Key Takeaways
- Launches slipped, not demand: Q3 pre-sales hit a 9-quarter low solely because management kept perfecting product designs, pushing launches into Q4 and Q1 FY27. Pricing power held firm with increases in Goregaon and Borivali.
- A self-inflicted miss, owned candidly: The chairman called it “a missed quarter and a missed opportunity”, acknowledging launches could have landed in Q3. The delay was about design ambition, not approvals or market conditions.
- The pipeline is now loaded for a spillover year: Multiple towers across Goregaon, Borivali, Thane and possibly Gurugram are queued for Q4, with Worli and Peddar Road following. Management calls FY27 “a much bigger year” on the back of these spillovers.
- Thane is being positioned as the next Goregaon: A mall, JW Marriott hotel and an international school are planned, and new tower launches will replenish lower-floor inventory that sells fastest.
- What to watch next quarter: Whether the 4–5 promised Q4 launches actually execute, whether the Gurugram project makes its “touch and go” Q4 deadline, and whether the three large Mumbai BD deals close as guided.
The Launch Miss: What Happened and Why
- Product perfection, not approvals, caused the slip: Management spent extra time refining designs: Gurgaon deck depth moved from 8 ft to 10 ft to 12 ft, and Peddar Road replaced car ramps with elevators. These changes consumed the quarter.
- The miss was in management’s control: Approvals were not the bottleneck for the core Mumbai launches; the company simply chose to keep perfecting. The chairman stated the launches “could have easily” landed in Q3.
- Pricing power was intact despite the weak print: Goregaon and Borivali saw price increases with no buyer resistance, and higher floors sold at higher prices. Thane prices were kept stable.
- Thane inventory mix amplified the pre-sales number: Lower and middle floors in high-rises sell first on cost advantage; with those largely absorbed, remaining higher-floor inventory moved slower. New tower launches will restock the faster-selling lower floors.
Vikas Oberoi: “We just got it wrong to be very honest, we just got it wrong. We could have easily got these in like maybe at least in the third quarter. But like I said we kept perfecting the product which will of course pay us and help us in the long run and all of that, but it's a missed quarter and a missed opportunity.”
Launch Pipeline: What Is Coming and When
- Q4 launches are “very much in our control”: One tower each in Goregaon and Borivali are confirmed for Q4, along with two towers in Thane (Forestville and Pokhran Road). Peddar Road is also coming up.
- Gurugram is the swing factor: Plan approvals are expected in 30–40 days, after which the company will immediately apply for RERA and launch. Management calls it “touch and go” for Q4; worst case slips to Q1 FY27.
- Worli (Adarsh Nagar) is close but likely Q1: IOD is expected “any day” with RERA to follow; if everything lines up perfectly it could still make Q4, but the realistic timeline has shifted to Q1 FY27.
- Nepean Sea Road is a 9-month story: The development agreement is signed, but management expects at least nine months before anything is visible on the ground.
- Sky City Mall nears full occupancy: Currently at 56% leased, with three large leases signed but agreements not yet finalized. Management expects 100% occupancy within two more quarters. Footfalls are already double those at Oberoi Mall, and an Apple store opens in February.
Thane: Building the Next Goregaon
- The ambition is explicit: Management is “trying to build another Goregaon out of that”, replicating the integrated township model that worked in the western suburbs.
- Social infrastructure is the next phase: A mall, a JW Marriott hotel and an international school designed by a Boston firm are the next planned developments, positioning the location as “Oberoi Garden City Thane.”
- New tower launches will support sustenance sales: With lower-floor inventory in existing towers largely sold, fresh launches will provide the cost-advantaged units that drive volume in high-rise projects.
Vikas Oberoi: “We're trying to build another Goregaon out of that.”
Business Development and Land Pipeline
- Three large Mumbai deals near closing: Management expects to announce them either this quarter or in Q1 FY27. No further detail was provided on location or scale.
- Bandra land parcel won via bid: The company emerged as the top bidder for an 11-acre land parcel in Bandra, adding a premium Mumbai micro-market to the pipeline.
- Versova update was requested but not answered: An analyst specifically asked for a Versova update; management addressed the other BD questions but remained silent on this project.
Financials and One-Offs
- Gratuity charge was a true-up, not a recurring cost: The ₹23 cr employee expense captures gratuity liability from each employee’s joining date to the present. Management described it as a ballpark maximum that may reduce once the regulation is finalized.
- Eternia received full occupation certificate: This milestone unlocks revenue recognition for the completed project.
- Worli commercial work has resumed: Excavation was done previously; site securing has restarted and work is proceeding at a brisk pace.
Demand and Market Questions
- Management pushed back on slowdown fears: When an analyst flagged Q3 pre-sales as the lowest in nine quarters and asked about demand softening linked to equity market declines, management attributed the entire drop to missed launches and pointed to successful price increases as evidence that demand is intact.
- No change in municipal policy post-elections: An analyst asked whether recent municipal elections had altered FSI norms or approval processes. Management stated flatly: “Frankly, there is no change.”
Guidance & Commitments
| Commitment | Specifics | Timeline |
|---|---|---|
| Goregaon tower launch | One tower launch | Q4 FY26 |
| Borivali tower launch | One tower launch | Q4 FY26 |
| Thane launches | Two towers (Forestville and Pokhran Road) | Q4 FY26 |
| Gurugram launch | Plan approval in 30–40 days, then RERA, then launch | Q4 FY26 (touch and go); worst case Q1 FY27 |
| Sky City Mall occupancy | 100% leased (LOIs done, agreements pending) | Within two quarters |
| Three large Mumbai BD deals | Announcement of deal closure | This quarter or Q1 FY27 |
| Nepean Sea Road visibility | Anything visible on ground | At least 9 months |
| FY27 outlook | Spillovers from FY26 make it “a much bigger year” | FY27 |
Key Metrics
| Metric | Q3 FY26 |
|---|---|
| Pre-sales | Lowest over the last 9 quarters, attributed to launch delays, not demand weakness |
| Revenue potential per tower (Goregaon/Borivali) | More than ₹3,000 crores per tower |
| Tower size (Goregaon/Borivali) | 6 lakh to 8 lakh square feet per tower |
| Commerz II occupancy | About 100% |
| Commerz III occupancy | 90% |
| Oberoi Mall occupancy | 99% |
| Sky City Mall leasing | 56% currently; 3 large leases signed, agreements pending |
| Sky City Mall footfalls | Double of Oberoi Mall within first 6 to 9 months of operation |
| Borivali apartment pricing | Beyond ₹50,000 per square foot on carpet for some apartments |
| Goregaon ready apartment pricing | Upward of ₹50,000 per square foot on carpet; some at ₹60,000, a 30% to 35% premium over market |
| Operating cash flow impact (FSI payments) | Close to ₹300 crores paid for FSI and related acquisition rights |
| One-off employee expenses (exceptional item) | ₹23 crores, true-up for gratuity for entire employee tenure to date |
| FY27 launch outlook | Very promising, with multiple launches spilling over from FY26; expected to be a much bigger year |