizationAverage INR 20/ton price increase to defray cost increaseQ3 FY27
Q4 cost increase (worst-case)Further INR 70–80/ton vs Q3Q4 FY27
Surat capacity utilization50–60% in Q4 FY27, 70–75% next yearQ4 FY27 / FY28
Gujarat annualized volume2 MTPA by Q4 FY27, from ~1.5 MTPA currentlyQ4 FY27
North capacity release~0.1 crore tons released from Q4 onwardQ4 FY27 onward
Kutch clinker availabilityClinker from Kutch by end of Q3; jetty operational by first week of DecemberQ3/Q4 FY27
FY27 capexINR 1,200 croresFY27
FY28 capexINR 800–900 croresFY28
East expansionDelayed to Q1/Q2 FY28Q1/Q2 FY28
Vadraj EBITDA parityGujarat EBITDA to match North EBITDA; Vadraj EBITDA/ton to match Nuvoco all-India blended EBITDA/tonYear 3 (FY29, possibly FY28 Q4)
Tax regime decisionEvaluation of old-to-new regime transitionNext 3–4 months
Year-end net debtExpected to return to March FY27 rangeMarch FY27

Key Metrics

MetricQ2 FY27
Volume growth9% YoY
Revenue growth~14% YoY
EBITDA growth11% YoY
Premium product share45%, historic high
Trade mix75%
Blended cement ratio83%, up from 82% in Q1
Fuel cost per million kcal₹1.59, up from ₹1.52 in Q1; energy cost of ₹1,080 per ton
Fuel mixCoal 66%, petcoke 27%, AFR 6%
CK ratio1.75, up from 1.73 in Q1
Road:rail share64:36, unchanged from Q1
Lead distance332 km, up from 328 km in Q1
Net debtCrossed ₹5,000 cr, up ~₹500 cr from March 2026 due to petcoke stocking and front-ended capex
H1 FY27 capex₹780 cr, versus original plan of ~₹450–460 cr
Full-year FY27 capex guidance₹1,200 cr, of which ₹1,000 cr for Vadraj, ₹50 cr for Viramgam
FY28 capex outlay₹800–900 cr, including ~₹800 cr for Kutch, Surat, Sachana, East debottlenecking
Surat grinding unit capacity utilization50–60% expected in Q4 FY27, 70–75% next year
Q3 FY27 expected fuel cost per million kcal₹1.8, translating to ₹70–80 per ton increase in energy cost QoQ
Q3 FY27 expected cost inflation QoQ₹100–120 per ton, driven by power and fuel, packing bags, and busy season surcharge
Q3 FY27 price increase taken~₹20 per ton average across North and East in October
Q3 FY27 net profitability improvement QoQ₹70–80 per ton, if prices and costs hold (per an analyst's math, which management did not confirm)
1H FY27 effective tax rate41.6% on reported basis, due to old tax regime and MAT credit unavailability