Key Takeaways
- Strong quarter, production still the soft spot: Standalone gross revenue up 33% YoY and PAT up 57% YoY on improved realizations, while oil and gas output moderated marginally YoY on supply chain, weather and customer off-take constraints.
- New well gas pricing is now a material earnings driver: INR 7,050 crore of H1 revenue from new well gas, an incremental INR 2,859 crore versus APM pricing, over 34% of nomination gas revenues.
- KG-DWN-98/2 is the clearest disappointment: Oil stuck at ~19,000 bpd and gas well connections delayed to Q4; management admits the reservoir is "much more complex" than originally envisaged and offers no timeline for a ramp-up.
- International portfolio is quietly turning: Mozambique drawdown expected next month, Venezuela has OFAC clearances and a new off-take structure, Sakhalin is back at ~183,000 bpd with no dividend repatriation restriction.
- What to watch next quarter: Whether KG-DWN-98/2 gas connections actually land in Q4, the pace of Mozambique drawdown, and any concrete Venezuela agreement signings.
Production & The KG-DWN-98/2 Problem
- Output broadly stable, not growing: Oil and gas production was stable sequentially but moderated marginally YoY, hit by supply chain disruptions affecting projects including DUDP, weather-related offshore challenges, and temporary customer off-take constraints including the OTPC facility shutdown in Tripura.
- FY27 and FY28 guidance is modest: Management expects to close FY27 at ~39 MMT oil and oil equivalent of gas, with FY28 only 0.5 to 1 MMT higher.
- KG-DWN-98/2 oil is stalled: Oil production sits at ~19,000 bpd while management studies intervention options and costs; no timeline was given for a ramp-up communication.
- KG-DWN-98/2 gas is delayed, not lost: Three wells are now expected to connect in Q4, adding ~1.5 MMSCMD, after monsoon and a recent disturbance pushed the timeline.
- The reservoir itself is the issue: Management flagged "reservoir surprises, subsurface surprises" and conceded the system is far more complex than originally envisaged, which caused the dip along the way.
Bhaskar Chowdary Nettem: "It's definitely a much more complex system than what we had originally envisaged, and that is also a reason why we had a small dip along the time. But at this point in time, we are still working on several concepts, and we hope to make the runway clear on this matter."
TSP with BP: Early Days, Green Shoots
- Mumbai High showing early promise: Management pointed to green shoots in gas output from the Bombay High area, with pipeline replacements also being taken up aggressively.
- BP has suggested positive interventions: Infill drilling is among the interventions BP has proposed to enhance production.
- Compensation structure limits near-term visibility: The first two years of the TSP are fixed-fee, so BP's performance-linked compensation only starts April 2027; management did not share specific production uplift numbers or baseline decline rates.
- TSP expansion is already underway: The program for remaining western offshore assets, Neelam and Bassein and Satellite fields, was awarded last quarter with teams mobilized and work plans being finalized.
- Gas output is the early win: Management gave a 7-8% increment on gas from Bombay High versus last year but declined to provide absolute production numbers, saying several things must stabilize before attribution.
Bhaskar Chowdary Nettem: "There are some green shoots in gas output from the Bombay High area, and simultaneously some pipeline replacements and things have also been taken up on a--on an aggressive mode."
International Portfolio: Mozambique, Venezuela, Sakhalin
- Mozambique is moving to drawdown: Force majeure was lifted last year, financing is tied up, and the Mozambique government's sovereign guarantee has been approved by cabinet; drawdown is expected to start next month onward.
- Venezuela has a new structure: ONGC has necessary approvals and OFAC clearances for new operating arrangements, with agreements expected in place in the next three to six months. ONGC will be sole operator of San Cristobal and joint operator in Petro Carabobo.
- The off-take model changes the recovery path: Under the new arrangement, ONGC will have off-take rights, operate the project, sell the produce, discharge fiscal responsibilities to the Government of Venezuela, and keep the rest; management expects to receive dues through this route next year.
- Old Venezuela dues remain stuck: The US$500-odd million of dividend stuck for years has not been received; the situation is where it was earlier.
- Sakhalin is back to pre-crisis levels: Re-entered in December 2025, consolidated in OVL and ONGC Group accounts, with average H1 production of 183,000 barrels per day, almost the same level as before the 2022 crisis.
- Sakhalin dividends can come home: No restriction exists today on repatriating dividends from Sakhalin; once the accounting year closes and a dividend is declared, it can be brought to India.
- Vankorneft funds are cleared: The dividend stuck in Russia was used to meet the abandonment fund liability in Sakhalin; no amount is stuck in Russia today.
Anupam Agarwal: "In the new arrangement, we will have off-take rights. We will be operating the project, we will off-take the produce, we will sell, and we will discharge various fiscal regime related responsibilities to the Government of Venezuela, and rest will belong to us."
OPaL & Petrochemicals
- OPaL turned EBITDA-positive: Q2 EBITDA of INR 147 crore came from a petchem price rebound, though feedstock prices also rose due to the Hormuz situation.
- Financing cost is structurally lower: Interest cost has declined from ~INR 2,000 crore last year after capital restructuring and the INR 18,000 crore infusion.
- Ethane sourcing is the long-term fix: ONGC Group is pursuing ethane from the USA with two ships under construction for delivery by early 2029, and long-term ethane price tie-ups are in discussion.
- New marketing entity is directionally positive, not yet quantified: ONGC Petrochemicals Marketing Limited was incorporated on 7th October 2026 as a single integrated marketing platform for ONGC, OPaL and MRPL petrochemical products; management said it is difficult to quantify synergy benefits at this stage.
Exploration & New Projects
- Two major western offshore projects awarded: Combined investment of ~INR 11,800 crore covering MB/OSN-2005/1, SD-4, BS-17, and additional development of Ratna-1 and Neelam-14, with completion expected over the next two to two and a half years.
- Samudra Manthan is live but rig-constrained: Detailed operational guidelines for the national offshore exploration scheme were issued during the quarter; 4 wells are planned this year and up to 13 next year subject to rig availability in a tight deepwater market.
- Deepwater rigs are being added: One deepwater rig is operational in the Mahanadi basin, and a second is expected to be mobilized during this financial year.
- Gas discoveries are accumulating: Gas was encountered in Mahanadi offshore basin exploratory drilling, and gas discoveries were made in the Silchar region, with monetization expected via the IGGL gas pipeline network.
- DUDP and DSF 2 are progressing: About half the DUDP wells are done with a few more under drilling, and volumes should start incrementing; DSF 2 construction is in progress with volumes expected towards the end of this financial year.
Anupam Agarwal: "You know the deepwater market is a rigged market right at this moment. So we are looking at the rigs; if we get those rigs, we will be completing 13 wells next year."
Financials & Capital Returns
- Earnings quality was mixed: Higher other expenses included an INR 1,861 crore provision for terminal excise duty receivable under litigation, taken out of conservatism, partially offset by an INR 609 crore opex decrease and INR 625 crore exchange loss decrease.
- Tax and depreciation moved in opposite directions: Lower corporate tax came from higher dividend earnings qualifying for 80M benefit, while higher depreciation reflected an impairment provision for exploratory wells carried for a longer period.
- Consolidated PAT was strong: INR 18,535 crore, driven by HPCL's rebound on improved GRMs and strong OVL and MRPL performance.
- Dividend policy is unchanged: The board declared a highest-ever interim dividend of 160% (₹8/share), total outgo INR 10,064 crore; management plans to continue paying around 40% of profits with no change in policy.
- Capex run-rate is steady: Management plans to continue incurring about $3.5 to $4 billion per year.
Anupam Agarwal: "We are not seeing that way. We are not seeing that way. We are going to maintain our dividend policy the way we have maintained in the past; there is no change in the dividend policy."
Guidance & Commitments
| Commitment | Specifics | Timeline |
|---|---|---|
| FY27 production | Close at ~39 MMT oil and oil equivalent of gas | FY27 end |
| FY28 production | 0.5 to 1 MMT higher than FY27 | FY28 end |
| KG-DWN-98/2 gas | Three wells connected, adding ~1.5 MMSCMD | Q4 FY27 |
| Mozambique drawdown | Drawdown on project financing to start | Next month onward |
| Venezuela agreements | New operating arrangements in place; ONGC sole operator of San Cristobal, joint operator in Petro Carabobo | Next 3-6 months |
| Venezuela dues recovery | Dues received through off-take route | Next year |
| Samudra Manthan drilling | 4 wells this year; up to 13 wells next year subject to rig availability | FY27 / FY28 |
| Western offshore projects | Two awarded projects completed | Next 2-2.5 years |
| DUDP volumes | Start incrementing volumes and stabilize | FY27 |
| DSF 2 volumes | Start getting volumes | End of FY27 |
| Capex | Continue at $3.5-4 billion per year | Ongoing |
| Dividend policy | Maintain ~40% payout, no change | Ongoing |
Key Metrics
| Metric | Q2 FY27 |
|---|---|
| Standalone gross revenue | ₹43,875 crore, up over 33% YoY |
| Standalone PAT | ₹15,489 crore, up over 57% YoY |
| Consolidated PAT | ₹18,535 crore |
| Average crude realization, nomination fields | US$92.33 per barrel |
| H1 FY27 PAT | ₹32,522 crore, highest-ever H1 profit after tax |
| Interim dividend | 160% (₹8 per share), total outgo ₹10,064 crore, highest-ever |
| FY27 production guidance | ~39 MMT oil and oil equivalent of gas |
| FY28 production guidance | 0.5 to 1 MMT higher than FY27 |
| KG-DWN-98/2 oil production | ~19,000 barrels per day |
| KG-DWN-98/2 gas production | ~2 MMSCMD in Q2, with ~1.5 MMSCMD additional expected in Q4 |
| OPaL EBITDA | ₹147 crore positive in Q2; ₹90 crore in H1 |
| OPaL PAT | ₹494 crore negative in Q2; ₹1,100 crore negative in H1 |
| H1 FY27 new well gas revenue | ₹7,050 crore, incremental ₹2,859 crore vs APM regime, over 34% of nomination gas revenues |
| Mozambique project investment | US$7 billion invested to date, ~49% completion achieved |
| Sakhalin average production, H1 | 183,000 barrels per day |
| Samudra Manthan wells planned | 4 wells this year, up to 13 wells next year subject to rig availability |
| ONGC annual capex | US$3.5 to 4 billion per year, plan to continue |
| Bombay High gas incremental | ~7% to 8% on a day basis |
| Industry standard decline rate | 6% to 8% on average |